Development of Active 5D CAD System for Replaning Progress Schedule According to Change of Project Cost  

Kim, Hyeonseung (Department of Civil Engineering, Gyeongsang National University)
Kang, Leenseok (Department of Civil Engineering, Gyeongsang National University, ERI)
Publication Information
Korean Journal of Construction Engineering and Management / v.17, no.5, 2016 , pp. 54-61 More about this Journal
Abstract
The initial planned annual cost is frequently adjusted under the construction process in construction projects. If the annual cost is reduced than the initial planned cost, the number of possible activities is also reduced from initial planned progress schedule. In such cases, project manager need to replan the progress schedule with possible activities within changed annual cost. However, most project manager will proceed as planned schedule without any change. After the project cost has been exhausted, there are many cases to stop the operation of the construction site. This study developed active 5D CAD system that can replan the progress schedule within changed annual cost and simulate the cost status according to the changed schedule for cost visualization. This system can be used as a decision-making tool in the replaning progress schedule and will be able to increase the practical usability of 5D CAD system.
Keywords
5D CAD; Optimization; Cost Simulation; Construction Cost; BIM;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Jongeling, R., and Olofsson, T. (2007). "A method for planning of work-flow by combined use of location-based scheduling and 4D CAD." Automation in Construction 16. pp. 189-198.   DOI
2 Hartmann, T., Gao, J., and Fischer. M. (2008). "Areas of Application for 3D and 4D Models on Construction Projects." Journal of Construction Engineering & Management , 134(10), pp. 776-785.   DOI
3 Hartmann, T., Van Meerveld, H., Vossebeld, N., and Adriaanse, A. (2012). "Aligning building information model tools and construction management methods." Automation in Construction 22, pp. 605-613.   DOI
4 Ha, C. S., Moon, S. Y., Moon, H. S., and Kang, L. S. (2014). "Development of Quantity Take-off Algorithm for Irregularly Shaped Structures using 3D Object." Journal of the Korean Society of Civil Engineers , 34(2). pp. 655-666.   DOI
5 Feng, C. W., Chen, Y. J., and Huang, J. R. (2010). "Using the MD CAD model to develop the time-cost integrated schedule for construction projects." Automation in Construction 19, pp. 347-356.   DOI
6 Ding, L., Zhou, Y., and Akinci, R. (2014). "Building Information Modeling (BIM) application framework: The process of expanding from 3D to computable nD." Automation in Construction 46, pp. 82-93.   DOI
7 Cheung, F. K. T., Rihan, J., Tah, J., Duce, D., and Kurul, E. (2012). "Early stage multi-level cost estimation for schematic BIM models." Automation in Construction 27, pp. 67-77.   DOI
8 Wang, X., Yung, P., Luo, H., and Truijens, M. (2014). "An innovative method for project control in LNG project through 5D CAD: A case study." Automation in Construction 45, pp. 126-135.   DOI
9 Shen, Z. and Issa, Raja R, A. (2010). "Quantitative evaluation of the BIM-assisted construction detailed cost estimates." Journal of Information Technology in Construction, Information Technologyin Construction , 15, pp. 234-257.
10 Popov, V., Juocevicius, V., Migilinskas, D., Ustinovichius, L., and Mikalauskas. S. (2010). "The use of a virtual building design and construction model for developing an effective project concept in 5D environment." Automation in Construction 19, pp. 357-367.   DOI
11 Lee, Y. W., and Kim, W. T. (2013). "Survey on Actual Status of construction delay and improvement method for in public construction." CERIK, construction-issue-focus 2013-11. pp. 1-30.
12 Kang, L. S., Moon, H. S., Dawood, N., and Kang, M. S. (2010). "Development of Methodology and Virtual System for Optimized Simulation of Road Design Data." Automation in Construction, 19(8), pp. 1000-1015.   DOI
13 Lee, J. G., Lee, H. S., Park, M. S., and Jung, M. Y. (2013). "A framework integrating cost and schedule based on BIM using IFC." Korean Journal of Construction Engineering and Management, KICEM 14(3). pp. 53-64.   DOI
14 Lee, S. K., Kim, K. R., and Yu, J. H. (2014). "BIM and ontology-based approach for building cost estimation." Automation in Construction 41, pp. 96-105.   DOI
15 Lawrence, M., Pottinger, R., Staub-French, S., and Nepal, M. P. (2014). "Creating flexible mappings between Building Information Models and cost information." Automation in Construction 45, pp. 107-118.   DOI
16 Kang, L. S., Kim, S. K., Moon, H. S., and Kim, H. S. (2013). "Development of a 4D object-based system for visualizing the risk information of construction projects." Automation in Construction 31, pp. 186-203.   DOI