A Case Study on Productivity Analysis and Methods Improvement for Masonry Work  

Chang, Chul-Ki (Department of Architectural Engineering, Hannam University)
Yoo, Wi Sung (Construction Management Division, Construction & Economy Research Institute of Korea)
Publication Information
Journal of the Korea Institute of Building Construction / v.13, no.4, 2013 , pp. 372-381 More about this Journal
Abstract
In the construction industry, a great deal of research has been focused on productivity improvement because a minor change in labor productivity can often make the difference between a profit and a loss. This study shows how productivity measurement methods can be applied in practice, step by step, to analyze and identify potential problems both in productivity and methods performance for masonry work. A work sampling technique was conducted to determine the nature and extent of an observable activity as an aid to measuring overall performance. Also, a method productivity delay model was used to identify non-productivity in individual cycle times. From the work sampling technique, it was found that the masonry crew had a Labor Utilization Factor of 47.1%, and from the videotape analysis, it was found that the material and dumpster location need to be adjusted to reduce the travelling distance. We have found that efforts to improve the productivity of masonry work should be focused almost exclusively on machine and labor delays, based on the result from the method productivity delay model.
Keywords
labor; delay; masonry work; productivity analysis; work sampling;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Joo JK, Kim TH, Kim SK. A Work Model for Enhancing the Productivity of Rebar Work. Journal of Architectural Institute of Korea. 2003 Dec;19(12):189-96.   과학기술학회마을
2 Jang JS, Shin YS, Kang KI. A Work Process for Productivity Improvement of Concrete Structural Frame Work in Tall Building. Journal of the Korea Institute of Building Construction. 2005 Mar;5(1):161-4.   DOI   ScienceOn
3 Kim BJ, Shim HW, Lee, UK, Choi HB, Kang KI. Rebar Work Improvement Method using Work Measurement in Apartment Building Construction-Focusing on Work Sampling and Crew Balance Study. Proceeding of Annual Conference; 2006 Oct 26-27; Yeungnam University. Seoul (Korea): Architectural Institute of Korea; 2006. p. 441-4.
4 Yoon JY, Kim YS, Kim JJ. Suggestion Improvement Based on Form Work Productivity Analysis in Apartment Housing Construction. Journal of the Korea Institute of Building Construction. 2010 Oct;12(5):49-56.   과학기술학회마을   DOI   ScienceOn
5 Lee TH, Ko YH, Kim YS, Han SW. Comparison of the Application of Various Productivity Analysis Methods for a Curtain Wall Operation in High-rise Building Construction. Proceeding of Korea Institute of Building Construction; 2011 May 20; Dong-Eui University. Seoul (Korea): the Korea Institute of Building Construction; 2011. p. 211-2.
6 Kim YS, Cha TS, Hwang KN, Choi YS. A study on the Improvement of Construction Work Efficiency by Work Sampling Technique. Journal of Architectural Institute of Korea. 1997 Jul;13(7):233-41.   과학기술학회마을
7 Sanders S, Thomas H. Masonry Productivity Forecasting Model. Journal of Construction Engineering and Management. 1993 Mar;119(1):163-79.   DOI
8 Oglesby CHP, Henry W, Howell GA. Productivity Improvement in Construction. New York (NY): McGraw-Hill; 1989. 343 p.
9 Prokopenko J. Productivity management: A Practical Handbook. Geneva (switzerland): International Labour Organization; 1987. 291. p.
10 Ahn SH, Yu JH, Kim CD. The Work Condition Management Method for Improvement of Work Efficiency. Journal of Architectural Institute of Korea. 2008 Apr;24(4):183-90.   과학기술학회마을
11 Jung HK, Yun YW, Yang KY. A Study on the Productivity of Form Work by Using Work Analysis Method. Journal of the Korea Institute of Building Construction. 2005 Dec;5(4):131-7.   DOI
12 Thomas H, Maloney W, Horner R, Smith G, Handa V, Sanders S. Modeling Construction Labor Productivity. Journal of Construction Engineering and Management. 1990 Dec;116(4):705-26.   DOI
13 Kim TH, Joo JK, Kim SK. Proposal of Plan for the Deck Plate Slab Construction on Productivity Improvement. Journal of Architectural Institute of Korea. 2000 Dec;16(12): 75-82.   과학기술학회마을
14 Lee JN, Son CB. An Analysis of Work Ration for Construction Curtain Wall by Work Sampling Technique. Proceeding of Annual Conference; 2003 Oct 24-25; Pukyong National University. Seoul (Korea): Architectural Institute of Korea; 2003. p. 519-22.
15 Tommelein ID, Riley DR, Howell GA. Parade Game: Impact of Work Flow Variability on Trade Performance. Journal of Construction Engineering and Management. 1999 Sep;125(5):304-10.   DOI
16 Reinschmidt K, Trejo D. Economic Value of Building Faster. Journal of Construction Engineering and Management. 2006 Jul; 132(7):759-66.   DOI   ScienceOn