Construction of Time - Cost Model for Building Projects in Vietnam  

Long, Le-Hoai (Pukyong National University, Interdisciplinary program of construction engineering and management)
Lee, Young-Dai (Dept. of Civil Engineering, Pukyong Nat. Univ.)
Cho, Jeong-Wook (Pukyong National University, Interdisciplinary program of construction engineering and management)
Publication Information
Korean Journal of Construction Engineering and Management / v.10, no.3, 2009 , pp. 130-138 More about this Journal
Abstract
Bromilow's time-cost (BTC) relationship was examined for building projects in Vietnam using actual construction time and total construction cost. Data set was collected from 77 historical building construction projects completed between 1999 and 2005 which were adjusted by consumer price index (CPI) to 2000 price. Time-cost equations were specified respected to two sectors, public and private, in Vietnamese construction industry and all cases. It is shown that a public funded building project has the longer construction duration than a similar budget private funded project. The resulting models are statistically significant. The adjusted R-square coefficients of all cases, public and private projects models are respectively 0.403, 0.436 and 0.377 mean that the BTC regression lines moderately fit the data set.
Keywords
Bromilow's model; building project; time-cost relationship; Vietnam;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Bromilow, F.J., Hinds, M.F. and Moody, N.F. (1988) The Time and Cost Performance of Building Contracts 1976-1986, The Australian Institute of Quantity Surveyors, Sydney
2 Chan, D.W.M., Kumaraswamy, M.M. (1995) A study of the factors affecting construction durations in Hong Kong. Construction Management and Economics, 17, 189-196   DOI   ScienceOn
3 Endut, I.R.; Akintoye, A.; Kelly, J. (2006) Relationship between duration and cost of Malaysian construction projects. Proceedings of the International Conference in the Built Environment in the 21st Century (ICiBE 2006) 299-309
4 Bromilow, F.J. and Henderson, J.A. (1976) Procedures for reckoning and valuing the performance of building contracts. The Chartered Builder, 10(9), 57
5 Sidwell, A.C. (1984) The time performance of construction projects. Architectural Science Review, 27, 85-91   DOI   ScienceOn
6 Walker, D.H.T. (1995) An investigation into construction time performance. Construction Management and Economics, 13(3), 263-74   DOI   ScienceOn
7 Ogunsemi, D.R and Jagboro, G.O. (2006) Time-cost for building projects in Nigeria. Construction management and Economics 24:3, 253-258   DOI   ScienceOn
8 Le-Hoai, L.Lee, Y.D., Lee, J.Y. (2007). Identification of factors affecting time and cost performance in Vietnam construction projects, Proceedings of KICEM Conference, Busan, 728-731
9 Chen, W.T. and Huang Y.H. (2006) Approximately predicting the cost and duration of school reconstruction projects in Taiwan. Construction management and Economics 24:12, 1231-1239   DOI   ScienceOn
10 Hoffman, G.J.; Thal, A.E.; Webb, T.S.; Weir, J.D. (2007) Estimating performance time for construction projects. Journal of Management in Engineering (ASCE) 23:4, 193-199   DOI   ScienceOn
11 Vietnamese Ministry of Finance (MOF) (2006) State issues market-oriented rules to control construction costs. Retrieved February 20, 2007, from the World Wide Web: http://www.mof.gov.vn/DefaultE.aspx?tabid=616&ItemID=37435
12 Vietnam General Statistic Office (GSO). The World Wide Web: http://www.gso.gov.vn/ (Vietnamese)
13 Ng, S.T.; Mak, M.M.Y.; Skitmore, R.M.; Lam, K.C.; Varnam, M. (2001) The predictive ability of Bromilow's time-cost model. Construction management and Economics 19:2, 165-173   DOI
14 Bromilow, F.J. (1969) Contract time performance expectation and the reality. Building Forum 1(3), 70-80.s
15 Kenley, R. (2001) The predictive ability of Bromilow's time-cost model: a comment. Construction management and Economics 19:8, 759-764   DOI   ScienceOn
16 Chan, A.P.C (2001) Time-cost relationship of public sector projects in Malaysia. International journal of Project Management 19, 223-229   DOI   ScienceOn
17 Bromilow, F.J., Hinds, M.F. and Moody, N.F. (1980) AIQS survey of building contract time performance. Building Economist, 19(2), 79-82
18 Tu Chi (2004) Unrealistic tendering process. Vietnamnet newspaper. Retrieved February 20, 2007, from the World Wide Web: http://vietnamnet.vn/kinhte/toancanh/2004/07/172192/ (Vietnamese)
19 Chan, A.P.C (1999) Modeling building durations in Hong Kong. Construction management and Economics 17, 189-196   DOI   ScienceOn
20 Kumaraswamy, M.M., Chan, D.W.M. (1995) Determinants of construction duration. Construction Management and Economics, 13, 209-217   DOI   ScienceOn
21 Long N.D., Ogunlana S., Quang T., Lam K.C. (2004). Large construction projects in developing countries: a case study Vietnam, Int J Project Management, 22, 553-561   DOI   ScienceOn
22 Love, P.E.D.; Tse, R.Y.C.; Edwards, D.J. (2005) Time-cost relationships in Australian building construction projects. Journal of Construction Engineering and Management (ASCE) 131:2, 187-194   DOI   ScienceOn
23 Kaka, A.P. and Price, A.D.F. (1991) Relationship between value and duration of construction projects. Construction Management and Economics, 9(4), 383-400   DOI
24 Chan, A.P.C. and Yeong C.M. (1995) A comparison of strategies for reducing variations. Construction management and Economics 13, 467-473   DOI   ScienceOn