Development of a methodology for analysing and quantifying the impact of delay factors affecting construction projects  

Shebob, Abdulhamid (School of Science and Engineering (SSE), Teesside University)
Dawood, Nashwan (School of Science and Engineering (SSE), Teesside University)
Shah, Raj K. (School of Science and Engineering (SSE), Teesside University)
Publication Information
Journal of Construction Engineering and Project Management / v.2, no.3, 2012 , pp. 17-29 More about this Journal
Abstract
Delays are one of the biggest problems facing by the construction industry and they have significant financial and social impact in construction projects. The paper presents a framework of Delay Analysis System (DAS) with the aim of analysing the impact of delay factors in Libyan construction projects. The system has designed by integrating the possible delay factors, critical activities of a project using@risk simulator. A case study of building project was demonstrated to identify the impact of delays and the sensitivity of delay factor. The case study result showed that the project might be delayed by 97 to 103 days in comparison to the planned duration. The developed DAS is a tool for analysing and identify the impacts of delay factors and assist to construction manager to take necessary measure in reducing the delay impact. The paper provides a methodology for analysing the possible delay impact in a construction project and informing to construction manager in advance of the possible delay factors.
Keywords
construction delay; industry survey; importance weight; critical delay factors; delay analysis system;
Citations & Related Records
연도 인용수 순위
  • Reference
1 M. Mezher, W. Tawil, "Causes of delays in the construction industry Lebanon", Engineering Construction and Architectural Management, vol. 5, no. 3, pp. 251-260, 1998.
2 C.A.R. Morano, C.G. Martins, M.L.R. Ferreira, "Application of techniques for the identification of risk in the E & P ventures Engevista", vol. 8, no. 2, pp. 120-133, 2006.
3 R. Sonmez, J.E. Rowings, "Construction labor productivity modelling with neural networks", Journal of Construction Engineering and Management, vol. 124, no. 6, pp. 498-504, 1998.   DOI
4 S.O. Ogunlana, K. Prokuntong, V. Jearkjirm, "Construction Delays in Fast Growing Economy Comparing Thailand with Other Economies", International Journal of Project Management, vol. 14, no. 1, pp. 37-45, 1996.   DOI   ScienceOn
5 W. Alaghbari, M.R.A. Kadir, A. Salim, Ernawati "The significant factors causing delay of building construction projects in Malaysia", Engineering, Construction and Architectural Management, vol. 14, no. 2, pp. 192-206, 2007.   DOI   ScienceOn
6 Y. Kim, K. Kim, D. Shin, "Delay Analysis Method Using Delay Section" Journal of construction engineering and management, vol. 131, no. 11, pp. 1155-1164, 2005.   DOI   ScienceOn
7 E.K. Zaneldin, "Construction claims in United Arab Emirates: Types, causes, and frequency", International Journal of Project Management, vol. 24, no. 5, pp. 453-459, 2006.   DOI   ScienceOn
8 T.M. Zayed, D.W. Halpin, "Pile Construction Productivity Assessment", Journal of Construction Engineering and Management, vol. 131, no. 6, pp. 705-714, 2005.   DOI   ScienceOn
9 N. Dawood, "Estimating project and activity duration: a risk management approach using network analysis", Construction Management and Economics, vol. 16, no. 1, pp. 41- 48, 1998.   DOI
10 Y. Frimpong, J. Oluwoye, I. Crawford, "Statistical methods", 2nd ed., Academic, New York, 2003.
11 General People's Committee, Regarding permission for investors to execute their investment activities in Libya, decision no. (22) 2003.
12 A.S. Hanna, M. Gunduz, "Early warning signs for distressed projects", Canadian Journal of Civil Engineering, vol. 32, no. 5, pp. 796-802, 2005.   DOI   ScienceOn
13 P. Jaskowski, S. Biruk, "The conceptual framework for construction project risk assessment", Reliability: Theory & Applications, vol. 2, no. 3, pp. 27-35, 2011.
14 E.J. Jaselskis, D.B. Ashley, "Optimal allocation of project management resources for achieving success", Journal of Construction Engineering and Management, vol. 117, no. 2, pp. 321-340, 1991.   DOI
15 Y.C. Kog, D.K.H Chua, P.K. Loh, E.J. Jaselskis, "Key determinants for construction schedule performance", International Journal of Project Management, vol. 17, no. 6, pp. 351-359, 1999.   DOI   ScienceOn
16 S.T. Kometa, P.O. Olomolaiye, F.C. Harris, "Attributes of UK construction clients influencing project consultants' performance", Journal of Construction Management and Economics, vol. 12, no. 5, pp 433-443, 1994.   DOI   ScienceOn
17 S. AbouRizk, P. Knowles, U.R. Hermann, "Estimating labor production rates for industrial construction activities", Journal of Construction Engineering and Management, vol. 127, no. 6, pp. 502- 511, 2001.   DOI   ScienceOn
18 S. Lee, D.W. Halpin, "Predictive tool for estimating accident risk", Journal of Construction Engineering and Management, vol. 129, no. 4, pp. 431-436, 2003.   DOI   ScienceOn
19 N.R. Mansfield, "Causes of delay and cost overruns in Nigerian construction project", International Journal of Project Management, vol. 12, no. 4, pp. 254-260, 1994.   DOI   ScienceOn
20 A.A. Bubshait, M.J. Cunningham, "Comparison of delay analysis methodologies", Journal of Construction Engineering and Management, vol. 124, no. 4, pp. 315-322, 1998.   DOI   ScienceOn
21 O. Abdelnaser, J. Peter, A. Mahmood, A. Hussin, H. Aziz, "Causes of construction delays", case studies in Langkawi Island, Malaysia, Paper presented at International Conference on built environmental in Kuala Lumpur, Malaysia, organized by University of Malaya, 2005.
22 S.M. Ahmed, S. Azhar, P. Kappagntula, D. Gollapudil, "Delays in construction: a brief study of the Florida construction industry", Proceedings of the 39th Annual ASC Conference, Clemson University, Clemson, SC, USA, pp. 257-266, 2003.
23 W.A.M. Alaghbari, "Factors affecting construction speed of industrialized building systems in Malaysia", Master's thesis, University Putra Malaysia, Serdang, 2005.
24 A.H. Al-Moumani, "Construction Delay: a quantitative analyses", International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000.   DOI   ScienceOn
25 D.K.H. Chua, Y.C. Kog, P.K. Loh, E.J. Jaselskis, "Model for construction budget performance neural network approach", Journal of Construction Engineering and Management, vol. 123, no. 3, pp. 214-222, 1997.   DOI   ScienceOn
26 S.A. Assaf, M. Al-Khalil, M. Al-Hazmi, "Causes of Delay in Large Building Construction Projects", Journal of Project Management in Engineering, vol. 11, no. 2, pp. 45-50, 1995.