Optimization of Estimating Duration of the Structural Frame for the High-rise Apartment Housing during the Winter season -Focusing on One Cycle Time Scheduling Mechanism of the Typical Floor-  

Bang Jong-Dae (경희대학교 건축공학과)
Han Choong-Hee (경희대학교 건축공학과)
Kim Sun-Kuk (경희대학교 건축공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.5, no.6, 2004 , pp. 170-178 More about this Journal
Abstract
Public construction companies have strictly followed a rule that they should not work in the wet area such as structural frame for a certain period during the winter season. It is usually known that the non-working period during the winter causes increase of the project duration, and the project cost escalation. Also, it makes negative effects on national economy because it reduces workers income. Therefore, the site work for the structural frame should be performed even during the whiter season. But the site work for the structural frame during that period cannot proceeds in the same way as during other periods, and requires a different method for estimating project duration. Through an analysis of time scheduling mechanism, actual working days are obtained for 1 cycle of typical floors in the structural frame during these periods, and non-working days of 5 years average are calculated based on calendar day using data of 5 years weather forecasts for that season. This study proposes an optimized way of estimating project duration for 1 cycle of typical floors in the structural frame during these periods. This estimating method uses the combined actual working days and non-working days of 5 years' average, and the estimated results are confirmed by being compared with field data. This study is expected to be used in estimating the construction duration of the structural frame during the winter season.
Keywords
non-working days; non-working periods; actual working days; winter season; time scheduling mechanism;
Citations & Related Records
연도 인용수 순위
  • Reference
1 한충희, 아파트 골조공사의 공기단축 및 효과적 공정운영방안, 2004.8, 건설관리학회 논문집 제5권 저14호(통권 제20호)
2 이준호, 거푸집 작업조를 중심으로 하는 공동주택 철근 콘크리트 공사의 공정계획방법, 1996.4, 대한건축학회 논문집 12권 4호 통권 90호
3 정인환, 아파트 공사의 주요 공종별 공정 및 생산성 분석, 1995.4, 대한건축학회 논문집 11권 4호 통권 78호
4 진영섭, 아파트 공사기간 산정에 영향을 주는 작업불가능 기준에 관한 연구, 1998.4, 대한건축학회 학술발표논문집 제 18권 제1호
5 신종현, 공동주택 골조공사의 적정 공사계획 시스템, 2003. 11, 대한건축학회 논문집 구조계 19권 11호 통권181호
6 ACI Committee 209, 'Prediction of creep, shrinkage, and temperature effects in concrete structures', 1992
7 대한주택공사, 건설공사의 적정 표준공사기간 산정방법에 관한 연구, 1998, 12