A Study on Normal Project Duration for Water Resource Project  

Lee, Bongsu (Department of Technology Security, K-water)
Kim, Kinam (Department of Civil Engineering, ChungNam National University)
Lee, Minjae (Department of Civil Engineering, ChungNam National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.16, no.1, 2015 , pp. 35-43 More about this Journal
Abstract
It is important to have enough design and construction duration for infrastructure projects. However, recent water resource project in Korea shows several problems caused by their fast-tract schedule. National Audit Committee report several water resource projects have quality problems caused by insufficient project duration. Especially, water resource projects such as dam and water pipeline construction should have proper time to secure their structure quality. Normal project duration for these projects should be estimated based on previous similar projects' historical data analysis. However there is no standard model which can estimate normal project duration for water resource projects in Korea. There are several normal project duration estimation models for building project developed by public(LH) and private construction companies. However, there is no proper model for water resource projects. So, this study developed normal project duration model for dam and water pipeline projects using historical data and show application of models.
Keywords
Normal project duration; Historical data; Regression model; Water resource;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 AbouRizk, Halpin (1992). "Statistical properties of construction duration data", Journal of Construction Engineering and Management, ASCE, 118(3), pp. 525-544.   DOI
2 Ahuja, Nandakumar (1985). "Simulation model to forecast project completion time", Journal of Construction Engineering and Management, ASCE, 111(4), pp. 325-342.   DOI   ScienceOn
3 Akinsola A.O, Potts K.F, Ndekugri I, and Harris FC (1997). "Identification and evaluation of factors influencing variations on building projects", International Journal of Project Management, 15(4), pp. 263-267.   DOI   ScienceOn
4 Han, Tae-Gon and Kim, Young-su (2000). "An Estimation Method of Activity Duration Using Fuzzy Set Theory", Journal of the Regional Association of Architectural Institute of Korea, 16(3). pp. 93-102.
5 Hwang, Hyo-Sang (2002). "Analysis of Actual Duration by Effecting Elements to Duration Estimate-Focused on Standard Duration of the Office Building Construction", Korean Journal of Construction Engineering and management, KICEM, 3(3), pp. 84-93.
6 Jeong, Suk-Nam and Lee, Hak-ki (2000). "a preliminary study on the effective decision-making support model for duration by the hypothetical weather simulation", Journal of the Regional Association of Architectural Institute of Korea, 20(2), pp. 587-590.
7 Korea Instituie of Civil Engineering and Building Technology (1992). "Study on the estimation standard of construction duration"
8 Kim, Byeong-soo and Chun, Jin-Ku (2005). "A Study on Estimation Model of Construction Duration for Public Construction", Korean Journal of Construction Engineering and management, KICEM, 6(6), pp. 142-151.
9 Kim, Sang-joong and Lee, Jae-Soeb (2004). "An Optimal Scheduling Method Using Probability on the Estimation of Construction Duration", Korean Journal of Construction Engineering and management, KICEM, 5(6), pp. 72-79.
10 Koo, Hae-Shik and Choi, Bong-CHUL (1999). "A Study on the Estimation of Construction Period Considering Weather Factor in Building Construction", Journal of the Regional Association of Architectural Institute of Korea, 15(11), pp. 87-96.
11 Kwon, Dong-Chan and Lee, Chan-Shik (2004). "The Estimation of Construction Duration for High School Buildings Based on the Actual Data", Korean Journal of Construction Engineering and management, KICEM, 5(6), pp. 138-145.   과학기술학회마을
12 Lee, Chan-Shik (1996). "Estimation Method for Construction Duration in the Frame Work of Reinforced Concrete Wall-Slab Type Apartments", KSCE of Civil Engineering, 12(7), pp 349-364.
13 Schexnayder, C., Knutson, K. and Fente, J (2005). "Describing a beta probability distribution function for construction simulation", Journal of Construction Engineering and Management, ASCE, 131(2), pp. 221-229.
14 Lee, D.E. (2005). "Probability of project completion using stochastic project scheduling simulation", Journal of Construction Engineering and Management, ASCE, 131(3), pp. 310-318.   DOI   ScienceOn
15 Lee, Hyun-soo (1996). "A Method of Estimating the Construction Duration based on Rdpetitive Work Modules for Reinforced Concrete Buildings", Journal of the Regional Association of Architectural Institute of Korea, 12(5), pp. 257-266.
16 Lee, Sang-Beom (2001). "A Study on the Optimal Duration Estimating Method by Line of Balance", Journal of the Regional Association of Architectural Institute of Korea, 17(9), pp. 233-240.