A Productivity Analysis of Tower Crane Installation Progress Based on Simulation Technique  

Kim, Yun-Sik (서울시립대학교 건축공학과)
Cho, Jae-Kyong (서울시립대학교 건축공학과)
Kim, Min-Ji (서울시립대학교 건축공학과)
Cho, Kyu-Man (서울시립대학교 건축공학과)
Hyun, Chang-Taek (서울시립대학교 건축공학과)
Publication Information
Journal of the Korea Institute of Building Construction / v.10, no.2, 2010 , pp. 33-40 More about this Journal
Abstract
Recently, the scale of construction work has been growing, and buildings are becoming higher. To enable greater efficiency of construction work, the use of vertical transportation equipment has been radically increasing. In this context, many studies have been conducted on tower cranes. While these studies have discussed issues such as the selection of tower cranes, the optimization of locations, and the hoisting time of tower cranes, there has been no research on the installation of tower cranes. As such, the installation of tower cranes on construction sites has been accomplished based on subjective judgment and technical assistance, and the experience of workers in equipment companies. Therefore, this study analyzes the productivity of tower cranes using simulation methodology, and proposes a generalized model of the installation process of tower cranes in order to offer a basic resource that site managers can directly utilize.
Keywords
T/C; Simulation; Productivity Analysis;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Furusaka, Shuzo & Gray, Colin, A Model for The Selection of The Optimum Crane for Construction Sites, Construction Management and Economics, Vol.2, No.2, pp.157-176, 1984   DOI
2 Leung, Arthur W. T. & Tam, C. M., "Models for Assessing Hoisting Times of Tower Cranes", ASCE J. of Construction Engineering and Management, Vol. 125, No. 6, pp.385-391, 1999   DOI
3 Han, S. W. and Halpin, D. W., The Use of Simulation for Productivity Estimatiions based Multiple Regression Analysis, Winter Simulation Conference, pp. 1492-1493, 2005
4 Halpin, D. W. and Riggs, L. S., Planning and analysis of construction operations, John Wiley & Sons, Inc., New York, 1992.
5 Rodriguez Ramos, W. E., Quatitative Techniques for Construction Site Layout Planning, Ph, D, The University of Florida, 1982.
6 Warszawski, A, Analysis of Transportation Methods in Construction, Journal of the Construction Division, ASCE, No. 99, Vol. 1, pp.191-202, 1973
7 건설기계관리법시행령, 별표 1, 2007.11
8 김걸회, 효율적인 양중작업을 위한 타워크레인의 배치에 관한 연구, 건국대학교 석사학위논문, 1998.8
9 김훈, 고층건축공사의 리프트 선정 의사결정 모델에 대한 연구, 한양대학교 석사학위논문, 2000
10 남시대, 양중작업의 효율화 방안에 관한 연구, 고려대학교 석사학위논문, 2006
11 박동근 외 4, 건설 시뮬레이션을 활용한 커튼월 적층공법의 생산성 분석방안, 한국건설관리학회 학술발표대회 논문집, pp.263-268,2008.11   과학기술학회마을
12 이동훈 외, 타워크레인 텔레스코핑 작업의 안전리스크 대응방안 연구, 한국건축시공학회 학술논문발표회 논문집, 제9권 제1호, pp.9-13, 2009.5   과학기술학회마을
13 이현수 외, 고층건축공사의 타워크레인 계획 프로세스 개발, 대한건축학회논문집(계획계), 제18권 제6호, pp.119-126, 2002.6   과학기술학회마을
14 이병구 외, Tower Crane 설치계획 및 구조보강 방법 소개, 쌍용건설기술연구소, 제23권, pp.33-37, 2002.6
15 이열, 효율적인 양중작업을 위한 타워크레인의 배치에 관한 연구, 한 양대학교 석사학위논문, 1998.
16 이종렬 외, 고층건축공사 타워크레인 양중시간 예측모델, 한국건설관리학회 학술발표대회 논문집, 제5회, pp.472-475, 2004.11
17 주진호 외, 고층건축공사에 있어서 타워크레인의 최적위치선정 방안에 관한 연구, 대한건축학회 학술발표대회논문집, 제14권 제1호,pp.491-494, 1994
18 허담 외, 고층 건축공사의 양중계획 최적화 방안에 관한 연구, 대한건축학회 학술발표대회논문집, 제14권 제2호, pp.779-784, 1994. 10
19 호종관 외, 상승식 타워크레인 지지구조의 안정성 검토 모델, 한국건설관리학회 논문집, 제9권 제2호, pp.190-198, 2008.4   과학기술학회마을
20 호종관, 타워크레인의 선정과 안정성검토 TOOL 개발, 대한건축학회지, 제50권 제5호, pp.112-116, 2006.5