Analysis of Structural Work Scheduling of Green Frame - Focusing on Apartment buildings -  

Lee, Sung-Ho (Department of Architectural Engineering, KyungHee University)
Kim, Shin-Eun (Department of Architectural Engineering, KyungHee University)
Kim, Gwang-Hee (Department of Architectural Engineering, Kyonggi University)
Joo, Jin-Kyu (Department of Architectural Engineering, KyungHee University)
Kim, Sun-Kuk (Department of Architectural Engineering, KyungHee University)
Publication Information
Journal of the Korea Institute of Building Construction / v.11, no.3, 2011 , pp. 301-309 More about this Journal
Abstract
Apartment housings that adopt a bearing wall structure design, which account for a majority of the housing units available in Korea, are not free from structural constraints that limit the extension of their service life. The resulting need for reconstruction from the ground up requires a massive consumption of resources and energy, and triggers environmental pollution resulting from construction wastes. As a solution to such issues, the government enforces incentive schemes to promote a remodeling-friendly rahmen structure design. Green Frame, which is a novel concept of composite precast concrete structure to support rahmen structure apartment housing buildings, can address the constraints of bearing wall structure and conventional rahmen structure designs that limit the potential for remodeling projects, while reducing the term of construction. Therefore, this study aims to analyze the characteristics of Green Frame and its absolute term of construction, and compare the terms of frame work construction in apartment housing projects adopting different structural design approaches to illuminate their differences. In the end, Green Frame is found to be capable of reducing the term of construction in apartment housing projects. As the term of construction is a very critical element of a construction project, Green Frame will ultimately prove to be one of the key enablers to ensure the success of apartment housing construction projects.
Keywords
green frame; structural work; scheduling; apartment buildings;
Citations & Related Records
Times Cited By KSCI : 5  (Citation Analysis)
연도 인용수 순위
1 Han CH, Bang JD. [Development of an effective time scheduling mechanism of the structural framework for the high-rise Apartment Housing Focusing on One Cycle time scheduling mechanism of typical floor]. Korea Journal of Construction Engineering and Management. 2004 Jul;15(4): 87-96. Korean.   과학기술학회마을
2 An SH, Kim GH, Kim JY, Park HI, Jung BW. [A Study on 3-Day Cycle Time for Reducing the Duration of Structural Frame Work Focused on High-rise Building Construction]. Review of Architecture and Building Science. 2007 May;23(5):203-10. Korean.   과학기술학회마을
3 Hong WK, Kim SK, Kim HG, Yoon TH, Yoon DY, Kim SI. [A Feasibility Study of Green Frame (GF) for the Implementation of Low-carbon Emissions & Long-life Housing]. Journal of the Korea Institute of Building Construction. 2010 May;10(1):57-63. Korean.   과학기술학회마을   DOI   ScienceOn
4 Hong SW, Park SH, Bae KS, Lee DJ, Son CB, Lee MK. [Economic analysis of the multi-family housing applied to flat plate wall system]. Review of Architecture and Building Science 2008 Dec;10(4):265-72. Korean.
5 Kim SH, Lee WK, Kim SK, Lee DH. [Development of Form to improve productivity of PC structure connection]. Journal of the Korea Institute of Building Construction. 2010 Oct;10(5):11-20. Korean.   DOI
6 Proverbs DG, Holt GD, Olomolaiye PO. Factors impacting construction project duration a comparison between France, Germany and the U.K. Building and Environment 1998 Mar;34(2):197-204.   DOI   ScienceOn
7 Lee SH, Kim SK, editors. A composite frame concept for the long life of apartment buildings. Proceedings of the 4th International Conference on Construction Engineering Project Management; 2011 Feb 16-18; Sydney, Australia. Sydney (Australia): University of New South Wales; 2011. p.38.
8 Hong SW, An YK, Park SH, Bae KS, Lee DJ, Son CB, Lee, MK. [A Study on the analysis of construction planning & scheduling in the similar case related Long-life Housing Focused on the FPWS(Flat Plate Wall System) multi-family housing]. Review of Architecture and Building Science. 2008 Mar;10(1):239-47. Korean.
9 Hong SW, Park SH, Kim SW, An JK, Son CB, Lee DJ, Lee MK. [Analysis of construction planning and scheduling in the mock-up house for practicality of Long Life Housing]. Review of Architecture and Building Science. 2009 jul;25(7):145-52. Korean.   과학기술학회마을
10 Hong WK, Park SC, Kim JM, Kim SI, Lee SG, Yun DY, Yoon TH, Ryoo BY. Development of Structural Composite Hybrid Systems and their Application with regard to the Reduction of $CO_2$ Emissions. Indoor and Built Environment. 2010 Feb; 19(1):151-62.   DOI   ScienceOn
11 Construction Economy Research Institute of Korea (KR). Efficiency Improvement of housing production system: the report of the Construction Economy Research Institute of Korea. Seoul (Korea): Construction Economy Research Institute of Korea; 2003 Jun. 186 p. Korean.