A Study on the Work Delay Factors of Reinforced Concrete Work in Apartment House Construction  

Lee, Hyun-Chul (전남대 대학원 건축공학과)
Lim, So-Yean (전남대 대학원 건축공학과)
Yeo, Sang-Ku (전남대 대학원 건축공학과)
Go, Seong-Seok (전남대 건축학부)
Publication Information
Journal of the Korea Institute of Building Construction / v.9, no.2, 2009 , pp. 55-61 More about this Journal
Abstract
In order to conduct construction projects effectively, the work delay factors would be managed by planned construction schedules. As construction works are delayed ceaselessly, the solution is to select and manage the key factors which delay the work ceaselessly. The subjects of this study were an apartment houses of reinforced concrete structure. Hidden work delay factor were extracted, the surveys were conducted and occurrence, severity and detection of each factor were analyzed. With this result, final orders of priority were fixed and key management factors were deducted and presented.
Keywords
Apartment house; Reinforced concrete work; Work delay factor; The priority order; Emphatic control factor;
Citations & Related Records
Times Cited By KSCI : 5  (Citation Analysis)
연도 인용수 순위
1 표영민 외 3명, AHP기법을 이용한 건설노동생산성 저하요인 분석에 관한 연구, 한국건축시공학회 학술논문발표회 논문집, 제5권 제1호, 2005   과학기술학회마을
2 안상현 외 2명, 공동주택 공사의 작업지연요소 분석, 한국건설관리학회 논문집, 제8권 제6호, 2007   과학기술학회마을   ScienceOn
3 지근창 외 2명, 건설공사의 투입요소에 의한 작업지연 원인 분류체계, 한국건설관리학회 학술발표대회 논문집, 2004   ScienceOn
4 안성훈 외 2명, 공동주택 공사의 작업간 간섭 감소 방안에 관한 연구, 한국건축시공학회 논문집, 제6권 제1호, 2006   과학기술학회마을   DOI   ScienceOn
5 손창백 외 1명, 공동주택 건축공사의 생산성 향상요인 선정 및 적용성 분석, 대한건축학회 논문집, 제21권 제4호, 2005
6 손창백 외 1명, 건축공사의 생산성 저하요인 분석, 대한건축학회 논문집, 제18권 제12호, 2002   ScienceOn
7 김예상, 건설 생산성에 영향을 미치는 요인분석에 관한 연구, 대한건축학회논문집, 제6권 제10호, 1994