A Competitive Advantage Analysis of Construction Duration through the Comparison of Actual Data of Domestic Construction Firms - Focused on Mix-Use Residential Building and Officetel Building -  

Ryu, Han-Guk (서울대학교 건축학과)
Kim, Sun-Kuk (경희대학교 토목건축대학)
Lee, Hyun-Soo (서울대학교 건축학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.7, no.1, 2006 , pp. 138-147 More about this Journal
Abstract
Construction companies have been interested in the construction duration which importantly affects the performance and the success of the construction projects in accordance with the systemic changes such as five days per week system, introduction of construction duration reduction bidding system and post sale system nowadays. It is also very important to estimate and forecast properly the construction duration as the construction companies compete for the projects in the situation of construction market reduction and the lowest bidding system. Recognizing the importance about the construction duration, the researches about comparing and analyzing or estiamting the construction duration have been performed. However, comparing studies about the construction duraion have been limited to the apartment and office building in domestic area. Many studies about forecasting construction duration have been performed through stochastic analysis and simulations. Little research has been addressed the comparison analysis of the real construction duration about the mix-use building and officetel building which occured according to the changes of the building requirements. Therefore, the objective of this study is to compare and analyze the real construction duration and the hypothetical construction duration about the mix-use building and officetel building of the domestic companies. Moreover, we select the most competitve construction company to get the strengths and analyze the competitive advatages of the construction companies about construction duration.
Keywords
Construction Duration Reduction; Construction Duration Comparison; Construction Duration Calculation; Construction Duration Competitiveness; Mix-Use Residential Building; Officetel Building;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 AbouRizk, S.M., and Halpin, D.W., 'Statistical properties of construction duration data', J. Constr. Engrg. and Mgmt., ASCE, 1992, 118(3), pp.525-544   DOI
2 Carr, R. I., 'Simulation of construction project duration', J. Constr. Div., Proceedings of ASCE, 1979, 105(CO2), pp.117-128
3 Lee, D.E., 'Probability of project completion using stochastic project scheduling simulation', J. Constr. Engrg. and Mgmt., ASCE, 2005, 131(3), pp.310-318   DOI   ScienceOn
4 Syal, M. G., and Grobler, F., Willenbrock, J. H., and Parfitt, M. K., 'Construction project planning process model for small-medium builders', J. Constr. Engrg. and Mgmt., ASCE, 1992, 118(4), pp651-666   DOI
5 권오현, 최민수, 한국건설산업연구원, 건설상품별 중장기 시장전망(II), 2004. 12
6 정석남, 이학기, '가상기후 시뮬레이션에 의한 공기산정 의사결정 지원모델에 관한 연구', 건설관리학회지, 한국건설관리학회, 제1권 제4호, 2000.12, pp. 74-81
7 정인수외 3인,' 군시설 공사의 순공사기간 예측모형에 관한 연구', 대한건축학회논문집 구조계, 제 16권 제9호, 2000.9. pp. 67-74
8 한태곤, 김영수, '퍼지 집합 이론을 이용한 액티비티 공기 산정 방안', 대한건축학회논문집 구조계, 제 16권 제3호, 2000.3. pp. 93-101
9 황효상 외 4인, '공기산정 영향요인별 실적공기 비교분석-사무소 건축공사 공기산정기준을 중심으로', 건설관리학회지, 한국건설관리학회, 제3권 제3호, 2002.9, pp. 84-93
10 Ahuja, H.N. and Nandakumar,V., 'Simulatio model to forcast project completion time', J. Constr. Engrg. and Mgmt., ASCE, 1985, 111(4), pp.325-342   DOI   ScienceOn
11 김상중, 이재섭, '확률적 공기산정에 의한 공정계획 합리화 방안', 건설관리학회지, 한국건설관리학회, 제5권 제4호, 2004.12, pp. 79-86
12 Akinsola, A. O., Potts, K. F., Ndekugri, I., and Harris, F. C.,' Identification and evaluation of factors influencing variations on building projects', International Journal of Project Management, Elsevier Science Ltd and IPMA, 1997, 15(4), pp.1263-267
13 이상범, '공정균형 개념을 적용한 공기산정 방법에 관한 연구', 대한건축학회논문집 구조계, 제 17권 제9호, 2001.9. pp. 233-240
14 Schexnayder, C., Knutson K., and Fente, J., 'Describing a beta probability distribution function for construction simulation', J. Constr. Engrg. and Mgmt., ASCE, 2005, 131(2), pp.221-229   DOI   ScienceOn
15 Proverbs, D. G., Holt G. D., Olomolaiye, P.O., 'Factors impacting constructin project duration : a comparison between France, Germany and the U.K.', Building and Environment 34, Elsevier Science Ltd, 1999, pp197-204