A Study on the Interpretation for Change Order Clause of USA Government Contract  

Cho, Young-Jun (중부대학교 건축공학과)
Publication Information
Journal of the Korea Institute of Building Construction / v.9, no.5, 2009 , pp. 103-110 More about this Journal
Abstract
A construction project consists of a variety of contracts for the completion of work. The large number of contracts involved in a single project increases the likelihood that disputes will arise between the parties involved regarding the terms of service. Actually, there are many disputes that are caused by a change 0 order. While such disputes should be settled by interpreting the terms stipulated in the agreement entered between the two parties, the process of dispute settlement is often restricted to arbitration and lawsuit, and as a result the parties tend to avoid it due to its inefficiency. For this reason, in Korea it is hard to find cases of interpreting terms of service, while in the U.S. it is easy to find diverse cases of interpreting terms of service, since there is a process of dispute settlement by each stage by the party who has placed an order. Therefore, this study presents analysis of case studies of contract changes, looking specifically at changes in the scope of the work, changes in quantity, changes in the period of implementation, changes in the method of implementation or attitude, changes in items provided by the government or the delivery place, and the acceptance of such change procedure by a contractor, and the adjustment of a reduction.
Keywords
Change Order; Interpretation of Contract; Arbitration; Lawsuit;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 김식, 김우종, 국내 설계.시공일괄방식 공사의 클레임 사례분석을 통한 공사계약일반조건의 개선 방향, 전국 대학생 학술발표대회 논문집, 한국건설관리학회, 2008.11
2 이상범, 황재우, 설계시공 일괄입찰공사에서 설계변경 클레임요인의 분석에 관한 연구, 한국건설관리학회 학술발표대회 논문집, 2006. 11   과학기술학회마을
3 중재 제99111-0020호, 2000.10.19
4 Blunt Inc., VABCA 3236, 93-1 BCA $\P$25,474
5 Bruce Anderson Co., ASBCA 29412, 89-2 BCA $\P$21,872
6 Edward R. Marden Corp. v. United States, 194 Ct. Cl. 799, 442 F.2d 364, 1971
7 Kenyon Magnetics, Inc., GSBCA 4769, 77-2 BCA $\P$12,786
8 Oren Childers Paint Contracting Co., ASBCA 13987, 70-2 BCA $\P$8388
9 R/W Contracting, ASBCA 17239, 73-2 BCA $\P$10,130
10 Silberblatt & Lasker, Inc. v. United States, 101 Ct. Cl. 54, 1944
11 W.H. Armstrong & Co. United States, 98 Ct. Cl. 519, 1943
12 Commercial Contractors, Inc., ASBCA 30675, 88-3 BCA $\P$20,877
13 미국, 회계감사보고서, 15 Comp. Gen. 573(A-66501), 1935
14 서용칠, 현장에서 바라본 분쟁 최소화 방안, 한국건설관리학회, 건설관리, 제10권 제2호, pp.46, 2009.4   ScienceOn
15 서울지법 2003. 9. 9. 선고 2002가합85997 판결 '보증금' 항소 '각공2003.11.10.(3),515'
16 Melrose Waterproofing Co., ASBCA 9058, 1964 BCA $\P$4119
17 백화숙, 양창현, 윤자영, 김경환, 김재준, 공사계약일반조건의 클레임 관련 조항의 개선방향, 한국건설관리학회 학술발표대회 논문집, 2007.11   과학기술학회마을
18 Spencer-Safford Loadcraft, Inc., ASBCA 6562, 1962 BCA $\P$3315
19 미국, 연방규정, 32 Fed. Reg. 16269, 1967
20 Peter Kiewit Sons' Co. v. Summit Constr. Co. 422 F.2d 242 (8th Cir. 1969)
21 Litton Sys., Inc., ASBCA 36976, 93-2 BCA $\P$25,705
22 Manis Drilling, IBCA 2658, 93-3 BCA $\P$25,931
23 Pan Arctic Corp., ASBCA 20133, 77-1 BCA $\P$12,514
24 Cibinic, John and Nash, Ralph, 'Administration of Government Contract', The George Washington University, 3rd Ed, 1995
25 Eagle Contracting, Inc., AGBCA 88-225-1, 92-3 BCA $\P$25,018
26 General Contracting & Constr. Co. v. United States, 84 Ct. Cl. 570, 1937
27 John McShain, Inc., GSBCA 3541, 73-1 BCA $\P$9981
28 우리나라 ○○공항 건설 클레임, 2000.2
29 윤준선, 대형 건축 턴키공사의 클레임예방을 위한 클레임 요인 분석에 관한 연구 / 국내 사례를 중심으로, 한국건설관리학회 논문집, 제6권, 제1호, 2005.2   과학기술학회마을
30 Centre Mfg. Co. v. United States, 183 Ct. Cl. 115, 392 F.ed 229, 1968
31 Nochols Dynamics, Inc., ASBCA 17949, 75-2 BCA $\P$11,556
32 Allied Materials & Equip. Co. v. United States, 215 Ct. Cl. 406, 569 F.2d 562
33 Spector, ‘An Analysis of the Standard 'Changes' Clause,’ 25 Fed. B. J. 177 (1965), 2 YPA 1273
34 곽진열, 이광복, 설계변경클레임의 예방을 위한 공사계약일반조건의 구체화 방안, 전국대학생 학술발표대회 논문집, 한국건설관리학회, 2008.11
35 State Mechanical Corp., VABCA 2797, 91-2 BCA $\P$23,830
36 Coley Properties Corp., PSBCA 291, 75-2 BCA $\P$11,514
37 Simmel Industrie Meccaniche Societa per Azioni, ASBCA 6141, 61-1 BCA $\P$2917
38 J.D. Hedin Constr. Co. v. United States, 171 Ct. Cl. 70, 347 F.2d 235, 1965
39 Luria Bros. & Co. v. United States, 177 Ct. Cl. 676. 369 F.2d 701, 1966
40 P.L. Saddler v. United States, 152 Ct. Cl. 557. 287 F.2d 411, 1961
41 J.W. Bateson Co. v. United States, 308 F.2d 510(5th Cir. 1962)
42 Freund v. United States, 260 U.S. 60, 1922
43 Liles Constr. Co. v. United States, 197 Ct. Cl. 164, 455 F.2d 527, 1972
44 Reliance Ins. Co. v. United States, 20 Cl. Ct. 715 (1990)m aff'd, 931 F.2d 863 (Fed. Cir. 1991)
45 정민정, 조영준, 국내의 공공건설 클레임 예방을 위한 계약제도 개선 방안 연구, 한국건설관리학회 학술발표대회 논문집, 2007.11   과학기술학회마을
46 Carpenter Constr. Co., NASBCA 18, 1964 BCA $\P$4452