A Research on a Comparison between the Strength and Weakness of Each Formwork Methods in the Core Wall Construction  

Shin, Han-Woo (목포대학교 건설공학부 건축공학)
Kim, Gwang-Hee (목포대학교 건설공학부 건축공학과)
Kim, Jae-Yeob (충주대학교 건축공학과)
Cho, Hyung-Keun (호남대학교 환경이공대학 건축학과)
Publication Information
Journal of the Korea Institute of Building Construction / v.7, no.4, 2007 , pp. 153-159 More about this Journal
Abstract
Recently, as a result of the economic growth, the concentration of population towards the cities and the rise in land prices, the demand for high rise buildings has increased significantly, the trend to build high rise buildings such as the mixed-use development buildings by the domestic construction companies continues. It's very important what kind of form work system is applied on the Core Wall of the high rise buildings to determine the economic efficiency for the whole project. That's because the appropriate selection of the Formwork system enables the construction cost lower, makes the good quality of the finished concrete, reduces the construction period, assurance of safety, and further more, it enables to achieve the successful performance of the projects. Therefore, this research, after comparing the strength and the weakness between the construction methods, focus the point to provide a builder the basic data to choose the right Formwork method.
Keywords
System form; Core wall; Form work;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 오정희, 박근준, 국내 초고층 건물 ACS 공법 적용효과, 한국건설관리학회 전국대학생 학술발표대회 논문집, pp.228-229, 2006.10
2 정영수, 박지호, 강승희, 박복만, 최인성, 건설프로젝트 거푸집 선정 요인의 현황 및 개선 방향, 한국건축시공학회 학술, 기술논문발표회 논문집, v.5 n.2(통권 제 9집), pp.111-116, 2005.11   과학기술학회마을
3 권상문, 초고층 건축물 시공을 위한 ACS Form 시공기술, 한국건축시공학회지, v2, n1, pp.80, 2002,02   과학기술학회마을   DOI
4 PERI ACS 기술 자료, http://www.perikorea.com
5 Kamarthi, S. V., Sanvido, V. E., Kumara, S. R. T., Neuroform-Neural Network System for Vertical Formwork Selection, Journal of Computing in Civil Engineering, 6(2), p.p.178-199, 1992   DOI
6 초고층건축포럼, Core Wall선행공법, 초고층건축포럼연구소, 2007
7 Hanna, A. S., Willenbrock, J. H., Sanvido, V. E., Knowledge Acquisition and Developement for Formwork Selection System, Journal of Construction Engineering and Management, 118(1), p.p.179-198, 1992   DOI
8 Hurd, M. K., Formwork for Concrete Fifth Edition, American Concrete Institute, Detroit, 1989
9 김석회, 초고층 건물 구조물 공사시 CORE WALL 선행 작업에 대한 비교 연구, 한양대 산업대학원 석사 학위 논문, pp.25-26, 2001.08
10 김광희 외 5인, 초고층 건물 공기단축을 위한 기둥철근 3개층 선조립 공법에 관한 연구, 한국생태환경건축학회논문집, v.7 n.2, pp.39-46, 2007.04   과학기술학회마을
11 문승호, 건축시공기술, 1판, 기문당, p.p.325-326, 2006
12 신윤석, 최희복, 이웅균, 안성훈, 강경인, 초고층 건축공사의 바닥판 거푸집 시스템 선정에 관한 연구, 대한 건축학회 논문집(구조계), v.22 n.2, pp.147-154, 2006.02   과학기술학회마을
13 김광희, 강경인, 초고층 골조공사를 위한 유닛 테이블 거푸집공법의 개발 및 적용에 관한 연구, 대한 건축학회논문집(구조계), v.19 n.8, pp.181-188, 2003.08   과학기술학회마을
14 오성록, 박근준, 초고층건물 RC조 코어월 선행 공법 개선방안, 한국건설관리학회 전국대학생 학술 발표대회 논문집, pp.340-343, 2005.10
15 Elazouni, A. M., Ali, A. E., Abdel-razek, R. H., Estimating the Acceptability of New Formwork Systems Using Neural Networks, Journal of Constructoin Engineering and Management, 131(1), p.p.33-41, 2005   DOI   ScienceOn
16 김성근, 이웅균, 조훈희, 강경인, 초고층 건축공사 바닥 거푸집 선정을 위한 의사 결정지원 시스템, 대한건축학회 논문집(구조계), v.22 n.11, pp.207-214, 2006.11   과학기술학회마을