An Analysis of the Duration of the Construction Document Phase of Large Public Building Projects Delivered by the Total Solution Service from 2009 to 2014  

Jung, Wooyoung (Department of Architectural Engineering, Yonsei University)
Lee, Taewon (Department of Architectural Engineering, Yonsei University)
Rhee, Pung-wook (Public Procurement Service in Korea)
Lee, Ghang (Department of Architectural Engineering, Yonsei University)
Publication Information
Korean Journal of Construction Engineering and Management / v.16, no.4, 2015 , pp. 89-97 More about this Journal
Abstract
This paper analyzes the duration of the construction document (CD) phase of 42 large public building projects delivered by the total solution service of Public Procurement Services in Korea from 2009 to 2014. The quality of construction documents significantly affects the quality of construction and facility management. Thus, securing appropriate time for the CD phase during project planning is important for the quality of a project. Currently, the duration of the CD phase is planned based on the construction costs of a project following a notice of the Ministry of Land, Infrastructure and Transport. However, our analysis results showed that the correlation between the actual duration of the CD phase and construction costs is very weak. The actual CD phase takes 1.33-1.79 times longer than the planned duration. The practitioners who were interviewed, were already aware that the correlation between the duration of the CD phase and the construction costs is weak. They identified the complexity of the project, the extent of the design changes, project type, client characteristics, and others as more influential factors on the CD phase than the construction costs. To improve the quality of CDs, a new guideline for determining an adequate CD phase duration should be studied and developed.
Keywords
Construction document phase; Construction documents; Duration of construction document phase; Correlation coefficient analysis;
Citations & Related Records
Times Cited By KSCI : 5  (Citation Analysis)
연도 인용수 순위
1 Lee, M. J., Park, B. J., and Im, K. S. (2008). "A Study on the Estimation of Change Orders Impact for the Public Construction", Journal of the Korean Society of Civil Engineers D, Korean Society of Civil Engineers, 28(3D), pp. 363-369.
2 Lee, N. J., Son, M. J., Kim, J. H., Ji, S. M., and Hyun, C. T. (2011). "Development of Construction Documents Checklists for Preventing Error of Design Process in Public Construction Projects", Journal of the Architectural Institute of Korea Structure & Construction, Architectural Institute of Korea, 27(2), pp. 149-158.
3 Love, P., Edwards, D., Smith, J., and Walker, D. (2009). "Divergence or Congruence? A Path Model of Rework for Building and Civil Engineering Projects", Journal of Performance of Constructed Facilities, 23(6), pp. 480-488.   DOI   ScienceOn
4 Ministry of Construction and Transportation (1999). Efficiency and Comprehensive plan for public construction projects, Korea.
5 Ministry of Land, Infrastructure and Transport (2014). Manual for Deliberation and Evaluation of Technology Proposals on Design Development and Construction Documents, 2014-02, Sejong, Korea.
6 Ministry of Land, Transport and Maritime Affairs (2010). Manual for Design Deliberation and Evaluation of Turn-key and Alternative Bids, 2010-03, Sejong, Korea.
7 Ministry of Land, Transport and Maritime Affairs (2012). Registered Architects' Workscope and Estimation Guideline for Public Projects, 2012-08, Sejong, Korea.
8 Presidential Decree Act No. 22637 (2011). Act on Contracts to Which the state is a Party, Enforcement decree Article 102(Choice for determination of successful bidder for construction document & technology proposal and etc.).
9 Kim, H. I. (1998). "The causes of design change and improvement countermeasure for public construction", The National Assembly of the Republic of Korea, pp. 23-27.
10 Kim, J. H. (2008). "The Constitution Plan of Design Error Management System in Construction Projects.", Journal of the Regional Association of Architectural Institute of Korea, 10(3), pp. 231-239.
11 Lee, B. K., Jung, T. H., Park, H. J., and Koo, K. J. (2010). "Checklists for Construction Drawings of Office Buildings based on Working Drawing Analysis", Korean journal of Construction Engineering and Management, KICEM, 11(4), pp. 3-11.   DOI
12 Lee, J. S. (2006). "Impacts of Pre-construction Design Quality on Construction Durations and Costs.", Journal of the Architectural Institute of Korea Structure & Construction, Architectural Institute of Korea, 22(5), pp. 219-226.
13 Lee, J. Y., Kim, D. H., and Seo, Y. S. (2005). "A Study on the Factor of Change Order in the public construction Project.", Architectural Institute of Korea, 25, pp. 523-526.
14 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 103 (Tending procedures for construction document & technology proposal).
15 Presidential Decree Act No. 22660 (2011). Act on Contracts to Which the state is a Party, Enforcement decree Article 85-2 (Choice for determination of qualified persons or successful bidder for construction document).
16 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 85 (Tending procedures for designbuild and etc.).
17 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 87 (Determination of successful bidder for design-build).
18 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 104 (Determination of successful bidder for construction document & technology proposal).
19 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 105 (Tending procedures for design development & technology proposal).
20 Presidential Decree Act No. 25358 (2014). Act on Contracts to Which the state is a Party, Enforcement decree Article 106 (Determination of successful bidder for design development & technology proposal).
21 Public Procurement Service (2007). "Construction Delivery Handbook", Public Procurement Service, 2007-12, Daejeon, Korea.
22 Shin, K. C., Park, H. K., Lee, Y. H., Kwak, J. H. (2011). "Development of the Design Management Guidelines to Enhance the Capability of Public Clients", Korean journal of Construction Engineering and Management, KICEM, 12(2), pp. 143-151.   DOI   ScienceOn