A Study on Estimation Model of Construction Duration for Public Construction  

Kim, Byeong-Soo (국립상주대학교 토목공학과)
Chun, Jin-Ku (삼안기술개발연구원)
Publication Information
Korean Journal of Construction Engineering and Management / v.6, no.6, 2005 , pp. 142-151 More about this Journal
Abstract
On public constructions, that the first planed projects delay than the scheduled completion day occurrence frequently because gap between the scheduled construction durations and the actual construction durations. These facts connect with not only problems of the construction during as the construction delay but also brought about the distribution costs increase as the failure of facility use plan and the people discomfort weight, failure of the production and the supply using facility then tremendous loss of each part etc. For reduce these loss, it must improve accuracy of the scheduled construction duration estimating when it order. This study try contribute to a successful manage of public project and reduce the construction duration extension frequent of the construction during, and then ensure the suitable construction duration by present the estimation model of the scheduled construction duration that include the construction duration correct element using as an index on the scheduled construction duration estimation.
Keywords
the scheduled construction duration; the estimation procedure model of the construction duration; duration extension; the construction duration correct element;
Citations & Related Records
연도 인용수 순위
  • Reference
1 공익사업을 위한 토지 등의 취득 및 보상에 관한 법률, 2002
2 최인환 외1인, [정성적 요소를 고려한 공사기간산정], 건설기술연구소논문집, 1999.12
3 한국토지공사 단지조성설계 및 적산기준, 2004
4 강인석 외4인, [공사일정상의 외부리스크를 고려한 예비비 및 예비공기 산정], 대한토목학회 논문집, 2000.9
5 신종웅 외1인, [지하철공사 공정산정 기준분석], 대한 토목학회 학술발표논문집, 1996
6 공사계약일반조건, 1999.9.9
7 손창백 외2인, [지하철공사에 있어 공기증가가 공사원가에 미치는 영향에 관한 연구], 대한건축학회논문집, 1999.6
8 구해식 외1인, [건축공사의 기후요소에 대한 공기산정 방안연구], 대한건축학회논문집, 1999.11
9 기상청홈페이지 http://www.kma.go.kr/index.jsp