Common Due-Date Assignment and Scheduling on Parallel Machines with Sequence-Dependent Setup Times  

Kim, Jun-Gyu (Department of Industrial Engineering, Hanyang University)
Yu, Jae-Min (Department of Industrial Engineering, Hanyang University)
Lee, Dong-Ho (Department of Industrial Engineering and Graduate School of Technology and Innovation Management, Hanyang University)
Publication Information
Management Science and Financial Engineering / v.19, no.1, 2013 , pp. 29-36 More about this Journal
Abstract
This paper considers common due-date assignment and scheduling on parallel machines. The main decisions are: (a) deter-mining the common due-date; (b) allocating jobs to machines; and (c) sequencing the jobs assigned to each machine. The objective is to minimize the sum of the penalties associated with common due-date assignment, earliness and tardiness. As an extension of the existing studies on the problem, we consider sequence-dependent setup times that depend on the type of job just completed and on the job to be processed. The sequence-dependent setups, commonly found in various manufacturing systems, make the problem much more complicated. To represent the problem more clearly, a mixed integer programming model is suggested, and due to the complexity of the problem, two heuristics, one with individual sequence-dependent setup times and the other with aggregated sequence-dependent setup times, are suggested after analyzing the characteristics of the problem. Computational experiments were done on a number of test instances and the results are reported.
Keywords
Parallel Machines; Due-Date Assignment; Scheduling; Sequence-Dependent Setup Times; Heuristics;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Balakrishnan, N., J. J. Kanet, and V. Sridharan, "Early/tardy scheduling with sequence dependent setups on uniform parallel machines," Computers and Operations Research 26 (1999), pp. 127-141.   DOI   ScienceOn
2 Biskup, D. and H. Jahnke, "Common due-date assignment for scheduling on a single machine with jointly reducible processing times," International Journal of Production Economics 69 (2001), 317-322.   DOI   ScienceOn
3 Chen, Z. L., "Scheduling and common due-date assignment with earliness-tardiness penalties and batch delivery costs," European Journal of Operational Research 93, (1996), 49-60.   DOI   ScienceOn
4 Cheng, T. C. E. and M. Y. Kovalyov, "Bath scheduling and common due-date assignment on a single machine," Discrete Applied Mathematics 70 (1996), 231-245.   DOI   ScienceOn
5 Cheng, T. C. E., "A heuristic for common due-date assignment and job scheduling on parallel machines," Journal of the Operational Research Society 40(1989), 1129-1135.   DOI
6 Hall, N. G., "Single and multiple processor models for minimizing completion variances," Naval Research Logistics 33 (1986), 49-54.   DOI
7 Kim, J.-G. and D.-H. Lee, "Algorithms for common due-date assignment and sequencing in a single machine with sequence-dependent setup times," Journal of the Operational Research Society 60(2009), 1264-1272.   DOI   ScienceOn
8 Kim, J.-G., J.-S. Kim, and D.-H. Lee, "Common duedate assignment and sequencing with sequencedependent setup times: a case study on a paper remanufacturing system," Management Science and Financial Engineering 18 (2012), 1-12.   DOI   ScienceOn
9 Kim, J-.G., J.-S. Kim, and D-.H. Lee, "Fast and metaheuristics for common due-date assignment and scheduling on parallel machines," International Journal of Production Research 60 (2012), 6040-6057.
10 Kim, S.-I., H-.S. Choi, and D-.H. Lee, "Scheduling algorithms for parallel machines with sequencedependent setup and distinct ready times: minimizing total tardiness," Proceedings of the Institution of Mechanical Engineers, Part B: Journal of Engineering Manufacture 221 (2007), 1087-1096.   DOI   ScienceOn
11 Min, L. and W. Cheng, "Genetic algorithms for the optimal common due-date assignment and the optimal scheduling policy in parallel machine earliness/tardiness scheduling problems," Robotics and Computer-Integrated Manufacturing 22 (2006), 279-287.   DOI   ScienceOn
12 Baker, K. R. and G. D. Scudder, "Sequencing with earliness and tardiness penalties: a review," Operations Research 38 (1990), 22-36.   DOI   ScienceOn
13 Ng, C. T. D., T. C. E. Cheng, M. Y. Kovalyov, and S. S. Lam, "Single machine scheduling with a variable common due-date and resource-dependent processing times," Computers and Operations Research 30 (2003), 1173-1185.   DOI   ScienceOn
14 Cheng, T. C. E., "A note on the common due-date assignment problem," Journal of the Operational Research Society 37 (1986), 1089-1091.   DOI
15 Baker, K. R. and G. D. Scudder, "On the assignment of optimal due-dates," Journal of the Operational Research Society 40 (1989), 93-95.   DOI
16 Cheng, T. C. E., Z. L. Chen, and N. V. Shakhlevich, "Common due-date assignment and scheduling with ready times," Computers and Operations Research 29 (2002), 1957-1967.   DOI   ScienceOn
17 Xia, Y., B. Chen and J. Yue, "Job sequencing and duedate assignment in a single machine shop with uncertain processing times," European Journal of the Operational Research 184 (2008), 63-75.   DOI   ScienceOn
18 Xiao, W. Q. and C. L. Li, "Approximation algorithms for common due-date assignment and job scheduling on parallel machines," IIE Transactions 34 (2002), 467-477.   DOI   ScienceOn
19 Cheng, T. C. E., "Common due-date assignment and scheduling for a single processor to minimize the number of tardy jobs," Engineering Optimization 16 (1990), 129-136.   DOI
20 De, P., J. B. Ghosh, and C. E. Wells, "Due-date assignment and early/tardy scheduling on identical parallel machines," Naval Research Logistics 41 (1994), 17-32.   DOI
21 De, P., J. B. Ghosh, and C. E. Wells, "On the multiplemachine extension to a common due date assignment and scheduling problem," Journal of the Operational Research Society 42 (1991), 419-422.   DOI
22 Diamond, J. E. and T. C. E. Cheng, "Error bound for common due-date assignment and job scheduling on parallel machines," IIE Tranactions 32 (2000), 445-448.
23 Dvir, S. and S. George, "Two due-date assignment problems in scheduling a single machine," Operations Research Letters 34 (2006), 683-691.   DOI   ScienceOn
24 Emmons, H., "Scheduling to a common due date on parallel uniform processors," Naval Research Logistics 34 (1987), 803-810.   DOI
25 Gordon, V., J. M. Proth, and C. Chu, "A survey of the state-of-the-art of the common due-date assignment and scheduling research," European Journal of Operational Research 139 (2002), 1-25.   DOI   ScienceOn
26 Sundararaghavan, P. S. and M. U. Ahmed, "Minimizing the sum of absolute lateness in single-machine and multi-machine scheduling," Naval Research Logistics 31 (1984), 325-333.   DOI
27 Hall, N. G., "Scheduling problems with generalized duedates," IIE Transactions 18 (1986), 220-222.   DOI
28 Panwalkar, S. S., M. L. Smith, and A. Seidmann, "Common due-date assignment to minimize total penalty for the one machine scheduling problem," Operations. Research 30 (1982), 391-399.   DOI   ScienceOn
29 Quaddus, M. A., "A generalized model of optimal duedate assignment by linear programming," Journal of the Operational Research Society 38 (1987), 353-359.   DOI