Suggestion improvement measures based on form work productivity analysis in apartment housing construction  

Yoon, Ja-Young (한양대학교 건축환경공학과)
Kim, Young-Suk (한양대학교 건축공학과)
Kim, Jae-Jun (한양대학교 건축공학과)
Publication Information
Journal of the Korea Institute of Building Construction / v.10, no.1, 2010 , pp. 49-56 More about this Journal
Abstract
A competitive construction project must address factors such as cost, performance, aesthetics, schedule and quality. The importance of these factors will vary from project to project and from market to market. Productivity is becoming an ever-more important factor in the acquisition of a project. As the technology or aesthetics of a product matures or stabilizes, and the competitive playing field levels, competition is increasingly based on time. Recently, the construction industry has been depressed due to difficult market circumstances. At this time in particular, construction companies are striving to rationalize their management, both in their planning offices and in the field. In this study, we present a method of calculating a reasonable duration for reinforced form work. We did this by first developing a question for field workers, then sampling form workers based the question. Second, we employed a work analysis method to analyze worker"s work-methods and Time. Then, using the result of this analysis, we measured the Productivity of form work. This measure can be used as basic data to determine the appropriate duration of form work.
Keywords
Form work; productivity; Work sampling; Apartment housing;
Citations & Related Records
연도 인용수 순위
  • Reference
1 David F. Rogge, Richard L. Tucker, Foreman-Delay Surveys: Work Sampling and Output, Journal of the Construction Division, Vol.108, No.4, pp.592-604, 1982.12
2 E C LimJahidul Alum, Construction productivity: issues encountered by contractors in Singapore, International Journal of Project Management, Vol.13, No.1, pp.51-58, 1995.2   DOI   ScienceOn
3 김두석, RC아파트 내측벽 거푸집공사에 있어서 거푸집 공법별 생산성 비교에 관한 연구, 대한건축학회 춘계학술발표대회 논문집(구조계) 제21권 제1호, pp.525-528, 2001.4
4 김예상 외 3인, 워크 샘플링 기법을 활용한 작업 효율 향상에 관한 연구, 대한건축학회 논문집 제13권 제7호, 1997.7
5 김예상, 건설생산성에 영향을 미치는 요인 분석에 관한 연구, 대한건축학회논문집, 제10권 제10호, pp.267-273, 1994.10
6 박찬혁, 워크샘플링을 활용한 작업효율 향상에 관한 연구, 한양대학교 산업경영대학원, 석사학위 논문, 2000
7 신성현, 워크샘플링 기법에 의한 작업측정에 관한 연구, 인하대학교 경영대학원 석사학위 논문, 1986.2
8 정인환, 아파트공사의 주요공종별 공정 및 생산성 분석, 대한건축학회논문집, 제11권 제4호, pp.269-277, 1995.4
9 경영공학대계, 작업연구, 한국공업표준협회, pp.137, 1982
10 건설산업연구원, 건설관리 및 경영, 보성각, 1997.1