A Fuzzy AHP Model for Selection of Consultant Contractor in Bidding Phase in Vietnam  

Ha, Tran Thanh (University of Technology, National University of Hochiminh City)
Hoai, Long Le (Faculty of Civil Engineering, University of Technology, National University of Hochiminh City)
Lee, Young Dai (Dept. of Civil and Construction Engineering, Pukyong National University)
Publication Information
Journal of Construction Engineering and Project Management / v.5, no.2, 2015 , pp. 35-43 More about this Journal
Abstract
Project Management Consultant (PMC) plays a vital role in the overall performance of any project. Selecting right PMC for right project is the most crucial challenge for any construction owner. Thus, PMC selection is one of the main decisions made by owners at the early phase of construction project. It is not easy for the project owner to select a competent PMC due to the fuzziness, imprecision, vagueness, incomplete and qualitative criteria of the decision. This paper presents a model for selecting PMC contractor using the Fuzzy Analytical Hierarchy Process (FAHP). And a fuzzy number based framework is proposed to be a viable method for PMC contractor selection. A case study to illustrate the application of the model is also presented in this paper.
Keywords
Project Management Consultant; Fuzzy Analytical Hierarchy Process; Decision Making; Vietnam;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Al-Harbi, K. M. A.S., "Application of the AHP in project management", Int. J. Proj. Manage, 19(1), pp. 19-27, 2001.   DOI
2 Nieto-Morote, A., Ruz-Vila, F., "A fuzzy multi-criteria decisionmaking model for construction contractor prequalification", Automation in Construction, 25, pp. 8-19, 2012.   DOI
3 Boroushaki, S., Malczewski, J., "Implementing an Extension of the Analytical Hierarchy Process using Order Weighted Averaging Operators with Fuzzy", Quantifiers ArcGIS Computers and Geoscience. 34, pp. 399 - 410, 2008.   DOI
4 Chan, A.P.C., Scott, D., Chan, A.P.L., "Factor affecting the success of a construction Project", Journal of Construction Engineering and Management, ASCE, 130, pp. 153-155, 2004.   DOI
5 Cheng, E. W. L., and Li, H., "Contractor selection using the analytical network process", Constr. Manage. Econ., 22(10), pp. 1021-1032, 2004.   DOI
6 Deng, H., "Multicriteria analysis with fuzzy pairwise comparison", International Journal of Approximate Reasoning, 21(3), pp. 215-231, 1999.   DOI
7 Fong, P. S.-W., and Choi, S. K.-Y., "Final contractor selection using analytical hierarchy process", Constr. Manage. Econom., 18, pp. 547-557, 2000.   DOI
8 Hatush, Z., and Skitmore, M., "Contractor selection using multicriteria utility theory: An additive model", Build. Environ., 33(2-3), pp. 105-115, 1998.   DOI
9 Hipel, K. W., Radford, K. J., and Fang, L., "Multiple participant multiple criteria decision making", IEEE Trans. Syst. Man Cybern. 23, pp. 1184-1189, 1993.   DOI
10 Holt, G. D., "Which contractor selection methodology?" Int. J. Proj. Manage., 16(3), pp. 153-164, 1998.   DOI
11 Hwang, C.L., and Yoon, K., Multiple attribute decision making: methods and applications, Springer, New York, 1981.
12 San Cristobal, J.R., "Contractor Selection Using Multicriteria Decision-Making Methods", Journal of Construction Engineering and Management, ASCE, 138, pp. 751-758, 2012.   DOI
13 Lam, K.C., Hu, T., Ng, S.T., Skitmore, M., Cheung, S.O., "A fuzzy neural network approach for contractor prequalification", Construction Management and Economics, 19(2), pp. 175-188, 2001.   DOI
14 Kaufmann, A., and Gupta, M. M., Introduction to fuzzy arithmetic theory and application, Van Nostrand Reinhold, New York, 1991.
15 Lambopoulos, S.,"The use of time and cost utility for construction contract award under European Union legislation", Build. Environ., 42(1), pp. 452-463, 2007.   DOI
16 Liou, T.S., and Wang, M.J.J., "Ranking Fuzzy numbers with Integral value", Fuzzy Sets & Systems, 50, pp. 247-255, 1992.   DOI
17 Madhi, I., Riley, M., Fereig, S., and Alex, A., "A multi-criteria approach to contractor selection", Eng. Constr. Archit. Manage., 9(1), pp. 29-37, 2002.
18 Marzouk,M., "An application of ELECTRE III to contractor selection" Construction Research Congress 2010
19 Ng, S.T. and Skitmore, R.M., "Client and consultant perspectives of prequalification criteria", Building and Environment, 34, pp. 607-21, 1999.   DOI
20 Meixner, O., Fuzzy AHP group decision analysis and its application for the evaluation of energy sources. Proceedings of the Proceedings of the 10th International Symposium on the Analytic Hierarchy/Network Process, Pittsburtgh/PA, USA, 2009.
21 Nguyen.V.U., "Tender evaluation by fuzzy sets", Journal of Construction Engineering and Management, 111(3), pp. 231- 243, 1985.   DOI
22 Ofori, G.,Ling, Y.Y., and Sui, P.L., "Evaluation and selection of consultants for design-build projects", Project Management Journal, 34.1, 2003.
23 Nguyen, D.L., Ogunlala, S.O. and Lan, D.T.X., "A study on Project success factors in large construction projects in Vietnam" Engineering, Construction and Architecture Management, 11(6), pp. 404-413, 2004.   DOI
24 Russell, J. S., and Skibniewski, M. J., "Decision criteria in contractor prequalification", J. Manage. Eng.,4(2), pp. 148-164, 1988.   DOI
25 Saaty, T.L., The analytic hierarchy process. New York NY: McGraw Hill, 1980.
26 Saaty, T L. and Kearns K P., Analytical Planning - The organizations of Systems. Pergamon Press, New York, 19-62, 1985.
27 Singh,D and Tiong, R.L.K., "A fuzzy decision framework for Contractor Selection", Journal of Construction Engineering and Management, ASCE Vol.131, pp. 62-70, 2005   DOI
28 Ng, S.T., Kumaraswamy, M. and Chow, L.K., "Selecting Consultants through combined technical and fee assessment: A Hong Kong Study", Association of Researchers in Construction Management, Vol.1, 639-47, 2001.
29 Topcu;Y.I., "A decision model proposal for construction contractor selection in Turkey", Build. Environ, 39(4), pp. 469- 481, 2004.   DOI
30 Tesfamariam, S., and Sadiq R., "Risk-based environmental decision-making using fuzzy analytic hierarchy process (FAHP)", Stochastic Environmental Research and Risk Assessment, 21(1), pp. 35-50, 2006.   DOI
31 Trivedi. M. K.; Pandey, M. K., Bhadoria, S.S., "Prequalification of Construction Contractor using a FAHP", International Journal of Computer Applications, Vol. 28- No.10, 2011.
32 Wong, C. H., "Contractor performance prediction model for the United Kingdom construction contractors: Study of logistic regression approach", J. Constr. Eng. Manage, 130(5), pp. 691- 698, 2004.   DOI
33 Li,Y.W., Nie, X.T., "Fuzzy Approach to Prequalifying Construction Contractors", Journal of Construction Engineering and Management, ASCE,Vol.133,No.1, 2007.
34 Zadeh, L.A., "Fuzzy sets", Information and Control, 8(3), pp.338-353, 1965.   DOI