Decision Model of Construction Errors Management Based on Modular Method Construction Process  

Shin, HyunKyu (School of Architecture & Architectural Engineering, Hanyang University ERICA)
Kim, SuYoung (SAMSUNG DISPLAY Construction Planning Group)
Ahn, YongHan (School of Architecture & Architectural Engineering, Hanyang University ERICA)
Publication Information
Korean Journal of Construction Engineering and Management / v.18, no.6, 2017 , pp. 98-108 More about this Journal
Abstract
Recently, the development of middle and high-rise building technology using modular construction method has emphasized the importance of site construction error management. The modular construction method is very limited to adjust the construction error in the field because of the factory production characteristics. Therefore, in order to prevent the construction error in advance, a management plan reflecting the characteristics of the modular construction method is required, and it is important to make the decision of the construction participant at each stage. This study analyzed the factor of construction error of modular construction and suggested a decision support model for construction error management based on construction process. The result of this study is expected to be a guideline for the modular construction participant to derive the construction error management plan.
Keywords
Modular Construction; Modular Method; Construction Errors; Errors Management; Decision Model;
Citations & Related Records
Times Cited By KSCI : 7  (Citation Analysis)
연도 인용수 순위
1 Ahn, Y. S. (1990). "A Field Survey & Analysis of Physical Deviations of Concrete Structures in Apartment Houses -I. Focus on Choosing Element & Measuring Method-" Journal of the Architectural Institute of Korea, 6(4), pp. 271-279.
2 Ahn, Y. S. (1996). "A Study on the Dimensional Tolerance analysis for Establishing Component- Systematized Building Production" Journal of the Architectural Institute of Korea, 12(2), pp. 209-216.
3 Ahn, S. H. (2015). "A Case Study of the Risk Identification in Construction Project" Korean Journal of Construction Engineering and Management, KICEM, 11(2), pp. 74-82.   DOI
4 Aleshin, A., and Dworatsch, S. (1997). "Risk Management of Joint of Joint Venture Construction Projects of Foreign Coorperation in Russia"PMI 28th Annual Seminars & Symposium, PMI, pp. 221-226.
5 Choi, J. H., and Ryu, H. G. (2015). "Application and Effects Analysis of BIM(Building Information Modeling for Construction Management of a Construction Field" Journal of the Korea Institute of Building Construction, 15(1), pp. 115-121.   DOI
6 Chun, J. Y., and Oh, S. J. (2003). "Constitutional Directions of Decision Suppert Process for Cooperative Design in Architectural Design Phase" Journal of the Korea Institute of Building Construction, 19(11), pp. 173-180.
7 Harrell, T. J., Pinon. J. P., and Shane, C. D. (2016). "Building Enclosure Design for Modular Construction" Proceedings of the 3rd Residential Building Design & Construction Conference, pp. 12-28.
8 International Atomic Energy Agency (IAEA) (2015). Development and Implementation of a Process Based Management System, Nuclear Energy Series Report, pp. 4-12.
9 Jaafari, A. (1994). "Total Project Risk Management Aided by Information Systems" 12th Internet World Congress on Porject Management, Proceedings. 2, pp. 311-317.
10 Johnsson, H., and Meiling, J. H. (2009). "Defects in offsite construction : timber module prefabrication" Construction Management and Economics, 27(7), pp. 667-681.   DOI
11 Joseph, M. S. (2012). A Case Study Approach to Identifying the Constraints and Barriers to Design Innovation for Modular Construction (Master of Science in Architecture), Virgina Polytechnic Institute and State University, Blacksburg, Virgina.
12 Kang, K. I., and Kim, J. Y. (2001). "A Study on Cause of Faulty Work in Korean Apartment Housing - Focused on the Form Works and Concrete Works" Journal of the Architectural Institute of Korea Structure & Construction, 17(2), pp. 121-128.
13 Lawson, R, M., and Richards, J. (2010). "Modular Design for High-rise Buildings" Proceedings of the Institution of Civil Engineers, 163(3), pp. 151-164.
14 Lee, J. S., and Chun, J. Y. (2010). "Decision Making Process for Alternative Selection of Proper Design Change in Construction Project" Korean Journal of Construction Engineering and Management, KICEM, 11(2), pp. 74-82.   DOI
15 Mootanah, D. P. (1997). "A Holistic Framework for Managing Risks in Construction Projects" PMI 28th Annual Seminal & Symposium, PMI, pp. 1056-1062.
16 Lawson, R, M., Ogden, R. G., and Goodier, C. (2014). Design in Modular Construction. 1st, Taylor & Francis Group, United Kingdom, pp. 11-14.
17 Matthew, S. G. (1989). A Quality Control Program Analysis for Modular Housings (Masters of Engineering), The Pennsylvania State University, State College, Pennsylvania.
18 Mayra, L. (1994). A review and analysis of modular construction practices (Masters of Science in Civil Engineering), Lehigh University, Bethlehem, Pennsylvania
19 Sacks, R., Eastman, C. M., and Lee, G. (2004). "Process Model Perspectives on Management and Engineering Procedures in the Precast/Prestressed Concrete Industry" Journal of Construction Engineering and Management, 130(2), pp. 206-215.   DOI
20 Shin, D. W., Shin, Y. S., and Kim, G. H. (2015). "Analysis on Risk Factors of Reactor Containment Building Construction using analytic Hierarchy Process" Journal of the Korea Institute of Building Construction, 15(4), pp. 425-431.   DOI
21 Shin, H. K., and Ahn, Y. H. (2016). "Modular Building Construction Process Development by Benchmarking International Best Practices" Korean Journal of Construction Engineering and Management, KICEM, 17(6), pp. 3-12.   DOI
22 SKANSKA (2014). "Skanska Termination Letter Atlantic Yards B2 Project" (April. 22, 2016)
23 Sorri, J., Kahkonen, K., and Rannisto, J. (2013). "Construction Business with Innovative Cellular Structures, Modules and Buildings" Proceeding of the 19th CIB World Building Congress 2013, Number : 245.
24 Zavadskas, E. K., Turskis, Z., and Tamositiene, J. (2010). "Risk Assessment of Construction Projects" Journal of Civil Engineering and Management, 16(1), pp. 33-46.   DOI
25 Yoon, S. C., Jee, N. Y., and Choi, k. B. (2010). "Field Survey on the Construction Errors for the Members of Reinforced Concrete Structures" Korean Journal of Construction Engineering and Management, KICEM, 16(1), pp. 15-23.
26 Yoon, Y. S., Suh, S. W., Park, M. S., and Jang, M. H. (2008). "Construction Process based Schedule Risk Management System" Korean Journal of Construction Engineering and Management, KICEM, 9(4), pp. 101-110.