A Study on Simulation Numerical Formula Model for Construction Process Efficiency  

Park, Jong-Hyuk (서일대학 토목과)
Jeon, Yong-Bae (한중대학교 토목환경공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.8, no.1, 2007 , pp. 87-95 More about this Journal
Abstract
If construction process operate composing work team by judgment manager's experience, possibility that progress of construction process becomes as inefficient is much. But, If produce optimal proposal of resources allocation, construction cost and duration through simulation at work plan step, work schedule because do quantification efficient operate do on. When plan construction process in this research, resources allocation by change of work team operation change, resources cost loss, total cost, optimal proposal of construction duration tentative plan of numerical formula model that can do simulation propose. Apply and revealed to apartment house framework which horizontal work area of process and vertical work area are composed as is each different construction process to verify proposed numerical formula model. Achieved efficiency than work team's operation results which apply numerical formula model that is presented in this research and enforce simulation is applied in actuality example construction.
Keywords
Construction Process; Simulation; Resource allocation by Change; Numerical Formula Model;
Citations & Related Records
연도 인용수 순위
  • Reference
1 김경주(2000), '건설공정 시뮬레이션을 위한 독립자원 모델 구축 방안 연구', 대한토목학회 논문집 제20권 제4-D호
2 신현식(1995), '공사관리 핸드북',태림문화사,pp. 139-151
3 Ming Lu and s.M.AbouRizk(2000),'Simplified CPM/PERT Simulation Model', Journal of Construction Engineering and Management. vol.126,no.3,pp219-226   DOI   ScienceOn
4 Robert B. Harris(1978),'precedence and Arrow Networking Techniques for Construction', Jon Wiley & Sons. pp254-312
5 長岡弘明 外3(1997), '繰り反し型工事におけるマイルスト-ンを 用いた 工程計劃.管理方法', 日本建築學會計劃系 論文集 第492號,pp. 171-177
6 한국건설산엽연구원(1997), '건설관리 및 경영 제1편 : 이론', 보성각,pp. 293-295
7 Olusegun 0. Faniran, Perter E.D.Love and Heng Li(1999),' Optimal Allocation of Construction Planning Resources', Journal of Construction Engineering and Management, vol. 125, no. 5, pp311-319   DOI
8 Jaeho Son and Miroslaw J.Skibniewski(1999),' Multiheuristic Approach for Resource Leveling Problem in Construction Engineering', Journal of Construction Engineering and Management, vol.125,no.l,pp23-31   DOI   ScienceOn
9 이배호(2000), '건설공사관리 이론과 실제',구미서관,pp. 116-145
10 대한건설협회(2006), '2006 상반기적용 건설업 임금실태조사 보고서' ,pp8-pp12, (http://cak.or.kr/)(2006,10)