Risk Identification and Priority method for Overseas LNG Plant Projects - Focusing on Design Phase -  

Jang, Woo-Sik (연세대학교 토목환경공학과)
Hong, Hwa-Uk (연세대학교 토목환경공학과)
Han, Seung-Heon (연세대학교 사회환경시스템공학부)
Publication Information
Korean Journal of Construction Engineering and Management / v.12, no.5, 2011 , pp. 146-154 More about this Journal
Abstract
Korean contractors have been maintained sustainable growth since entering into overseas construction market for the first time in 1960' s. In 2010, Korean contractors ordered 761 billion (USD) from overseas markets. Especially, billion (USD) were earned by Korean contractors in overseas plant construction market which account for more than 80% of the total amount by Korean contractors. Nevertheless, many Korean contractors are suffering from lack of technological competitiveness and construction management skills in the design phase compared with global leading contractors. These conditions have directly effect on the success of projects in terms of cost, duration, and quality. So, this study focused on identifying the risk factors and developing risk priority method for the design phase of LNG plant projects whose market is expanding. Research procedures were conducted by the following three steps. First, total 57 risk factors were identified in design phase through extensive literature reviews and experts survey. Second, the authors developed risk priority method which are more suitable for design phase of LNG plant projects by using three criteria, Probability(P), Impact(I), and Coordination Index(CI). Finally, the suitability of risk priority method and practical applicability were verified through expert survey and interview. Consequently, if korean contractors use the suggested risk factors and priority method based on their own know-how and experiences, then more reasonable and rational risk management will be conducted in the design phase of LNG plant projects.
Keywords
Overseas LNG plant; Design phase; Risk; Priority method; Three-dimensional evaluation; Coordination index;
Citations & Related Records
Times Cited By KSCI : 7  (Citation Analysis)
연도 인용수 순위
1 Riley, D. R., Varadan, P., James, J. S., Thomas, H. R. (2005)." Benefit-Cost Metrics for Design Coordination of Mechanical, Electrical, and Plumbing Systems in Multistory Buildings", Journal of Construction Engineering and Management, Vol. 131, No. 8, pp. 877-889   DOI   ScienceOn
2 Zhi, H. (1995)." Risk management for overseas construction projects", International Journal of Project Management, 13(4), pp. 231-237   DOI   ScienceOn
3 Fayek, A. R., Dissanayake, M., Campero, O. (2003). "Measuring and Classifying Construction Field Rework: A Plot Study", Construction Owners Association of Alverta(COAA)
4 Hastak, M., Shaked, A. (2000). "ICRAM-1: Model for International Construction Risk Assessment", Journal of Management in Engineering, 16(1), pp. 59-69   DOI   ScienceOn
5 이현영(2009)." 해외플랜트 리스크 분석 사례", 한국건설관리학회 논문집, 제10권, 제4호, pp.11-17
6 Inniss, H. (2004), "Operational Vertical Integration in the Gas Industry, with Emphasis on LNG: Is it Necessary to ensure Viability?", Center for Energy, Petroleum & Mineral Law & Policy Annual Review
7 Mulholland, B., Christian, J. (1999). "Risk assessment in construction schedules", Journal of Construction Engineering and Management, 125(1), pp. 8-15   DOI   ScienceOn
8 Renn, O. (1998). "The role of risk perception for risk management", Reliability Engineering and System Safety, 59(1), pp. 49-62   DOI   ScienceOn
9 해외건설협회 (2011). "해외건설종합정보서비스", [online DB, cited 11.03.21],
10 Aleshin, A. (2001). "Risk management of international projects in Russia", International Journal of Project Management, 19(4), pp. 207-222   DOI   ScienceOn
11 윤나리 (2010). "LNG 플랜트 프로젝트의 통합지식관리시스템 Framework 구축에 관한 연구", 석사학위 논문, 경희대학교
12 Construction Industry Institute (2003), "International Project Risk Assessment", CII
13 Cox, L. A. Jr.. (2008)." What's wrong with risk matrices?", Risk Analysis, 28(2), pp. 497-512   DOI   ScienceOn
14 유영훈(2008)." 플랜트 설계단계 정량적 평가모델 개발 및 사례 수집에 관한 연구", 석사학위 논문, 홍익대학교
15 이상엽, 손재호, 유영훈, 한충희(2008)." 플랜트사업 설계사례의 체크리스트기반 평가모델에 관한 연구", 한국건설관리학회 논문집, 제9권, 제3호, pp.146-152
16 안성훈, 이영남, 조호규 (2008)." 해외 플랜트 공사 리스크 평가 방안 및 적용에 관한 연구", 한국건설관리학회 논문집, 제9권, 제1호, pp.134-142
17 김한힘 (2004)." 실무적 차원의 해외건설 프로젝트 리스크 관리 모델 연구", 석사학위 논문, 연세대학교
18 안승규, 조동환, 허진혁, 문승재, 유호선 (2010)." 해외 플랜트 프로젝트 리스크의 평가 및 관리시스템에 관한 연구", 플랜트저널, 제6권, 제1호, pp.56-63
19 원서경, 강민우, 이준복, 김선국, 한충희(2008)." 해외 플랜트 프로젝트 구매조달 시스템 구축을 위한 프로세스 분석", 대한건축학회 논문집, 제24권, 제2호, pp.113-120
20 구본학, 김태희 (2007)." 플랜트설계를 위한 표준코드의 활용체계 개선방안", 한국건설관리학회 논문집, 제8권, 제2호, pp.81-89
21 강인석, 이승렬(2004)." 공기 및 공사비 위험도의 가중치를 적용한 건설공사 리스크 관리기법 연구 ", 대한토목학회 논문집, 제24권, 제2D호, pp.229-238
22 손재호, 이상엽, 한충희, 김재은 (2007). "플랜트 설계단계 핵심 성공요인(CSF) 도출에 관한 연구", 한국건설관리학회 논문집, 제8권, 제6호, pp.227-234