Investigating Main Causes for Schedule Delay in Construction Projects in Bangladesh  

Rahman, MD. Mizanur (Interdisciplinary Program of Construction Engineering and Management, Pukyong National University)
Lee, Young Dai (Department of Civil Engineering, Pukyong National University)
Ha, Duy Khanh (Interdisciplinary Program of Construction Engineering and Management, Pukyong National University)
Publication Information
Journal of Construction Engineering and Project Management / v.4, no.3, 2014 , pp. 33-46 More about this Journal
Abstract
Delay is the most common problem in the construction industry. It has many negative effects on project's success in terms of time, cost, quality, and safety. From the literature review, a total of thirty-five factors of delay were selected. These factors were divided into seven groups related to materials, manpower, owner, consultant, contractor, construction, and external problems. This study was carried out to identify the main causes of delay for a construction project through their importance level. The importance level was determined based on the frequency of occurrence and severity of impact. The structured questionnaire has distributed to the respondents who have much experience in construction management in Bangladesh. The results of analysis indicated that top five factors of construction delay according to their level of importance are: (1) price of construction materials increased very rapidly, (2) political situation (revolution/ public strikes), (3) shortages of skilled workers, (4) poor site management and supervision by contractor, (5) incompetent/ immature subcontractors. These findings of this study are expected to be significant contributions to Bangladesh construction industry in controlling current performance of project on time overrun.
Keywords
Delay; Cause; Construction project; Bangladesh;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 N.K. Acharya, Y.D. Lee, H.M. Im, "Investigating Delay Factors in Construction Industry: A Korean perspective." Korean Journal of Construction Engineering and Management, vol. 10, no. 6, pp. 177-190, 2006.   과학기술학회마을
2 A.A. Aibinu, A. Odeyinka, "Construction Delays and their Causative Factors in Nigeria." Journal of Construction Engineering Management, ASCE, vol. 132, no. 7, pp. 667-677, 2006.   DOI   ScienceOn
3 S.A. Asaaf, M. Al-Khalil, "Causes of Delay in Large Building Construction Projects." International Journal of Project Management, vol. 11, no. 2, pp. 45-50, 1995.
4 R.T.M. Akogbe, X. Feng, J. Zhou, "Importance and Ranking Evaluation of Delay Factors for Development Construction Projects in Benin." KSCE Journal of Civil Engineering, vol. 17, no. 6, pp. 1213-1222, 2013.   DOI   ScienceOn
5 A.H. Al-Momani, "Construction Delay: A Quantitative Analysis." International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000.   DOI   ScienceOn
6 S.A. Asaaf, S. Al Hejji, "Causes of Delay in Large Construction Projects." International Journal of Project Management, vol. 24, pp. 349-357, 2006.   DOI   ScienceOn
7 J.R. Baldwin, J.M. Manthei, "Causes of Delay in the Construction Industry." Journal of Construction Division, ASCE, vol. 97, no. 2, pp. 177-187, 1971.
8 D.W. Chan, M.M. Kumaraswamy, "A Comparative Study of Causes of Time Overruns in Hong Kong Construction Projects". International Journal of Project Management, vol. 15, no. 1, pp. 55-63, 1997.   DOI   ScienceOn
9 H. Doloi, A. Sawhney, K.C. Iyer, S. Rentala, "Analyzing Factors Affecting Delays in Indian Construction Projects." International Journal of Project Management, Vol. 30, 479-489, 2012.   DOI   ScienceOn
10 M.E. El-Razek, H.A. Bassioni, A.M. Mobarak, "Causes of Delay in Building Construction Projects in Egypt." Journal of Construction Engineering and Management, ASCE, vol. 134, no. 11, pp. 831-841, 2008.   DOI   ScienceOn
11 A.S. Ezeldin, M. Abdel-Ghany, "Causes of Construction Delays for Engineering Projects in the Middle-East: An Egyptian Perspective." AEI, ASCE, pp. 53-62, 2013.
12 A.S. Faridi, S.M. Sayegh, "Significant Factors Causing Delay in the UAE Construction Industry." Construction Management and Economics, vol. 24, no. 11, pp. 1167-1176, 2006.   DOI   ScienceOn
13 Y. Frimpong, J. Oluwoye, L. Crawford, "Causes of Delay and Cost Overruns in Construction of Groundwater Projects in a Developing Countries; Ghana as a Case Study." International Journal Project Management, vol. 21, pp. 321-326, 2003.   DOI   ScienceOn
14 M. Ibrahim, A. Bruland, N. Dmaidi, "Causes of Delay in Road Construction Projects." Journal of Management in Engineering, ASCE, vol. 28, no. 3, pp. 300-310, 2012.   DOI
15 T.Y. Lo, I.W.H. Fung, K.C.F. Tung, "Construction Delays in Hong Kong Civil Engineering Projects." Journal of Construction Engineering Management, ASCE, vol. 132, no. 6, pp. 636-649, 2006.   DOI   ScienceOn
16 P. Kaming, P. Olomolaiye, G. Holt, F. Harris, "Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia." Construct Management and Economics, vol. 15, pp. 83-94, 1997.   DOI
17 P.A. Koushki, K. Al-Rashid, N. Kartam, "Delays and Cost Increases in the Construction of Private Residential Projects in Kuwait." Construction Management and Economics, Vol. 23, no. 3, pp. 285-294, 2005.   DOI   ScienceOn
18 L. Le-Hoai, Y.D. Lee, J.Y. Lee, "Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with other Selected Countries." KSCE Journal of Civil Engineering, Vol. 12, no. 6, pp. 367-377, 2008   과학기술학회마을   DOI   ScienceOn
19 M.M. Marzouk, T.I. El-Rasas, "Analyzing Delay Causes in Egyptian Construction Projects." Journal of Advanced Research, 2013.
20 M. Sambasivan, Y.W. Soon, "Causes and Effects of Delays in Malaysian Construction Industry." International Journal of Project Management, vol. 25, pp. 517-526, 2007.   DOI   ScienceOn
21 MD.R.R. Shaon, "Investigation of Construction Delay of Real Estate Companies in Dhaka City", Bachelor of Science thesis, Bangladesh University of Engineering and Technology, Dhaka, Bangladesh, 2012.
22 MD. A. Hasan, "Evaluation of Building Construction Management in Sylhet City, Bangladesh" KICEM Journal of Construction Engineering and Project Management, vol. 2, no.2, pp. 40-47, 2012.   과학기술학회마을   DOI   ScienceOn
23 H. A. Rahman, M. A. Berawi, A.R. Berawi, O. Mohamed, M. Othman, I.A. Yahya, "Delay mitigation in the Malaysian construction industry." Journal of Construction Engineering Management, vol. 132, no. 2, pp.125-133, 2006.   DOI   ScienceOn