A Control Account Planning Using Material Requirement Planning in Earned Value Project  

Kim Soo-Yong (부경대학교 산업공학과)
Lee Yang-Ho (효성건설(주)공사팀)
An Dong-Geun (포스코건설 건설기술연구팀)
Publication Information
Korean Journal of Construction Engineering and Management / v.3, no.4, 2002 , pp. 114-122 More about this Journal
Abstract
Earned Value Management System(EVMS) is a management technique that is emerging as a valuable tool in the management of all projects, including and in particular construction projects. It is based on C/SCSC that has been released by the U.S. Department of Defense (DOD) in 1967. In a project that employs the earned value management concept, the project's measurable performance plans will be formed with the creation of CAPs. The formation of CAPs is a planning step necessary to form an earned value baseline. In this paper, a method is proposed to form CAPs using Material Requirement Planning(MRP) that is also known as a useful planning tool in the manufacturing industry. An application to a real project has been carried through workpackaging model.
Keywords
EVMS; MRP; MPS(Master Production Schedule);
Citations & Related Records
연도 인용수 순위
  • Reference
1 강성수외 공역, '생산시스템 운영관리' 사이텍미디어, 2001
2 이명호, 유지수 '경쟁우위확보를 위한 생산관리' 박영사, 1999
3 정남기, 유철수, 'CALS 시대 생산관리', 청문각, 1998
4 CII, 'Work Packaging For Project Control', Construction Industry Institute(CII), The University of Texas at Austin, 1997
5 EIA Engineering Dep, 'Earned Value Management Systems (ANSI/EIA-748)', EIA(Electronic Industries Alliance), 1998
6 http://www.suu.edu/faculty/christensend/evbib.html. Comprehensive Bibliography of EV Articles
7 Christensen, David S., 'Determining an Accurate Estimate at Completion', National Contract Management Journal 25: 17-25, 1993
8 김양택, 현창택, 'Work Packaging Model의 개선을 통한 공정 - 공사비 통합모텔구축' 건설관리학회지 한국건설관리학회, 제1권 제4호, 2000, pp.82-90
9 PMBOK, 'A Guide to the Project Management Body of Knowledge', Project Management Institute, 2000
10 Christensen, David S., 'Using The Earned Value Cost Management Report to Evaluate the Contractor's Estimate at Completion, Acquisition Review Quarterly, pp.283-291, 1999
11 Primavera Korea, 'P3 Manual', Primavera, 2000
12 이유섭, '건설공사 EVMS적용방안', 한국건설기술연구원, 2001
13 Fleming, Quentin W. and Koppelman, Joel M., 'Earned Value Project Management', Project Management Institute, 2000
14 건설교통부, '건축공사 . 기계설비공사 수량산출기준', 2000
15 Ahuja, Hira N. and Dozzi, S. M. Abourizk, 'Project Management' (2nd), JOHN WILEY & SONS, INC. 1994
16 http://www.acq.osd.mil/pm/. EVM Official Web site
17 http://www.dmo.defence.gov.au/esd/evm/index.cfm. EarnedValue Web Site for Australia
18 김선규, 김재준, 'EVMS 최종공사비 예측 모델 최적성과 지수에 대한고찰', 건설관리학회지 한국건설관리학회, 제1권 제3호(통권 제3호), 2000, pp.101-107
19 건설교통부, '건설사업관리업무지침', 2001
20 최윤기, '일정과 비용을 통합한 건설공사 진도율 산정 시스템' 박사학위논문, 서울대학교, 1999