Cost Management System for Mechanical, Electrical, and Plumbing(MEP) Coordination Using Building Information Modeling(BIM) - A Case Study  

Won, Jongsung (Department of Architecture, Korea National University of Transportation)
Ham, Sungil (Department of Architecture, Engineering, Jeonju University)
Jang, Sejun (Department of Architectural Engineering, Kyungil University)
Publication Information
Journal of the Korea Institute of Building Construction / v.22, no.2, 2022 , pp. 195-205 More about this Journal
Abstract
This paper aims to propose a cost-based mechanical, electrical, and plumbing(MEP) coordination process using building information modeling(BIM). The proposed process can help project participants eliminate identified clashes between the MEP elements, analyze trends relating to MEP costs during the coordination process, and share their findings. MEP quantity-related information extracted through BIM was integrated with the cost database and schedule information. To check the applicability of the proposed process, it was applied to a construction project in South Korea. Through the application of the proposed process, MEP-related cost was reduced.
Keywords
building information modeling(BIM); mecanical.electrical and plumbing(MEP) coordination; cost management;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Lee G, Park KH, Won JS. D3 city project - economic impact of BIM-assisted design validation. Automation in Construction. 2012 Mar;22:577-86. https://doi.org/10.1016/j.autcon.2011.12.003   DOI
2 Tabesh AR, Staub-French S. Case study of constructability reasoning in MEP coordination. Construction Research Congress 2005; 2005 Apr 5-7; San Diego, CA. Reston (VA): American Society of Civil Engineers; 2005. p. 1-10. https://doi.org/10.1061/40754(183)119   DOI
3 Tatum CB, Korman TM. MEP Coordination in Building and Industrial Projects. Stanford (CA): Stanford University; 1999. 51 p. Report No.: TR54.
4 Mahanim H, Lauri K, Mohan S. Traditional cost management vs. lean cost management. Proceedings of the 18th CIB World Congress; 2010 May 10-13; Salford, United Kingdom. Kanata (Canada): CIB Publication; 2010. p. 280-93.
5 Khanzode A, Fischer M, Reed D. Benefits and lessons learned of implementing building virtual design and construction (VDC) technologies for coordination of mechanical, electrical, and plumbing (MEP) systems on a large healthcare project. Electronic Journal of Information Technology in Construction. 2008 Jun;13:324-42.
6 Pishdad-Bozorgi P, Moghaddam, EH, Karasulu Y. Advancing target price and target value design process in IPD using BIM and risk-sharing approaches. Proceedings of 49th Annual International Associated School of Construction; 2013 Apr 10-13; San Luis Obispo, CA. Cheyenne (WY): the Associated Schools of Construction; 2013. p. 1-9.
7 Tatum CB, Korman TM. Coordinating building systems: process and knowledge. Journal of Architectural Engineering. 2000 Dec:6(4):116-21. https://doi.org/10.1061/(ASCE)1076-0431(2000)6:4(116)   DOI
8 Gao J, Fischer M. Framework and case studies comparing implementations and impacts of 3D/4D modeling across projects. Stanford (CA): Stanford University; 2008. 113p. Report No.:TR172.
9 Khanzode A. An Integrated, Virtual Design and Construction and Lean (IVL) Method for Coordination of MEP. Stanford (CA): Stanford University; 2010. 35 p. Report No.: TR187
10 Leite F, Akinci B, Garrett JJ. Identification of data items needed for automatic clash detection in MEP design coordination. Construction Research Congress 2009; 2009 Apr 5-7; Seattle, WA. Reston (VA): American Society of Civil Engineers; 2009. p. 416-25. https://doi.org/10.1061/41020(339)43   DOI
11 Sacks R, Radosavljevic M, Barak R. Requirements for building information modeling based lean production management systems for construction. Automation in Construction. 2010 Aug:19(5):641-55. https://doi.org/10.1016/j.autcon.2010.02.010   DOI
12 Korman TM, Tatum CB. Prototype tool for mechanical, electrical, and plumbing coordination. Journal of Computing in Civil Engineering. 2006 Jan:20(1):38-48. https://doi.org/10.1061/(ASCE)0887-3801(2006)20:1(38)   DOI
13 Won JS, Cheng JCP, Lee G. Quantification of construction and demolition waste prevented by BIM-based design validation: case studies in south korea. Waste Management. 2016 Mar;49:170-80. https://doi.org/10.1016/j.wasman.2015.12.026   DOI
14 Korman TM, Fischer M, Tatum CB. Knowledge and reasoning for MEP coordination. Journal of Construction Engineering and Management. 2003 Dec:129(6):627-34. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:6(627)   DOI