Challenges to Prevent in Practice for Effective Cost and Time Control of Construction Projects  

Olawale, Yakubu A. (WMG, University of Warwick)
Publication Information
Journal of Construction Engineering and Project Management / v.10, no.1, 2020 , pp. 16-32 More about this Journal
Abstract
Cost and time control of projects is important in preventing project failure. However, achieving effective cost and time control in practice is often challenging. The challenges of project cost and time control in practice are investigated by carrying out a questionnaire survey on the top 150 construction contractors in the UK followed by in-depth semi-structured interviews of practitioners from 15 construction companies in the country. Quantitative analysis reveals that design change is the most important factor inhibiting the ability of UK contractors from effectively controlling both the cost and time of construction projects. Four of the top five factors inhibiting effective cost control are also the top factors inhibiting effective time control albeit in a different order. These top factors-design changes, inaccurate evaluation of project time/duration, risk and uncertainty, non-performance of subcontractors and nominated suppliers were also found to be endogenous factors to the project. Additionally, qualitative analysis of the interviews reveals 16 key challenges to prevent for effective project cost and time control in practice. These are classified into four categorised based on where they stem from as follows; from the organisation (1. Lack of integration of cost and time during project control, 2. lack of management buy-in, 3. complicated project control systems and processes, 4. lack of a project control training regime); from the construction management/project management approach (5. Lapses in integration of interfaces, 6. project control not being implemented from the early stages of a project, 7. inefficient utilisation and control of labour, 8. limited time devoted to planning how a project will be controlled at the outset); from the client; (9. Excessive authorisation gates, 10. use of adversarial and non-collaborative forms of contracts, 11. communication problems within client set-up, 12. obstructive client representatives) and; from the project team (13. Lack of detailed/complete design, 14. lack of trust among the project partners, 15. limited time devoted to project control on site, 16. non-factual reporting). The study posits that knowledge of these project control inhibiting factors and challenges is the first step at ensuring they are avoided and enable the implementation of a more effective project cost and time control process in practice.
Keywords
Cost control; Overrun; Project control; Project management practice; Project success;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Acebes, F., Pajares, J., Galan, J., and Lopez-Paredes, A., "A new approach for project control under uncertainty. Going back to the basics", International Journal of Project Management, vol. 32, no. 3, pp. 423-434, 2014.   DOI
2 Platje, A. and Seidel, H., "Breakthrough in multiproject management: how to escape the vicious circle of planning and control", International Journal of Project Management, vol. 11, no. 4, pp. 209-213, 1993.   DOI
3 Besteiro, E., De Souza Pinto, J., and Novaski, O., "Success factors in project management", Business Management Dynamics, vol. 4, no. 9, pp. 19-34, 2015.
4 Abdul-Rahman, Z. H., Berawi, M., Berawi, A., Mohamed, O., Othman, M.J.A., and Yahya, I., "Delay mitigation in the Malaysian construction industry", Journal of Construction Engineering and Management, vol. 132, no. 2, pp.125-133, 2006.   DOI
5 Chan, A., "Time-cost relationship of public sector projects in Malaysia", International Journal of Project Management, vol. 19, pp. 223-229, 2001.   DOI
6 White, D. and Fortune, J., "Current practice in project management - An empirical study", International Journal of Project Management, vol. 20, no. 1, pp. 1-11, 2002.   DOI
7 Winch, G. and Kelsey, J., "What do construction project planners do?", International Journal of Project Management, vol. 23, no. 2, pp. 141-149, 2005.   DOI
8 Zou, Y. and Lee, S., "The impacts of change management practices on project change cost performance", Construction Management and Economics, vol. 26, no. 4, pp. 387-393, 2008.   DOI
9 Chang, A., "Reasons for cost and schedule increase for engineering design projects", Journal of Management in Engineering, vol. 18, pp. 29-36, 2002.   DOI
10 Iyer, K. and Jha, K., "Factors Affecting Cost Performance Evidence from Indian Construction Projects", International Journal of Project Management, vol. 23, pp. 283-295, 2005.   DOI
11 Larsen, J., Shen, G., Lindhard, S., and Brunoe, T., "Factors affecting schedule delay, cost overrun, and quality level in public construction projects", Journal of Management in Engineering, vol. 32, no. 1 pp. 04015032, 2016.   DOI
12 Aibinu, A. and Jagboro, G., "The effects of construction delays on project delivery in Nigerian construction industry," International Journal of Project Management, vol. 20, pp. 593-599, 2002.   DOI
