A Study on Duration Calculation Method for Eco-Friendly Remodeling Demolition Work Using Productivity Analysis  

Woo, Joong-Pyung (아주대학교 건축공학과)
Cha, Hee-Sung (아주대학교 건축공학과)
Kim, Kyung-Rai (아주대학교 건축공학과)
Shin, Dong-Woo (아주대학교 건축공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.14, no.1, 2013 , pp. 124-132 More about this Journal
Abstract
An influx of the population to the city has soared due to industrialization. As times go by, cities become densely populated so Korean government started to construct a number of buildings including apartment housings. Because they have become functionally, structurally, esthetically deteriorated over the past two decades. some improvements are needed. There are mainly two ways to improve old buildings: remodeling and reconstruction. Between the two, the first one is more popular as it is less time-consuming and more eco-friendly. Demolition work comes first for both of them and it should not give negative effects since it is regarded as a CP(Critical path) in the overall process. For this reason, a thorough construction management must be done. The reality, however, demolition is managed by the construction manager's experiences and decisions. If the key factor of demolition which is the planning of manpower and machine equipment, is determined by unscientific and subjective judgments, its period and risk also will increase. In particular, eco-friendly demolition can be more risky because it's been rarely conducted. Therefore, scientific and objective ways of demolition management are needed. In this context, this paper aims at analyzing productivity in each process of demolition focusing on manpower and machinery equipment which are the main parts of demolition assuming that the demands of eco-friendly remodeling demolition projects will be increasing. At the same time, by estimating working period through the output, this paper would be helpful to set up the plans for overall project in earlier stage.
Keywords
Eco-Friendly Remodeling Demolition Work; Initial Duration Method;
Citations & Related Records
연도 인용수 순위
  • Reference
1 서상욱.박태근.이찬식.김문한 (1992), "공사비상으로 고찰한 건축공사의 최적공기산정에 관한 연구", 대한건축학회논문집 계획계 v.8, n.1.
2 안용선 (1986), "건설공사진행에 있어서 공기단축에 따른 Cost 분석", 대한건축학회 춘계학술발표대회 논문집 v6, n1.
3 윤영상.김경환.김재준 (2004), "개선된 자원 평준화 기법을 활용한 적정 공기산정에 관한 연구", 한국건설관리학회 정기학술발표대회논문집 제5권
4 장효원.김수용.김대영(2007)," 건설현장 생산성 측정의 효율적 방안 제시", 한국건설관리학회 정기학술발표대회 논문집 제8권.
5 조규만.현창택 (2009), "건설 시뮬레이션을 이용한 일정관리 기법", 한국건설관리학회 정기학술발표대회논문집.
6 황영규(2008)," 친환경 리모델링 철거공사 프로세스 모델개발", 아주대학교 박사학위논문.
7 Azaron, A., Katagiri, H., and Sakawa, M. (2007)," Time- Cost Trade-Off via optimal control theory in Markov PERT networks", Annals of Operations Research, v. 150, n. 1, Springer.
8 Anagnostopoulos, K. P. (2008), "A Fast Algorithm for Time Compression in Project Scheduling", Operational Research v.2, n. 3, pp.407-417, Springer.
9 강사일 (2008), "리모델링 특성을 반영한 철거공사의 공정계획 수립방안 - 벽식 노후화 공동주택을 대상으로", 아주대학교 석사학위논문.
10 권병기.이현수.박문서.김우영.지세현 (2009) "TACT 공정 관리 작업조 유휴시간 제어를 위한 Data model", 한국건설관리학회 학술발표대회 논문집, pp.672-678,
11 김수민.조재호.이재석.전재열(2009)," 기본설계단계에서의 약식 물량산출을 이용한 건축 구조체 공사비 개산견적 모델", 대한건축학회 논문집 v25, n12.
12 Love, P., Tse, R., and Edwards, D. (2005), "Time-Cost Relationships in Australian Building Construction Projects", ASCE J. of Constr. & Mgmt , v. 131, n. 2.
13 김창학.이경희.김효진 (2008) "해체산업발전을 위한 해체시장분석 및 예측", 한국건설관리학회 학술발표대회 논문집.
14 김효진(2004)," 자원재활용 효율 향상을 위한 분별해체공정 정립 방안", 건설관리, 한국건설관리학회, pp.42-45
15 백종현 (2006), "노후건축물 해체공사의 실태부석 및 개선방안에 관한 연구", 영남대학교 대학원 석사학위 논문
16 Le-Hoai, L, Lee, Y., Cho, J. (2009), "Construction of Time-Cost Model for Building Projects in Vietnam", 한국건설관리학회 논문집 v10, n3.