A Study on Estimating Construction Equipment Annual Standard Operating Hours  

Lee, Joong-Seok (부산대학교 건축공학과)
Huh, Young-Ki (부산대학교 건축학부)
Ahn, Bang-Ryul (한국건설기술연구원 건설코스트연구센터)
Publication Information
Journal of the Korea Institute of Building Construction / v.8, no.1, 2008 , pp. 37-42 More about this Journal
Abstract
As use of construction equipment has been increasing continuingly, the proportion of equipment expense to the total construction cost has become higher. However, there is a difference between the equipment expenses section in 'Poom-Sam' and practical data, because 'Poom-sam' does not consider non-working days due to weather conditions, legal holidays and management conditions. Therefore, 'Poom-Sam' does not present a reasonable standard for estimating construction equipment expenses. In this study, to estimate realistic construction equipment operating hours, firstly, construction equipment was classified according to work, and weather conditions, in which each work could not be executed, were established. Then, weather data on Seoul and Busan($2004{\sim}2006$) and legal holidays were analyzed to suggest annual standard operating hours. The annual standard operating hours of earthmoving & excavating, compaction, and drilling equipment was estimated to be 1,430 hours, and lifting equipment, concrete paving equipment, asphalt paving equipment, concrete equipment, and crushing & conveying equipment were estimated to be 2,124 hours, 1,156hours, 1,188hours, 1,688hours, and 2,152hours respectively.
Keywords
Equipment Expenses; Construction Equipment; Ownership Cost; Annual Standard Operating Hours;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 건설공사 표준품셈, 한국건설기술연구원, 2007
2 Cost Reference Guide for Construction Equipment, Equipment Watch, 2006
3 Construction Equipment Ownership and Operating Expense Schedule, Department of U.S. Army Corps of Engineers, 2005
4 양극영,"기상조건에 의한 건축공사 네트워크 계획에 관한 연구". 박사학위 논문, 동국대학교 대학원, 1978
5 윤철희,"건설기계 손료 산정방법 개선방안에 관한 연구". 박사학위 논문, 중앙대학교 대학원, 1995
6 이찬식 외,"건설공사의 적정 표준공사기간 산정방법에 관한 연구", 대한주택공사, 1998
7 김창덕 외,"기후요소에 의한 철골공사 작업불가능일 산정에 관한 연구". 한국건설관리학회논문집, 제7권, 제4호, pp. 137-145, 2006   과학기술학회마을
8 신종현 외,"기후요소를 고려한 인천지역의 작업불가능 일수 산정". 한국건설관리학회논문집, 제6권, 제1호, pp. 58-64, 2005   과학기술학회마을
9 구해식 외,"건설공사의 기후요소에 대한 공기산정 방안 연구", 대한건축학회 논문집, 제15권, 제11호, pp. 87-96, 1999   과학기술학회마을
10 김병수, 전진구,"공공건설공사 공사기간 산정모델에 관한 연구". 한국건설관리학회논문집, 제6권, 제6호, pp. 142-151, 2005   과학기술학회마을
11 한국건설기술연구원,"건설기계 손료산정방법 개선방안에 관한 연구", 1990
12 정석남, 이학기,"기후요소를 고려한 최적 착공시기 결정방법 연구". 대한건축학회 논문집, 제19권, 제5호, pp. 113-120, 2003   과학기술학회마을
13 건축공사표준시방서, 대한건축학회, 2006
14 이근효 외,"국내 건설공사의 기후조건에 의한 작업불능일 예측방법 개선". 한국건설관리학회논문집, 제7권, 제4호, pp. 100-108, 2006   과학기술학회마을
15 산업안전기준에 관한 규칙, 노동부, 2006
16 권기태, 건설기계와 시공, 동명사, 서울, 2002
17 권기태. 토목시공학, 동명사, 1999
18 기상청 홈페이지