Construction Process based Schedule Risk Management System  

Yoon, You-Sang (서울대학교 린건설연구단)
Suh, Sang-Wook (경원대학교 건축공학과)
Park, Moon-Seo (서울대학교 건축학과)
Jang, Myung-Houn (제주대학교 건축학부)
Publication Information
Korean Journal of Construction Engineering and Management / v.9, no.4, 2008 , pp. 101-110 More about this Journal
Abstract
In order to achieve the best performance of a project, uncertainties involved in the building construction process need to be identified in the planning phase of the project. Risk management plays a significant role in construction to minimize risk occurred due to uncertainties of a project. Although the importance of the risk management has been known to the construction industry, a more effective system should be developed to meet the demands of the industry. The purpose of this study is to develop the effective risk management system for scheduling the construction processes. The study provides a tool that can optimize the management system which would assist managers to identify schedule risks in the planning phase of the project.
Keywords
Schedule; Risk; Trade; Construction; Process;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 주해금 외 2인 (2005). '위험관리 중심의 곤정관리모델.' 건설관리, 6(6), 한국건설관리학회, pp.81-89   과학기술학회마을
2 Miyagawa, Tetsuya (1997). 'Construction Manageability Planning-A System for Manageability Analysis in Construction Planning.' Automation in Construction, 6(3), Elsevier, pp.175-191   DOI   ScienceOn
3 Mulholland, B. and Chritian, J. (1999). 'Risk assessment in construction schedules.' Journal of Construction Engineering and Management, 125(1), ASCE, pp.8-15   DOI   ScienceOn
4 Jaafari, A. (1994). 'Total Project Risk management Aided by Information Systems. '12th Internet World Congress on Project Management, Proceedings. Vol.2, pp.311-317
5 김인호 (2001). 건설사업의 리스크관리-건설사업의 위험성과 불확실성에 대한 전략적 접근방법, 기문당
6 조훈희 외 2인 (2001). '공기연장 실태조사를 통한 발주자 중심 공기지연 리스크 대응방안 - 공공발주 공동주택을 대상으로.' 대한건축학회논문집(구조계), 17(12), 대한건축학회, pp.159-166
7 홍성욱 외 2인 (2003), '국내 건설기업의 리스크 관리의 실태 분석 및 개선방향에 관한 연구.' 대한건축학회논문집(구조계), 19(5), 대한건축학회, pp.153-160
8 Mootanah, D. P. (1997). 'A Holistic Framework for Managing Risks in Construction Projects. 'PMI 28th Annual Seminar & Symposium, PMI, pp.1056-1062
9 윤철성 외 1인 (2003). '국내 건설공사 클레임 사례를 기준한 위험요인 및 대응전략 도출.' 대한건축학회논문집(구조계), 19(9), 대한건축학회, pp.163-170
10 Construction Industry Institute (1996), PDRI: Project Definition Rating Index for Building Projects. Construction Industry Institute, pp.1-61
11 Yi, Kyoo-jin and Langford, David (2006). 'Scheduling-Based Risk Estimation and Safety Planning for Construction Project.' Journal of Construction Engineering and Management, 132(6), ASCE, pp.626-635   DOI   ScienceOn
12 강인석 외 2인 (2001). '건설공사단계별 리스크 인자 중요도에 관한 현황 분석.' 대한건축학회논문집(구조계), 17(8), 대한건축학회, pp.103-110
13 장명훈 (2006a). '확률적 방법에 의한 공정리스크 시뮬레이션 시스템 개발.' 대한건축학회논문집(구조계), 22(8), 대한건축학회, pp.117-124
14 Aleshin, A. and Dworatsch, S. (1997). 'Risk Management of Joint Venture Construction Projects of Foreign Cooperation in Russia.'PMI 28th Annual Seminars & Symposium, PMI, pp.221-226
15 주해금 외 1인 (2003). '건설사업 위험분류체계의 재정립을 통한 위험인지 체크리스트 개발.' 건설관리, 4(2), 한국건설관리학회, pp.109-117
16 황지선 외 1인 (2003),' 초기 건설공사의 리스크 분류체계에 관한 연구.' 대한건축학회 학술발표대회논문집, 23(1), 대한건축학회, pp.339-342
17 Wang, Wei-Chih, Liu, Jang-Jeng and Chou, Shih- Chieh (2006). 'Simulation-based safety evaluation model integrated with network schedule.' Automation in Construction, 15(3), Elsevier, pp.341-354   DOI   ScienceOn
18 서석원 외 2인 (2002). '건설공사의 최적 리스크 대응방안 선정을 위한 의사결정 모델.' 대한건축학회논문집(구조계), 18(8), 대한건축학회, pp.115-122
19 한종관 외 2인 (2003). '시공자 중심의 주요 공종별 공기지연 원인 분석에 관한 연구 - 공동주택을 중심으로.' 대한건축학회논문집(구조계), 19(3), 대한건축학회, pp.163-170
20 장명훈 외 2인 (2006b). '공정관리 프로그램을 이용한 공정 리스크 관리 방안.' 대한건축학회논문집(구조계), 22(12), 대한건축학회, pp.131-138
21 Nasir, D., McCabe, B. and Hartono, L. (2003). 'Evaluating Risk in Construction-Schedule Model (ERIC-S): Construction Schedule Risk Model.' Journal of Construction Engineering and Management, 129(5), ASCE, pp.518-527   DOI   ScienceOn