Front End Planning Tool (FEPT) Based on an Electronic Process Management  

Safa, Mahdi (Department of Civil and Environmental Engineering, University of Waterloo)
Haas, Carl T. (Department of Civil and Environmental Engineering, University of Waterloo)
Hipel, Keith W. (Department of Systems Design Engineering, University of Waterloo)
Gray, Joel (Coreworx Inc.)
Publication Information
Journal of Construction Engineering and Project Management / v.3, no.2, 2013 , pp. 1-12 More about this Journal
Abstract
Research indicates that good front-end planning (FEP) results in the achievement of higher levels of project performance. By facilitating collaboration among stakeholders in diverse locations with the use of workflow-enabled processes, such pressures can be reduced, and the overall process and results of FEP can be improved. With these goals, a front-end planning tool (FEPT) has been developed as support for owners and major contractors who are engaged in front-end planning. This paper presents the new FEPT and describes how it has been used for construction megaprojects in the nuclear power, oil and gas, and mining industries. The paper begins with the definitions related to and an explanation of the general process for implementing and applying the FEPT and then describes and analyzes how the FEPT was applied in case study projects in order to test its validity. The results indicate that the FEPT increases the efficiency and effectiveness of front-end planning for the megaprojects studied and that it has the potential to produce similar results for other megaprojects.
Keywords
front-end planning; supply chain; document management; workflow;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 T.R. Stacey, "Design-a strategic issue. Proc. 2nd Int. Seminar on Strategic vs Tactical Approaches in Mining, Perth, Australia", Australian Centre for Geo mechanics, Section 4, pp. 13, 2006.
2 T. Williams, K. Samset, "Issues in Front-End Decision Making on Projects", Project Management Journal, vol. 41, no. 2, pp. 38-49, 2010.   DOI   ScienceOn
3 Construction Industry Institute (CII), "Break the Rules and Pay the Price", RS213-1, Construction Industry Institute (CII), Austin, Texas, 2008.
4 G.E. Gibson, "The real value of front end planning for capital projects", FIATECH Webinar, http://fiatech.org/webinar-archives, 2010.
5 K. London, R. Kenley, A. Agapiou, "Theoretical Supply Chain Network Modelling in the Building Industry", 14th Annual Association of Research in Construction Management, pp. 369-379, 1998.
6 R. Vrijhoef, L. Koskela, "The Four Roles of Supply Chain Management in Construction", European Journal of Purchasing & Supply Management, vol. 6, pp. 169-178, 2000.   DOI   ScienceOn
7 Emerson Process Management, "Front End Engineering Design Capabilities", Emerson Process Management, USA, 2005.
8 Chiyoda Corporation, "FEED (Front End Engineering Design)", http://www.chiyoda-corp.com/service/en/plant/feed.html, 2012.
9 Bentley, "Best Practices in Front-End Design", A Bentley White Paper, www.bentley.com, 2008.
10 G. Stephen, W. Hughes, D. Ancell, "Risk under performance-based contracting in the UK construction sector", Construction Management & Economics, vol. 25, no. 7, pp. 691-99, 2007.   DOI   ScienceOn
11 S. Konukcu, C. Anumba, P. Carrillo, "The need for knowledge chains in construction", Rotterdam (Netherlands) in-house publishing, 2008.
12 S. Laryea, W. Hughes, "Risk and price in the bidding process of contractors", Journal of Construction Engineering and Management, ASCE, vol. 137, no. 4, pp. 248-260, 2011.   DOI   ScienceOn
13 K.M. Cho, T.H. Hong, C.T. Hyun, "Effect of project characteristics on project performance in construction projects based on structural equation model", Expert Systems with Applications, vol. 36, no. 7, pp. 10461-10470, 2009.   DOI   ScienceOn
14 C. Cheah, M. Garvin, J. Miller, "Empirical Study of Strategic Performance of Global Construction Firms", Journal of Construction Engineering and Management, ASCE, vol. 130, no. 6, pp. 808-817, 2004.   DOI   ScienceOn
15 C.Y.J. Cheah, D.A.S. Chew, "Dynamics of strategic management in the Chinese construction industry", Management Decision, vol. 43, no. 4, pp. 551-567, 2005.   DOI   ScienceOn
16 B. Kidd, "Validate definitions and experiences with project stages", http://www.kentz.com/what-we-do/specialist-epc/15/kentz-integrated-solutions, Tele-conference (interview), Husky Energy Inc, September 15, 2011.
