A Study on Standard Construction Process Management System for Prediction of Proper Construction Period of Subsea Tunnel  

Bae, Keunwoo (Department of Construction Management, Hyeon-In PCM)
Publication Information
Korean Journal of Construction Engineering and Management / v.18, no.4, 2017 , pp. 36-47 More about this Journal
Abstract
As a typical domestic subsea tunnel construction the Gadeok subsea tunnel applying the method of immersed tunnel has been completed and the Boryeong-Taean subsea tunnel is under construction using NATM. The high-speed railway subsea tunnels between the Honam and Jeju are under consideration, and the feasibility of constructing subsea tunnels with Japan and China is also under consideration. However, it is difficult to provide the process plan information for the construction work such as the analysis of the feasibility of the subsea tunnel and the prediction of the proper construction period because there is no case of domestic construction for it applying the shield TBM method. Due to economic and other reasons, government organizations are reluctant to apply the shield TBM, and there is lack of data on the construction process management field using the shield TBM method. Therefore, a standard construction process management system for the subsea tunnel is needed to analyze the feasibility of the subsea tunnel and to predict the proper construction period. By presenting the standard construction process management system of subsea tunnels such as WBS, Network Diagram, and construction period calculation model, I hope to contribute technically and economically to future subsea tunnel projects.
Keywords
Standard Construction Process Management System; Prediction of Proper Construction Period of Subsea Tunnel; Work Breakdown Structure(WBS) of Subsea Tunnel;
Citations & Related Records
Times Cited By KSCI : 8  (Citation Analysis)
연도 인용수 순위
1 Baek, S. H., and Moon, H. K. (2003). "Development and Application of the Assessment System of TBM Tunnelling Procedure" Tunnel and underground space, 13(6). pp. 455-464.
2 Cho, M. S., Woo, D. C., Kim, K. G., and Lee, J. M. (2003). "Applicability Analysis of Empirical Methods for the Calculation of TBM Advance Rate" Tunnel and underground space, 13 pp. 260-269.
3 Choi, J. J., and Park, H. T. (2014). "Analysis of Monthly Excavation Length Depending on Ground Condition and TBM Diameter" Journal of the Korean Society of Disaster Information, 23 pp. 141-150.
4 Choi, S. B. (2010). "Undersea Tunnel Cases and Issues and Suggestions on the Honam-Jeju Undersea High-Speed Railway" Korea Logistics Review, 20(5), pp. 243-268.
5 Design practice tips of the national highway construction work (2016). MOLIT (Ministry of Land, Infrastructure and Transport).
6 Jeong, W. T. (2014). "Study on the Improving drilling rate by analyzing in Korea TBM construction site" Kyonggi Univ., pp. 18-37.
7 Kim, B. S., and Chun, J. K. (2005). "A Study on Estimation Model of Construction Duration for Public Construction" Korean Journal of Construction Engineering and Management, KICEM, 6(6), pp. 142-151.
8 Lee, S. W., and Woo, S. K. (2008). "Productivity Improvement by Application of Simulation based Tunneling Operation Planning Model - focused on NATM" Korean Journal of Construction Engineering and Management, KICEM, 9(5), pp. 127-136.
9 Kim, K. C. (2009). "Sheild TBM Design and Construction Case on Han River passage section of Bundangline" Korea Rail Network Authority, Korea railway technology, 27, pp. 56-62.
10 Lee, J. W. (2009). "A study of relevant model of information management system based on business process for embodying BPM on construction company" Korean Journal of Construction Engineering and Management, KICEM, 10(6), pp. 13-27.
11 Park, H. T. (2012). "Analysis of Standard Cost and the Construction Period Applied TBM Excavation Method" Journal of the Korean Society of Disaster Information, 18, pp. 319-327.
12 Park, H. T., and Lee Y. k. (2013). "Analysis of Standard Construction by TBM Diameter Through the Rock Scenario Models in the Field" Journal of the Korean Society of Disaster Information, 9(2). pp. 195-205.
13 Shin, J. Y. (2009). "Korea Rail Network Authority, Successful penetration of tunnel in Han river for the first time in Korea" Press Relsease of the Korea Rail Network Authority, pp. 1-3.
14 Choi, S. B., Lee, S. D., Kim, H. W., and Jeon, S. K. (2014). "Review of Subaqueous Tunneling Case Histories" Tunnel and underground space, 24(2), pp. 120-130.   DOI
15 MOLIT, KICT (2017). "2017 Standard of construction estimate" MOLIT (Ministry of Land, Infrastructure and Transport), KICT (Korea Institute of Civil Engineering and Building Technology), pp. 268-269.