Developing an Optimization Model and Program for Planning the Earthwork Based Upon Transportation Theory  

Lee, Seunghak (Department of Architectural Engineering, Hongik University)
Son, Jaeho (Department of Architectural Engineering, Hongik University)
Pyeon, Jaeho (Department of Civil Engineering, San Jose State University)
Lee, Seunghyun (Department of Architectural Engineering, Hong-ik University)
Publication Information
Korean Journal of Construction Engineering and Management / v.17, no.1, 2016 , pp. 101-109 More about this Journal
Abstract
During road construction, minimizing haul and return distances as well as keeping a balance between cut and fill quantities are two of the key tasks for earthmoving operation planning. The result of the earthwork planning has a significant impact on the construction cost and duration. Although there have been research efforts regarding optimized earthwork planning using linear programming, the current practice of selecting earthwork planning methods typically depends on a field manager's intuitive and/or experimental knowledge. Furthermore, there is no system considering earthwork influential field factors including the transportation distance, the earthwork quantity, and the recycling ratio of earth volume. Therefore, this research focuses on the development of such a model for planning the optimized earthwork to increase the efficiency of a road construction. The proposed model is developed based upon the transportation problem method which is a part of Linear Programming. The application result of optimization model on a case study shows that the duration and cost for earthwork ha sbeen reduced approximately 19% and 11% respectively
Keywords
Earthwork Planning; Optimization; Transportation Theory; Productivity; Least-Cost Path;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Park, H., Tae, Y,. and Woo, S. (2007). "A Study on the Estimating of the Dump Truck's Travel Speed Based on Analysis of Factors Affecting Earthmoving Operation," Korean Journal of Construction Engineering and Management, KICEM, 8(3), pp. 97-105.
2 Kang, S., Baek, K,. Baek, H,. and Seo, J. (2010). "A GIS-Based Planning Methodology to Determine the Haul Route Layout in Complex Construction Project," Journal of the Korean Society of Civil Engineers, 30(6D), pp. 631-639.
3 Baek, K,. Kang, S,. and Seo, J. (2009). "Temporary Haul Road and Bridge Planning Based on Economic Efficiency and Productivity," Journal of the Korean Society of Civil Engineers, pp. 3590-3593.
4 Lee, C,. Kim, S,. and Sung, Y. (2003). "A Study on 2D-Based Earthwork Planning Methods," Journal of the Korean Society of Civil Enginerrs, 23(3D), pp. 349-357.
5 Choi, Y,. Sunwoo, C,. and Park, H. (2007). "Analysis of Optimal Haulage Routes for Dump Trucks in Large Open Pit Mines," Journal of the Korean Society for Geosystem Engineering, 44(6), pp. 477-491.
6 Kang, T,. and Cho, Y. (2011). "The Study on the Optimized Earthwork Transfer Path Algorithm Considering the Precluded Area Massive Cutting and Banking," International Journal of Highway Engineering, 13(4), pp. 1-8.
7 Son, J., Mattila, K., and Myers, D. (2005). "Determination of haul distance and direction in mass excavation." J. Constr. Eng. Manage, 131(3), pp. 302-309.   DOI
8 Baek, K,. Kang, S,. Baek, H,. Park, H,. and Seo, J. (2009). "A Study on the Factors of Haul Routes Planning for Earthmoving," Proceedings of KICEM Annual Conference, KICEM, 9, pp. 899-902.
9 Karimi, S., Mousavi, J., Kaveh, A., and Afshar, A. (2007). "Fuzzy optimization model for earthwork allocations with imprecise parameters." J. Constr. Eng. Manage., 133(2), pp. 181-190.   DOI
10 Ji, Y., Borrmann, A., Rank, E., Seipp, F., and Ruzika, S. (2010). "Mathematical modeling of earthwork optimization problems." Proc. Int. Conf. on Computing in Civil and Building Engineering.
11 Lee, J,. Pyeon, M,. Koo, J,. and Park, J. (2010). "Earthwork Plan Using the Precise 3D Topographic Data," Journal of the Korean Society for GeoSpatial Information System, 18(1), pp. 63-72.
12 Atkinson, D.M., Deadman, P., Dudycha,D., and Traynor, S (2005). "Multi-criteria evaluation and least cost path analysis for an article all-weather road," Applied Geography, 24(4), pp. 287-307.
13 Mayer, R. H., and Stark, R. M. (1981). "Earthmoving logistics." J. Constr. Div., 107(CO2), pp. 297-312.
14 Easa, S. M. (1987). "Earthwork allocations with nonconstant unit costs." J. Constr. Eng. Manage, 113(1), pp. 34-50.   DOI
15 Easa, S. M. (1988). "Earthwork allocations with linear unit costs." J. Constr. Eng. Manage, 114(4), pp. 641-655.   DOI
16 Khaled Nassar, Ossama Hosny (2012). "Solving the Least-Cost Route Cut and Fill Sequencing Problem Using Particle Swarm" JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 138(8), pp. 931-942.   DOI