17 A. Griffith, G. Gibson, "Alignment during pre-project planning", Journal of Management in Engineering, ASCE, vol. 17 , no. 2, pp. 69-76, 2001.   DOI   ScienceOn
18 S.K. Lee, J.H. Yu, "Critical Success Factors for Project Management Information System in Construction" Journal of Construction Engineering and Project Management, vol. 1, no. 1, pp. 25-30, 2011.   과학기술학회마을   DOI   ScienceOn
19 S. Shokri, M. Safa, C. Haas, R. Haas, "A Conceptual Framework to Improve Information and Process Management in the Execution of Capital Projects", 3rd International/9th Construction Specialty Conference, Ottawa, Ontario, 2011.
20 Tenaska Trailblazer Partners, LLC, "Final Front End Engineering and Design Study Report", Report to the Global CCS Institute, 2012.
21 KBR Inc., "KBR Awarded FEED and Project Management Services Contract by Saudi Aramco for the Jazan Refinery and Marine Terminal Project", http://www.kbr.com/Newsroom/Press-Releases/2011/02/09/KBR-Awarded-FEED-and-Project-Management-Services-Contract-by-Saudi-Aramco-for-the-Jazan-Refinery-and-Marine-Terminal-Project/, 2011.
22 G. Briscoe, A. Dainty, S. Millett, "Construction supply chain partnerships: skills, knowledge and attitudinal requirements", European Journal of Purchasing & Supply Management, vol. 7, no. 4, pp. 243-255, 2001.   DOI   ScienceOn
23 C.T. Hyun, Y.W. Cha, R.Z. Jin, M.J. Son, "Change and contract management modules of intelligent- program management information systems (i-PgMIS) for urban renewal project", Gerontechnology, vol. 11, no. 2, pp. 172-179, 2012. http://dx.doi.org/10.4017/gt.2012.11.02.419.00, 2012.   DOI
24 J.H. Tah, "Toward an agent-based construction supply network modeling and simulation platform", Automation in Construction, vol. 14, no. 3, pp. 353-359, 2005.   DOI   ScienceOn
25 A. Cox, P. Ireland, M. Townsend, "Managing in Construction Supply Chains and Markets", London, United Kingdom: Thomas Telford Publishing, 2006.
26 Construction Industry Institute (CII), "Pre-project planning handbook", SP39-2, Construction Industry Institute (CII), Austin, Texas, 1995.
27 D.I. Cleland, L.R. Ireland, "Project management: Strategic design and implementation", New York: McGraw-Hill, 2002.
28 G. E. Gibson, J. H. Kaczmarowski, H. E. Lore, "Pre-project planning process for capital facilities", Journal of Construction Engineering and Management, ASCE, vol. 121, no. 3, pp. 312-318, 1995.   DOI   ScienceOn
29 G. Bates, "Envisioning Successful Construction: Project Planning is the Key", Journal of Management in Engineering, vol. 11, no. 4, pp. 3, 1995.
30 D.A Whittington, G.E. Gibson, Q. Cui, "Analysis Supporting Front End Planning for Renovation and Revamp Projects, Part 2", RR242-12, Construction Industry Institute (CII), Austin, Texas, 2009.
31 S.M. AbouRizk, "Value for Money Audit: Project Management-Cost Estimating" Report to City of Edmonton, Office of the Auditor General, 1998.
32 M.Z.A Abd Majid, R. McCaffer, "Factors of Non-Excusable Delays that Influence Contractors'Performance", Journal of Management in Engineering, vol. 14, no. 3, pp. 42-48, 1998.   DOI   ScienceOn
33 S. T. Ariaratnam, C. W. MacLeod, "Financial outlay modelling for a local sewer rehabilitation strategy," Journal of Construction Engineering and Management, vol. 128, no. 6, pp. 486-495, 2002.   DOI   ScienceOn
34 D.N. Ford, D.M. Lander, J.J. Voyer, "A real options approach to valuing strategic flexibility in uncertain construction projects", Construction Management and Economics, vol. 20, pp. 343-351, 2002.   DOI   ScienceOn