Special Cases on Two Machine Flow Shop Scheduling with Weighted WIP Costs  

Yang, Jae-Hwan (School of Business Administration, University of Seoul)
Publication Information
Management Science and Financial Engineering / v.15, no.2, 2009 , pp. 69-100 More about this Journal
Abstract
In this paper, we consider a relatively new two-machine flow shop scheduling problem where the unit time WIP cost increases as a job passes through various stages in the production process, and the objective is to minimize the total WIP (work-in-process) cost. Specifically, we study three special cases of the problem. First, we consider the problem where processing times on machine 1 are identical. Second, the problem with identical processing times on machine 2 is examined. The recognition version of the both problems is unary NP-complete (or NP-complete in strong sense). For each problem, we suggest two simple and intuitive heuristics and find the worst case bound on relative error. Third, we consider the problem where the processing time of a job on each machine is proportional to a base processing time. For this problem, we show that a known heuristic finds an optimal schedule.
Keywords
WIP Cost; Machine Flow Shop Scheduling; Heuristic Analysis;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Allahverdi, A., 'Two-machine proportionate flowshop scheduling with breakdowns to minimize maximum lateness,' Computers and Operations Research 23 (1996), 909-916   DOI   ScienceOn
2 Choi, B.-C., S.-H. Yoon, and S.-J. Chung, 'Minimizing the total weighted completion time in a two-machine proportionate flow shop with different machine speeds,' International Journal of Production Research 44 (2006), 715-728   DOI   ScienceOn
3 Conway, R. W., Maxwell, W. L., and Miller, L. W., Theory of scheduling, Addision-Wesley, Reading, MA, 1967
4 Garey, M. R, D. S. Johnson, and R. Sethi, 'The complexity of flowshop and jobshop scheduling,' Mathematics of Operations Research 1 (1976), 117-129   DOI   ScienceOn
5 Gonzalez, T. and S. Sahni, 'Flowshop and job shop schedules: Complexity and approximation,' Operations Research 26 (1978), 36-52   DOI   ScienceOn
6 Graham, R L., E. L. Lawler, J. K. Lenstra, and A. H. G. Rinnooy Kan, 'Optimization and approximation in deterministic sequencing and scheduling: A survey,' Annals of Discrete Mathematics 5 (1979), 287-326   DOI
7 Shakhlevich, N., H. Hoogeveen, and M. Pinedo, 'Minimizing total weighted completion time in a proportionate flow shop,' Journal of Scheduling 1 (1998), 157-168   DOI   ScienceOn
8 Yang, J., 'Two machine flow shop scheduling problem with weighted WIP weight,' Computers and Operations Research 36 (2009), 472-486   DOI   ScienceOn
9 Yang, J. and M. E. Posner, 'Flow Shops with WIP and Value Added Costs,' Journal of Scheduling (2009), in press
10 Adiri, I. and N. Amit, 'Openshop and flowshop scheduling to minimize sum of completion times,' Computers and Operations Research 11 (1984), 275-284   DOI   ScienceOn
11 Croce, F. D., V. Narayan, and R. Tadei, 'The two-machine total completion time flow shop problem,' European Journal of Operational Research 90 (1996), 227-237   DOI   ScienceOn
12 Croce, F. D., M. Ghirardi, and R. Tadei, 'An improved branch-and-bound algorithm for the two machine total completion time flow shop problem,' European Journal of Operational Research 139, (2002), 293-301   DOI   ScienceOn
13 Hou, S. X. and H. Hoogeveen, 'The three-machine proportionate flow shop problem with unequal machine speeds,' Operations Research Letters 31 (2003), 225-231   DOI   ScienceOn
14 Wang, C., C. Chu, and J.-M. Proth, 'Efficient heuristic and optimal approaches for n / 2 / F / ${\Sigma}C_i$ scheduling problems,' International Journal of Production Economics 44 (1997), 225-237   DOI   ScienceOn
15 Cheng, T. C. E. and N. Shakhlevich, 'Proportionate flow shop with controllable processing times,' Journal of Scheduling 2 (1999), 253-265   DOI   ScienceOn
16 Sipper, D. and R Shapira, 'JIT Vs. WIP-a trade-off analysis,' International Journal of Production Research 27 (1989), 903-914   DOI   ScienceOn
17 van de Velde, S. L., 'Minimizing the sum of the job completion times in the two-machine flow shop by Lagrangian relaxation,' Annals of Operations Research 26 (1992), 257-268
18 Lee, W.-C. and C.-C. Wu, 'Minimizing the total flow time and tardiness in a two-machine flow shop,' International Journal of Systems Science 32 (2001), 365-373   DOI   ScienceOn
19 Vollman, T. E., W. L. Berry, and D. C. Whybark, Manufactuting planning and control systems, McGraw-Hill, New York, NY, 1997
20 Ow, P. S., 'Focused scheduling in proportionate flowshops,' Management Science 31 (1985), 852-869   DOI   ScienceOn
21 Hoogeveen, J. A. and T. Kawaguchi, 'Minimizing total completion time in a two-machine flowshop: analysis of special cases,' Mathematics of Operations Research 24 (1999), 887-910   DOI   ScienceOn