Study on Optimization for Construction Vertical Lifting with Transfer Operation for Super High-rise Buildings  

Moon, Jooyong (Department of Architecture & Architectural Engineering, Seoul National University)
Park, Moonseo (Department of Architecture, Seoul National University)
Lee, Hyunsoo (Department of Architecture & Architectural Engineering, Seoul National University)
Jung, Minhyuk (Department of Architecture & Architectural Engineering, Seoul National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.15, no.6, 2014 , pp. 53-62 More about this Journal
Abstract
Recently, the number of super high-rise building projects have been increased after recovering from international financial crisis. In super high-rise building project, vertical lifting is critical to overall project productivity, due to its limited lifting equipments. Also for projects which buildings' height are higher than 400m, transfer operation in lifting is inevitable because of lifts' maximum lifting height. In transfer operation, setting a transfer floor is essential for saving lifting time of resources. In this research, using discrete event simulation modeling with AnyLogic 7.0 software and metaheuristic optimization with OptQuest software, the method of optimizing a transfer floor for workers during the morning peak time is proposed. Comparing to the result of the case which transfer floor is designated to the middle floor, setting optimized transfer floor significantly decrease the total lifting time of workers. By using proposed simulation and optimization tool, saving budget and time through increasing available working hour is expected.
Keywords
Construction Lift; Transfer Operation; Efficiency; Super High-irse Buildings; Transfer Floor; Optimization; Simulation;
Citations & Related Records
Times Cited By KSCI : 6  (Citation Analysis)
연도 인용수 순위
1 Cho, C. (2011). "An Algorithm for Hoisting Time Calculation in Super-Tall Building Construction" Korean Journal of Construction Engineering and Management, KICEM, 12(6) pp. 120-129.   과학기술학회마을   DOI
2 Ahn, B. (2004). "A Vertical Movement Plan for Labors in High-Rise Building Construction Using Discrete- Event Simulation" Korean Journal of Construction Engineering and Management, KICEM, 5(2) pp. 47-54.   과학기술학회마을
3 Ahn, B. (2004). "Condition and Problem of Lift-up Plan for Finishing Material in High-Rise Building Construction" Proceedings of the 4th International Symposium of KSTBF, Seoul, South Korea.
4 Banerjee, D. (2011). "Simulation-Based Evaluation of Dispatching Policies in Service Systems" Proceedings of the 2011 Winter Simulation Conference, Phoenix, AZ, USA.
5 Chan, V. W. K. (2010). "Agent-Based Simulation Tutorial-Simulation of Emergent Behavior and Difference between Agent-Based Simulation and Discrete-Event Simulation" Proceedings of the 2010 Winter Simulation Conference, Baltimore, MD, USA.
6 Cho, C. (2010). "Simulation Method of Construction Hoist Operating Plan For High Rise Bulidings Considering Lifting Heights and Loads" Proceedings of the 27th ISARC, Prague, Czech Republic, pp. 22-28.
7 Cho, C. (2013). "An optimal algorithm of the multi-lifting operatiing simulation for super-tall building construction" Automation in Construction, 35, pp. 595-607.   DOI
8 Cho, H. (2010). "Trend of Lift planning and technology development in High-rise Building Construction" Construction Engineering and Management, KICEM, 11(1), pp. 15-18.
9 CTBUH (2014). "Tall Buildings in Numbers", International Journal on Tall Buildings and Urban Habitat, CTBUH, 2014(1), pp. 38-39.
10 Ebrahim R. M. (2009), "Scatter search algorithm for supplier selection and order lot sizing under multiple price discount environment", Advanced in Engineering Software, 40, pp. 766-776.   DOI
11 Jie, W. (2008). "Simulation for Constrainted Optimization of Inventory System by Using Arena and OptQuest" 2008 International Conference on Computer Science and Software Engineering, Wuhan, China.
12 Ioannou, P.G., and Martinez, J.C. (1996). "Scalable Simulation Models for Construction Operations." Proceedings of 28th Conference on Winter Simulation, IEEE Comp. Soc., December 8-11, 1996, Coronado, CA, USA, pp. 1329-1336.
13 Han, C. (2012). "A Computation Model for Resource-based Lifting loads of the lift-cars for super high-rise buildings" Journal of Construction Engineering and Management, KICEM, 13(5) pp. 135-143.   과학기술학회마을   DOI
14 Halpin, D. W. (1973). "An Investigation of the use of simulation networks for modeling construction operations." Ph.D. Thesis, The University of Illinois at Urbana-Champaign, IL, USA.
15 Hwang, S. (2009). "Planning temporary hoists for building construction" 2009 Construction Research Congress, ASCE, Seattle (April), pp. 1300-1307.
16 Jung, Y. (2004). "The Rationalization Method of Lift Car Planning in the High-rise Building Construction" Proceedings of the 2004 Spring Annual Conference, Architectural Institute of Korea, Seoul, South Korea.
17 Kim, K. (2000). "A Study for the Implementation of Self-controlling Resource Model in the Simulation of Heavy Construction Operations", Journal of the Korean Society of Civil Engineers, KSCE, 20(4D) pp. 389-402.
18 Kim, S. (2002). Management Simulation, 1st ed, Hankyoung-Sa, Seoul.
19 Martinez, J. C. (1996). "STROBOSCOPE : State and Resource Based Simulation of Construction Process." Ph.D. Thesis, The University of Michigan, Ann Arbor, MI, USA.
20 Kim, S. (2008). "A Study on the Estimation of Proper Numbers of Construction Lifts", Journal of the Korea Institute of Building Construction, 8(3) pp. 119-125.   과학기술학회마을   DOI   ScienceOn
21 Park, K. (2001). "An Analysis of the Optimal Planning of Material Lifting in the High-rise Building Construction" Proceedings of the 2001 Annual Conference, Architectural Institute of Korea, Asan, South Korea.
22 Laguna, M. (1997). "Optimization of Complex Systems with OptQuest", University of Colorado, Boulder, CO, USA.
23 Lee, H. (2008). "Development of the Model Using Queueing Theroy for Lift Planning in Tall Buildings" Proceedings of 2008 KICEM Annual Conference, Seoul, South Korea.
24 Park, E. (2009). "A Study on the Influential Factors of Construction Lifting Planning for Super-High rise Building Projects" M.S. Thesis, Kyunghee University, Seoul, South Korea.
25 Park, M. (2011). "An Optimization Model of Temporary Lift's Vertical Zoning for Worker Lifting Operation in the High-rise Building Construction" Journal of the Architectural Institute of Korea Structure & Construction, 27(11) pp. 193-202.
26 Rogers, P. (2002). "Optimum-Seeking Simulation in the Design and Control of Manufacturing Systems: Experience with OptQuest for Arena" Proceedings of the 2002 Winter Simulation Conference, San Diego, CA, USA.
27 Shin, Y. (2010). "Interactive lift operation planning system for finishing work in tall building construction" Ph.D. Thesis, Korea University, Seoul, South Korea.