13 Yong, Y. and Mustaffa, N., "Critical success factors for Malaysian construction projects: an empirical assessment", Construction Management and Economics, vol. 31, no. 9, pp. 959-978, 2013.   DOI
14 Akintoye, A., Fitzgerald, E. "A survey of current cost estimating practices in the UK", Construction Management and Economics, vol. 18, no. 2, pp. 161-172, 2000.   DOI
15 Barraza, G. and Bueno, R., "Probabilistic control of project performance using control limit curves", Journal of Construction Engineering and Management, vol. 133, no. 12, pp. 957-965, 2007.   DOI
16 Chan, P., Ho, D., and Tam, C., (2001) "Design and build project success: multivariate analysis", Journal of Construction Engineering and Management, vol. 127, no. 2, pp. 93-100, 2001.   DOI
17 Cho, K., Hong, T., and Hyun, C., (2010) "Integrated schedule and cost model for repetitive construction process", Journal of Management in Engineering, vol. 26, no. 2, pp. 78-88, 2010.   DOI
18 Thompson, C. and Walker, B., "Basics of research (Part 12): Qualitative research," Air Medical Journal, vol. 17, pp. 65-70, 1998.   DOI
19 Gibson, G., Wang, Y., Cho, C., and Pappas, M., (2006) "What is preproject planning anyway?" Journal of Management in Engineering, vol. 22, no. 1, pp. 35-42, 2006.   DOI
20 Flyvbjerg, B., Holm, M., and Buhl, S., "How common and how large are cost overruns in transport infrastructure projects?" Transport Reviews, vol. 23, no. 3, pp. 71-88, 2003.   DOI
21 Jung, Y. and Woo, S., "Flexible work breakdown structure for integrated cost and schedule control", Journal of Construction Engineering and Management, vol. 130, no. 5, pp. 616-625, 2004.   DOI
22 Kim, S. and Liu, L. "Cost information models for managing multiple projects". Journal of Construction Engineering and Management, vol. 133, no. 12, pp. 966-974, 2007.   DOI
23 Koga, Y., Chua, D., Loh, P. and Jaselskis, E., "Key determinants for construction schedule performance", International Journal of Project Management, vol. 17, no. 6, pp. 351-359, 1999.   DOI
24 Larson, E., "Project partnering: Results of study of 280 construction projects", Journal of Management in Engineering, vol. 11, no. 2, pp. 30-35, 1995.   DOI
25 Laufer, A. and Tucker, R., "Is construction project planning really doing its job? A critical examination of focus, role and process", Construction Management and Economics, vol. 5, no. 3, pp. 243-266, 1987.   DOI
26 Lee, S., Thomas, S., Tucker, R., "The relative impacts of selected practices on project cost and schedule", Construction Management and Economics, vol. 23, no. 5, pp. 545-553, 2005.   DOI
27 Leu, S., Chen, A., and Yang, C., "A GA-based fuzzy optimal model for construction time-cost trade-off" International Journal of Project Management, vol. 19, pp. 47-58, 2001.   DOI
28 Young, R. and Poon, S., "Top management support-almost always necessary and sometimes sufficient for success: Findings from a fuzzy set analysis" International Journal of Project Management, vol. 31, pp. 94-957, 2013.
29 Sanchez, Otavio Prospero, Terlizzi, Marco Alexandre, Cesar de Moraes, Heverton Roberto de Oliveira (2017) Cost and time project management success factors for information systems development projects, IJPM (35), 1608-1626.
30 Kanwal, N., Zafar, M., Bashir, S., (2017), "The combined effects of managerial control, resource commitment, and top management support on the successful delivery of information systems projects", vol. 35, pp. 1459-1465, 2017.   DOI
31 Bryde, D., Unterhitzenberger, C., and Jober, R., "Conditions of success for earned value analysis in projects, International Journal of Project Management, vol. 36, pp. 474-484, 2018.   DOI
32 Ling, F., "How project managers can better control the performance of design-build projects", International Journal of Project Management, vol. 22, no. 6, pp. 477-488, 2004.   DOI
33 Ling, Y., Low, S., Wang, S., and Lim, H., "Key project management practices affecting Singaporean firms' project performance in China", International Journal of Project Management, vol. 27, no. 1, pp. 59-71, 2009.   DOI
34 Marco, A., Briccallero, D., Rafele, C., "Cost and schedule monitoring of industrial building projects: Case study", Journal of Construction Engineering and Management, vol. 135, no. 9, pp. 853-862, 2009.   DOI
35 Milosevic, D. and Patanakul, P., "Standardised project management may increase development projects success" International Journal of Project Management, vol. 23, no. 3, pp. 181-192, 2005.   DOI
36 Olawale, Y. and Sun, M., (2015) "Construction project control in the UK: Current practice, existing problems and recommendations for future improvements", International Journal of Project Management, vol, 33 no. 3, pp. 623-637, 2015.   DOI
37 Ritchie, L. and Spencer, W. O'Connor, "Carrying out qualitative analysis", in: Qualitative research practice: A guide for social science students and researchers, Eds, J. Ritchie, J. Lewis, SAGE publications, London, pp. 219-262, 2003.
38 Olawale, Y. and Sun, M., "PCIM: Project Control and Inhibiting Factors Management Model", Journal of Management in Engineering, vol. 29, no. 1, pp. 60-70, 2013.   DOI