A Method to Build Daily Progress Management Model based on BIM Estimate Data in Construction Phase  

Jung, Jun-Ho (성균관대학교 대학원 건설환경시스템공학과)
Chin, Sang-Yoon (성균관대학교 건축공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.12, no.5, 2011 , pp. 23-34 More about this Journal
Abstract
Reliable progress management at construction requires integrated information of cost and schedule, and information is used as a basis for project performance measurement. However, separate handling of cost and schedule information at construction projects makes objective measurement more difficult and decreases management productivity due to additional works for breaking down bill of quantities into corresponding activities. Recently, research related to BIM addresses issues on effective progress management based on BIM with incorporation of daily progress management. Therefore, the objective of this paper is to propose information model for daily progress rate and budgeted cost of work performed by utilizing BTM-based quantity and location information.
Keywords
Building Information Modeling(BIM); Estimate Data; Progress Management Unit; Daily Management;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Teicholz, M. (1987)," Current needs for cost control system", Conference Proceeding on Project Control: Needs and solutions ASCE, pp. 47-57
2 Kenley, Russell. and Seppanen, Olli. (2010), "Location- Based Management for Construction", 1st ed., Spon Press, New York, pp. 125
3 Chin, S. Y., Kim, K. R. and Kim, Y. S. (2005)," Generate- Select- Check Based Daily Reporting System", ASCE Computing in Civil Engineering, Volume 19, Issue 4, pp. 412-425   DOI   ScienceOn
4 Spencer, gray Rock. (1987)," Integration of cost estimation with critical path scheduling", A Doctoral Dissertation, Oklahoma State University, pp. 8-10
5 Vico Software (2008), "Virtual Construction 2008 User Guide", pp. 18-19
6 Rasdorf, William J. and Abudayyeh, Osama Y. (1991), "Cost and Schedule Control Integration: Issue and Need", Journal of Construction Engineering and Management, Vol. 117, No.3, pp. 486-502   DOI
7 정준호.이창희.김성아.진상윤.최철호 (2010)," 국내 건설산업에서의 물량산출 특성을 고려한 공법기반 견적자동화 시스템개발", 한국전산구조공학회 학술발표대회 논문집
8 최철호.박영진.한성훈.진상윤 (2006), "레서피(Recipe) 기반의 견적 방법을 이용한 5D CAD", 한국건설관리학회 학술발표대회 논문집, pp. 154-160
9 Hendrickson, Chris. (1989), "Project Management For Construction", Prentice Hall
10 Kim, J. J. (1989), "An object-oriented database management system approach to improve construction project planning and control", Thesis presented to the U. of Illinois, at Urbana, Ill.
11 정영수.강승희.진상윤.김예상.정문헌.박순찬 (2004), "건설진도율 산정을 위한 진도관리단위에 관한 연구", 한국건설관리학회 학술발표대회 논문집, pp. 565-571
12 안재홍.장명훈(2009)," 수량산출정보를 이용한 공정 원가 통합 방안", 대한건축학회지, 제25권 제2호 통권 제244호, pp. 133-140
13 윤수원(2003)," 작업의 특성을 반영한 진도 측정 방안에 관한 연구", 성균관대학교 석사학위논문
14 이복남(1997)," 건설공사진도및기성고산정방법개선", 한국건설산업연구원, pp. 9-10
15 김우영.김옥규.최윤기.이현수(2002)," 공통자와 분류체계에 의한 비용/일정 통합모델 개발", 대한건축학회지, 제18권 제 8호 통권 제166호, pp. 99-106
16 안승준.이현수.박문서.김우영 (2009), "공정 원가 통합관리를 위한 BIM 기반 객체지향형 공정 모델링", 대한건축학회지, 제25권 제12호 통권 제254호, pp. 165-174
17 박찬정 (2006), "린 건설 사례", 한국건설관리학회지 7(3), pp. 13-16
18 배신호(1989)," 건설공사에 있어서 진도관리의 효율화에 관한 연구", 중앙대학교 석사학위논문