An Administration Model for Causation of the Schedule Delays in Construction Projects  

Kim, Jong-Han (아주대학교 건축학부)
Kim, Kyung-Rai (아주대학교 건축학부)
Publication Information
Korean Journal of Construction Engineering and Management / v.8, no.3, 2007 , pp. 125-133 More about this Journal
Abstract
If project time extension were required in the construction projects, either liquidated damages or extension costs should be applied according to causation of the schedule delays. However, in actual cases it is not applied so far according to the contract conditions. The reason why this situation happened Is that function of the present planning and scheduling is not working feasibly. The CPM schedule could not provide a proper solution for apportioning responsibility for the schedule delays. This situation could be considered as breach of contract and will cause potential disputes for schedule delay. Therefore, in this research process based contract administration model for construction delay claim is proposed to prevent schedule delay and solve the claims. The model is based on pro-active management for causation of delay to provide apportionment of responsibility and written evidences.
Keywords
Project time extension; Delay claims; Causation of the schedule delays;
Citations & Related Records
연도 인용수 순위
  • Reference
1 한종관외 2인, / 시공자 중심의 주요 공종별 공기지연 원인 분석에 관한 연구, 대한건축학회논문집 통권173호, 2003
2 Schumacher, L., Quantifying and Apportioning Delay on Construction Projects, Cost Engineering, 37(2), 11- 13
3 Yates J. K, Avoiding and Minimizing Construction Delay Claim Disputes in Relational Contracting, Journal of Professional Issues in Engineering Education and Practice, 2006, 4
4 Zark James G. Jr., 'Claim Prevention: Offence versus Defense', Cost Engineering, Vol. 39, No. 7, 1997
5 구자민, 이재섭, '생산성을 고려한 공기지연분석방법', 대한건축학회논문집 20권 4호, 2004
6 Departmeny of army, Office of the Chief of Engineers' Modification Impact Evaluation Guide, Ep-415-3
7 이재섭, 건설공사의 공기연장분석기준, 한국건설산업연구원, 1999
8 이재섭, 계약당사자 모두에게 책임이있는 공기지연의 해석방 법, 대한건축학회논문집 통권202호, 2005
9 FIDIC, Constructions of Contract for Construction, 1999
10 Abdul-Malak, M. Asem U, Process Model for Administrating Construction Claims, journal of management in engineering, 2002, 4
11 이정호외 3인, 웹기반의 공기지연클레임 분석모형 구축에 관 한 연구, 대한건축학회논문집 통권170호, 2002
12 Shi Jonathan Jingsheng, Construction Delay Computation Method, Journal of Construction Engineering and Management 2001, 1
13 모용운외 2인, '국내 공공건설공사 공기지연분석모델 개발', 대한건축학회 논문집(구조계), 18(2), 131-138
14 주해금외 2인, '위험관리 중심의 공정관리모델', 한국건설관리학회논문집 제6권 제6호, 2005
15 이상범, '공정균형개념을 적용한 공기산정방법에관한 연구', 대한건축학회논문집 구조계 V.17 n,9, 2001
16 Veterans Admin, VACPM Handbook H-08-11
17 김재욱외 1인, '국내 회계예규상의 공기지연 클레임 관련사항 의 개선방안', 한국건설관리학회 학술발표대회 논문집, 2002
18 김영재외 3인, '건설공사 공기지연클레임의 분석방법에 관한 연구', 대한건축학회논문집 구조계 15권7호(통권129호) (1999-7)
19 조훈희외 2인, 공기연장 실태조사를 통한 발주자중심 공기지연 리스크 대응방안(공공발주 공동주택대상으로), 대한건축학회논문집 통권158호, 2001
20 Kim Youngjae, Delay Analysis Method Using Delay Section, Journal of Construction Engineering and Management, 2005, 11
21 Kelleher, T.H., 'Common Sense Construction Law', 3rd Ed., John Wiley & Sons, Inc., 2005
22 Cheung Sai On, Are Construction Disputes Inevitable?, IEEE transactions on engineering management, vol. 53, no. 3, 2006, 8
23 윤성민외 3인, 경부고속철도 건설사업의 공기지연분석에 관한연구