Probabilistic Earlier GMP Calculation Method for Apartment Using CM at Risk  

Hyun, Chang-Taek (Department of Architectural Engineering, University of Seoul)
Go, Gun-Ho (Department of Architectural Engineering, University of Seoul)
Jin, Zhengxun (Department of Architectural Engineering, University of Seoul)
Publication Information
Journal of the Korea Institute of Building Construction / v.18, no.3, 2018 , pp. 295-303 More about this Journal
Abstract
In the DBB delivery system, the design stage and the construction stage are separated. Because of this, design changes frequently occur, and problems such as construction cost overrun, schedule delay, and quality deterioration happen as well. Recently, in the construction industry CM at Risk(CM@R) delivery system, which can systematically solve the above-mentioned problems of DBB delivery system, meet various demands of clients, and overcome the limited cost and period. In the CM@R delivery system, the contractor negotiates for a maximum guaranteed price(GMP) with the client at the design stage, and the CM performer carries out the construction within the GMP. However, uncertainties are inherent in the GMP calculation because the calculation is based on unfinished drawings and documents. In this study, a Probabilistic Earlier GMP Calculation Method by combining a probabilistic tool of Monte Carlo simulation with a case based reasoning is proposed so that the uncertainty in GMP calculation is reflected. After the earlier GMP is calculated, a process to calculate the $2^{nd}$ GMP at the time of around 80 % of detailed deign and to negotiate with the client to fix the final GMP is proposed. The Probabilistic Earlier GMP Calculation Method is verified through the case study. In this study, researchers set the range of GMP through the proposed probabilistic GMP calculation and tried to reduce the risk through negotiation between the client and the CM performer. The proposed method and process would contribute to the successful introduction of CM@R in Korea.
Keywords
CM at risk; CBR; GMP scope; probabilistic earlier GMP calculation; consultation;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Ahn YH, Lee SY. Application of the preconstruction services in the CM at risk delivery system. construction engineering and management. 2016 Dec;17(6):27-30.
2 Shin SH. A plan for application of CM at risk to the public construction sector in Korea [master's thesis]. [Seoul (Korea)]: University of Seoul; 2004. 120 p.
3 Koo SK. Risk factor assessment for guaranteed maximum price contract in CM at risk [master's thesis]. [Seoul (Korea)]: University of Seoul; 2017. 115 p.
4 Lee KD. A Study on the Analysis of main Barriers for the Activation of CM at Risk in the Domestic Construction Industry [master's thesis]. [Daegu (Korea)]: Kyungpook National University; 2015. 67 p.
5 Jung JH. Cost prediction model based on random forest using CBR for early construction stage [master's thesis]. [Seoul (Korea)]: University of Seoul; 2017. 114 p.
6 Jin ZX. Stochastic hybrid cost prediction model of construction project in early stage [master's thesis]. [Seoul (Korea)]: University of Seoul; 2014. 105 p.
7 Koh MH. A feasibility study for introduction of 'CM at risk' in the public construction [master's thesis]. [Suwon (Korea)]: Sungkyunkwan University; 2009. 64 p.
8 Kim WY. The introduction and implications of CM at risk. Construction Engineering and Management. 2016 Jun;17(3):17-21.
9 Dogan SZ, Arditi D, Gunaydin HM. Determining attribute weights in a CBR model for early cost prediction of structural systems. Journal of Construction Engineering and Management. 2006 Oct;132(10):1092-8.   DOI
10 Kim YS. MRA revision model based on CBR for cost prediction in early stage [master's thesis]. [Seoul (Korea)]: University of Seoul; 2010. 92 p.
11 Hyun CT, Lee HS, Lee SH, Ji SM. Framework of construction cost estimating system in public housing. construction engineering and management. 2011 Oct;11(5):33-7.
12 Ministry of Land, Transport and Maritime Affairs. Development of innovative construction cost engineering system for public construction projects in Korea. Gwacheon(Korea): Ministry of Land, Transport and Maritime Affairs; 2011 may. 215 p. Report No.: 1615001603.