A Study on Characteristic Analysis of Major Issues in Negotiating Concession Agreement for BTO Projects Using AHP  

Roh, Tae-Ho (부경대학교 공학연구소)
Kim, Jong-Won (부산도시공사)
Lim, Chang-Sik (부경대학교 대학원 건설관리공학협동과정)
Lee, Jong-Chool (부경대학교 건설공학부)
Publication Information
Korean Journal of Construction Engineering and Management / v.9, no.6, 2008 , pp. 137-146 More about this Journal
Abstract
Both competent authorities and private entrepreneurs face plenty of risks when negotiating BTO(Build Transfer Operation) methods of PPI(Private Participations in Infrastructures) projects. Also, success and failure of projects largely depend on the concession agreement contract. In this study, for more efficient negotiation, major issues are examined, and quantitatively analyzed to find out not only the relationship but also the characteristics of which these issues share. Questionnaire research was conducted through both research and by experts who were divided into an ordering agency, design company and constructor. Characteristics of major issues were quantitatively analyzed using the Likert index method, ANOVA(ANalysis of VAriance) and AHP(Analytic Hierarchy Process) analysis. Case studies were examined in order to estimate construction cost, rates of return, government finance support, level of operation-revenues guarantees, estimating operational costs and usage fees. With these 6 items, relative priority, relative impression which is sensible to risk and extent of difficulty in presenting data which is objective were quantitatively analyzed by the ordering agency, design company and constructor groups. From the analysis, there were some similarities between the design company and constructor groups while there was less of similarities between the ordering agency and design company or constructor. The government is diversifying the methods of project promotion, and PPI project from infrastructure-centered to public culture facilities are being expand. The current study will provide not only supporting efficient negotiation but also revitalizing PPI projects.
Keywords
PPI; BTO; Major issue; AHP; ANOVA;
Citations & Related Records
연도 인용수 순위
  • Reference
1 기획예산처(2006). 민간투자사업 업무 매뉴얼, pp. 34-76
2 김흥수외 4인 (2003). 민간투자사업의 주요 쟁점별 협상방안 연구, 국토연구원
3 이규방, 송병록 (2000). 인프라 민간투자사업의 표준실시 협약(안) 지침수립, 국토연구원
4 Kerf, Michel & Gray, R. David & Irwin, Timothy & Levesque, Celine & Taylor, Robert R.(1998). "Concessions for Infrastructure : A Guide to Their Design and Award", World Bank Technical Paper No.399
5 이달곤 (1989). "협상이론의 연구와 원칙에 준거한 협상전략", 서울대학교 행정대학원 행정연구소 행정논총, 제27권 제1호, pp. 302-329
6 Thomas L. Saaty(1995). Decision Making for Leaders, RWS Publication
7 Likert, Rensis(1932). "The method of constructing an attitude scales", Archives of Psychology 140, pp. 44-53
8 정정만 (2006). 교육시설 BTL 사업의 리스크 식별 및 협상 주요 쟁점 개선 방안, 부경대학교 대학원, 박사학위논문
9 UNIDO(1996). Guidelines for Infrastructure Development Trough BOT Projects, UNIDO Publication
10 임정규 (2004). 민자유치 도로사업에서 사업성에 미치는 영향 변수에 관한 연구, 대우건설기술, pp. 7-21
11 Fisher, Roger, Ury, William and Patton, Bruce(1991). Getting to Yes : Negotiating Aggrement without Giving In, Penguin Books
12 NICITRAL(1995). Model Law on Procurement of Goods Construction and Services with Guide Enactment, United Nations
13 곽노성 (2003)." 민간투자사업 실시협약 협상의 구조적 특성과 효율적 협상방법". 협상연구, 제9권 제1호, 한국협상학회, pp. 49-75
14 김명수, 권혁진 (2003). "민간투자사업의 투자추이와 전망". 건설경제, 제37권, 국토연구원, pp. 51-69