Cause Analysis of Cost Overruns in International Infrastructure Project Conducted by Korean Contractors  

Jung, Wooyong (Department of Civil & Environmental Engineering, Yonsei University)
Han, Seungheon (Department of Civil and Environmental Engineering, Yonsei University)
Publication Information
Korean Journal of Construction Engineering and Management / v.18, no.3, 2017 , pp. 105-116 More about this Journal
Abstract
In recent years, large Korean construction companies have suffered serious losses in their overseas business. Many practitioners and researchers have analyzed causes of cost overrun in these projects. However, these arguments have not been empirically verified based on acutal project cases. This study investigated cost overrun rate, contingency, allowance, predicted risk before bidding, and actual and residual risk after award in the 67 international infrastructure projects conducted by 13 large construction companies. The causes of cost overruns are derived as follows. First, they identified the possibility of cost overrun to some extent before the bidding, but did not reflect the enough risk money to bid price. In particular, this behavior was more severe in badly cost-overrun projects. Second, the causes of cost overrun were more influenced by external environmental risk than internal capability risk. However, the internal risk in badly cost-overrun projects was relatively high compared to cost-underrun projects. Third, badly cost-overrun projects failed to mitigate risk. However, cost underrun projects were affected more by low exterior risk conditions than by well mitigated risk. This study provides more informed knowledge in controlling project costs in international infrastructure projects.
Keywords
Cost Overrun; Risk; Contingency; Allowance; International Infrastructure Project;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Han, S. H., Kim, D. Y., and Kim, H. (2007). "Predicting profit performance for selecting candidate international construction projects" Journal of Construction Engineering and Management, 133(6), pp. 425-436.   DOI
2 Han, S. H., Sun, S. M., Park, S. H., and Jung, D. Y. (2006). "The hierarchical structures of cause-and-effect relationships on the profit factors in overseas construction project" Korean Journal of Construction Engineering and Management, KICEM, 7(5), pp. 64-76.
3 Hastak, M., and Shaked, A. (2000). "ICRAM-1: Model for international construction risk" Journal of Management in Engineering, 16(1), pp. 59-69.   DOI
4 Jang, W., Yang, H. B., and Han, S. H. (2014). "Development of evaluation system for overseas business capability of construction firms" Journal of The Korean Society of Civil Engineers, 34(3), pp. 977-987.   DOI
5 Jung, W. and Han, S. (2017). "Which risk management is more crucial to control project cost?" Journal of Management in Engineering, In press, DOI: 10.1061/(ASCE)ME.1943-5479.0000547.   DOI
6 Kim, B. Y. (2016a). "Financial performance of large construction companies depends on cost management capability" The Bell, (Mar. 11, 2016).
7 Kim, H. J. (2016b). "Checking external variables related to overseas construction" K-build Journal, 16(6), pp. 5-13.   DOI
8 Knight, K., and Robinson Fayek, A. (2002). "Use of fuzzy logic for predicting design cost overruns on building projects" Journal of Construction Engineering and Management, 128(6), pp. 503-512.   DOI
9 Lee, J. K. (2008). "Cost overrun and cause in Korean social overhead capital projects: Roads, rails, airports, and ports" Journal of Urban Planning and Development, 134(2), pp. 59-62.   DOI
10 Love, P. E., Wang, X., Sing, C. P., and Tiong, R. L. (2012). "Determining the probability of project cost overruns" Journal of Construction Engineering and Management, 139(3), pp. 321-330.   DOI
11 Nunnally, J. C. (1978). Psychometric Theory, NY: McGraw-Hill.
12 Part, P. S. and Kim Y. S. (2015). "A study on the cost analysis model based on risk factors of the overseas gas plant construction industry" Journal of The Architectural Institute of Korea, 31(3), pp. 53-62.
13 Son. T. H. (2015). "Localization as survival and growth strategy in international construction market" K-build Journal, 15(12), pp. 25-38.
14 Rosenfeld, Y. (2014). "Root-Cause Analysis of Construction-Cost Overruns" Journal of Construction Engineering and Management, 140(1), 10.1061/(ASCE)CO.1943-7862.0000789.   DOI
15 Seo, D. W. (2016). "3 out of 10 construction companies, 'deficit management'" Moneytoday, (May. 2, 2016).
16 Shehu, Z., Endut, I. R., Akintoye, A., and Holt, G. D. (2014). "Cost overrun in the Malaysian construction industry projects: A deeper insight" International Journal of Project Management, 32(8), pp. 1471-1480.   DOI
17 Touran, A. (2009). "Probabilistic approach for budgeting in portfolio of projects" Journal of construction engineering and management, 136(3), pp. 361-366.   DOI
18 Utama, W. P., Chan, A. P., Zahoor, H., and Gao, R. (2016). "Review of research trend in international construction projects: a bibliometric analysis" Construction Economics and Building, 16(2), pp. 71-82.
19 CII (Construction Industry Institute) (2003). International Project Risk Assessment (IPRA) Tool, Implementation Resource, 181-2, Austin, TX.
20 Bu-Qammaz, A.S., Dikmen, I., and Birgonul, M., T. (2009). "Risk assessment of international construction projects using the analytic network process" Canadian J. Civil Eng., 36(7), pp. 1170-1181.   DOI
21 Gelman, A., and Hill, J. (2007). "Data Analysis Using Regression and Multilevel/Hierarchical Models" Cambridge University Press, Cambridge, MA.
22 Creedy, G. D., Skitmore, M., and Wong, J. K. (2010). "Evaluation of risk factors leading to cost overrun in delivery of highway construction projects" Journal of construction engineering and management, 136(5), pp. 528-537.   DOI
23 Dikmen, I., Birgonul, M. T., and Han, S. (2007). "Using fuzzy risk assessment to rate cost overrun risk in international construction projects" International Journal of Project Management, 25(5), pp. 494-505.   DOI
24 Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). "Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study" International Journal of project management, 21(5), pp. 321-326.   DOI