A Study on the Work Crew Based for the Estimation from Construction Analysis of Cement Liquid Waterproofing in Apartment House  

Ha, Gee-Joo (경일대학교 건축학부, 사)건설기술정책연구원)
Ha, Min-Su (사)건설기술정책연구원)
Publication Information
Journal of the Korea Institute of Building Construction / v.10, no.3, 2010 , pp. 121-128 More about this Journal
Abstract
This study aims to make improvements to the standard estimation process used to estimate reasonable costs for construction work, and to suggest a work crew based estimation using a new cost estimation model. In addition, work crew shift combination and construction process were systematically organized in order to improve the estimation technique and the construction capability of the cement liquid waterproofing work for apartment buildings. In addition, in terms of manpower and productivity, analyses were performed on the cement liquid waterproofing work for apartment buildings with net areas between $84-85m^2$ and $125-184m^2$, and the results were then compared with those calculated using the conventional work-crew based estimation method. Through this study, when the results of this study and those calculated by the conventional method were compared, for apartments with the net area of $84-85m^2$, the differences between specialists were shown to be 1.91 times to 2.13 times on average, while they were 8.82 times to 9.52 times between normal workers on average. For apartments with the net area of $125-184m^2$, the differences betweenspecialists were shownto be 1.89 times to 2.07 times on average, and 8.57 times to 9.38 times on average between normal workers.
Keywords
Standard Estimating; Work Crew; Cement Liquid Waterproofing Construction; Productivity; Labor;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 류춘성.장세한.김경래.임국일, 국내 건설산업에서의 적정공사비 개념과 기준에 관한 연구 대한건축학회 논문집(구조계), 제18권 제3호, 2002.3
2 신진수, 작업조 및 일정을 고려한 상세설계단계의 적산방법 개선에 관한 연구 경희대학교, 2003.2
3 유용환·이규헌·김종원·최인성, 공동주택 실적공사비 산정시 공종별 변동요인에 관한 연구 한국건축시공학회 논문집, 제4권 제4호, 2004.12   과학기술학회마을   DOI
4 작업조 기반 차세대 Cost data 개발 연구보고서, (사)건설기술정책연구원, 2007
5 작업조 기반 차세대 Cost data 개발 연구보고서, (사)건설기술정책연구원, 2008
6 전상훈·구교진, 공동주택 골조공사의 표준품셈 노무량과 실투입 노무량 비교, 한국건설관리학회, 2008
7 전재열, 실적자료 분석에 의한 건축공사비 산정 방법 적용에 관한 연구, 대한건축학회 논문집(구조계), 제18권 제4호, 2002.4
8 정대권, 도로포장 및 유지공사 표준품셈 개정 방법에 대한 연구, 중앙대학교, 2008
9 정영호, 공공공사의 합리적인 공사비 산출을 위한 표준품셈 작업조 구성에 관한 연구, 경희대학교 2009
10 하기주.최민권.이동렬.하민수.하재훈.김외곤, 시멘트 액체방수 공사의 작업조 기반 품셈을 위한 생산량 및 노무량 분석, 한국건축시공학회 학술발표논문집, pp.171-174, 2009
11 R.S Means Company Assemblies Cost Data 2009
12 김범중.신한우.이웅균.최희복.강경인, 공동 주택 공사시 작업 분석을 통한 철근공사 개선 방안 대한건축학회, 2006
13 2007 건축수량산출기준지침서 건설교통부 2007
14 건설공사 표준품셈 개정내용 한국건설기술연구원 2008