Browse > Article
http://dx.doi.org/10.5370/JEET.2015.10.3.740

Comparison of the Operational Speed of Hard-wired and IEC 61850 Standard-based Implementations of a Reverse Blocking Protection Scheme  

Mnguni, Mkhululi Elvis Siyanda (Dept. of Electrical, Electronic and Computer Engineering, Cape Peninsula University of Technology)
Tzoneva, Raynitchka (Dept. of Electrical, Electronic and Computer Engineering, Cape Peninsula University of Technology)
Publication Information
Journal of Electrical Engineering and Technology / v.10, no.3, 2015 , pp. 740-754 More about this Journal
Abstract
This paper focuses on the reverse blocking busbar protection scheme with aim to improve the speed of its operation and at the same time to increase operational reliability, flexibility and stability of the protection during external and internal faults by implementation of the extended functionality provided by the IEC61850 standard-based protective Intelligent Electronic Devices (IEDs). The practical implementation of the scheme by the use of IEC 61850 standard communication protocol is investigated. The proposed scheme is designed for a radial type of a distribution network and is modeled and simulated in the DigSILENT software environment for various faults on the busbar and its outgoing feeders. A laboratory test bench is built using three ABB IEDs 670 series that are compliant with the IEC 61850 standard, CMC 356 Omicron test injection device, PC, MOXA switch, and a DC power supplier. Two types of the reverse blocking signals between the IEDs in the test bench are considered: hard wired and Ethernet communication by using IEC 61850 standard GOOSE messages. Comparative experimental study of the operational trip response speeds of the two implementations for various traffic conditions of the communication network shows that the performance of the protection scheme for the case of Ethernet IEC 61850 standard-based communication is better.
Keywords
Busbar; Power system; Reverse busbar blocking scheme; IEC61850 standard; Distribution systems; Protection relays; IEDs; GOOSE message; Laboratory test bench;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Gill, H.S., Sidhu, T.S. & Sachdev, M.S. 2000. Microprocessor-based busbar protection system Generation, Transmission and Distribution, IEE Proceedings-, 147(4):252-260.   DOI   ScienceOn
2 Warrington, A.R.v.C. 1978. Erratum: Protective Relays: “Their Theory and Practice” Vol. 2. Electronics and Power, 24(8):599.
3 Kasztenny, B. & Cardenas, J. 2004, “New phase-segregated digital busbar protection solutions”, Protective Relay Engineers, 2004 57th Annual Conference for, pp. 308.
4 Yu Nan-hua & Gao Xin-Hua 2010, “Experimental research on 10kV fast busbar protection system with GOOSE technology”, Electricity Distribution (CICED), 2010 China International Conference on, pp. 1.
5 Kasztenny, B., Whatley, J., Urden, E.A., Burger, J., Finney, D. & Adamiak, M. 2006, “JEC 61850 - A Practical Application Primer for Protection Engineers”, Power Systems Conference: Advanced Metering, Protection, Control, Communication, and Distributed Resources, 2006. PS ’06, pp. 18.
6 Gustavo, B. 2003. microprocessor-based relays and enabler to scada integration. Electricity Today, Issue 4, 2003, page 10-11.
7 Duncan, B. & Self, H. 2006, “Applications and Advantages for Protection schemes using IEC 61850 Standard”, Power Systems Conference: Advanced Metering, Protection, Control, Communication, and Distributed Resources, 2006. PS '06, pp. 63.
8 Andersson, L., Brunner, C. & Engler, F. 2003, “Substation automation based on IEC 61850 with new process-close technologies”, Power Tech Conference Proceedings, 2003 IEEE Bologna, pp. 6, pp. Vol. 2.
9 IEEE Recommended Practice for Industrial and Commercial Power Systems Analysis, IEEE Std 399-1997 September

10 Thekla N. Boutsika and Stavros A. Papathanassiou, "Short-circuit calculations in networks with distributed generation," Elsevier ScienceDirect, Electric Power Systems Research, Dec. 2007.
11 Network protection automation guide first adition July 2002 htpp://www.areva-td.com.
12 ABB-Oy, D.A. 2011. Distribution Automation Handbook. FI-65101 Vaasa, FINLAND).
13 B.C. Sung, and S.H Lee, "Adaptive Protection Alogorithm for Overcurrent Relay in Distribution system with DG," JEET Vol. 8, No. 5 pp.1002-1011, Korea, School of Electrical and Electronic Engineering, Yonsie University May 2013.
14 H.J. Lee, G. T. Son, and J.W. Park, "Study on Wind-Turbine Generator System Sizing Considering Voltage Regulation and Overcurrent Relay Coordination," IEEE Trans. Power Systems, vol. 26, no. 3, pp. 1283-1293, Aug. 2011.   DOI   ScienceOn
15 Bertil, L., Berith, B. & Torbjörn, E. 2007. A user friendly implementation of IEC 61850 in a new generation of protection and control devices ABB Power Technologies AB (Sweden)
16 Wireshark Network Analyser software. Available from: http://www.wireshark.org/ [27 March 2014]
17 Mnguni, M., 2014.Investigation of the application of IEC 61850 standard in distribution busbar protection schemes Cape Peninsula University of Technology (South Africa)

18 Jiaying Miao; Dostanov, D.; Redfern, M. Using IEC 61850 Data Transfere beyond the Substation for Enhanced Protection for distribution Networks, Power Engineering Conference (UPEC), 2013 48th International Universities'