Scenario Analysis of Natural Gas Demand for Electricity Generation in Korea  

Park, Jong-Bae (Dept. of Electrical Engineering, Konkuk University)
Roh, Jea Hyung (Dept. of Electrical Engineering, Konkuk University)
Publication Information
The Transactions of The Korean Institute of Electrical Engineers / v.63, no.11, 2014 , pp. 1503-1510 More about this Journal
Abstract
This study organizes scenarios on the power supply plans and electricity load forecasts considering their uncertainties and estimates natural gas quantity for electricity generation, total electricity supply cost and air pollutant emission of each scenario. Also the analysis is performed to check the properness of government's natural gas demand forecast and the possibility of achieving the government's CO2 emission target with the current plan and other scenarios. In result, no scenario satisfies the government's CO2 emission target and the natural gas demand could be doubled to the government's forecast. As under-forecast of natural gas demand has caused the increased natural gas procurement cost, it is required to consider uncertainties of power plant construction plan and electricity demand forecast in forecasting the natural gas demand. In addition, it is found that CO2 emission target could be achieved by enlarging natural gas use and demand-side management without big increase of total costs.
Keywords
Power supply and demand plan; supply and demand uncertainties; electricity-sector natural gas demand forecasting;
Citations & Related Records
연도 인용수 순위
  • Reference
1 NETL, "Life Cycle Analysis: Power Studies Compilation Report", 2010.
2 Wood Mackenzie, "Japan and Korea LNG procurement . Searching for clarity", Global Gas Insight, 2013.
3 ASTE, "The Hidden Costs of Electricity: Externalities of Power Generation in Australia", 2009.
4 Ministry of Trade, Industry and Trade, "The 6th Basic Plan of Electricity Supply and Demand", 2012.
5 J. Park, N. Ahn, Y. Yoon, K. Koh, D. W. Bunn, "Investment Incentives in the Korean Electricity Market", Energy Policy, Vol 36, No. 11, pp. 5819-5828, Nov. 2007
6 Ministry of Trade, Industry and Trade, "The 1st Basic Plan of Electricity Supply and Demand", 2002.
7 Ministry of Trade, Industry and Trade, "The T/F Report on Brown Out", 2011.
8 Korea Energy Management Corporation, "2013 Energy Usage Statistics", 2014
9 Ministry of Trade, Industry and Trade, "The 2nd National Energy Basic Plan", 2014.
10 Y. Cho, "Review of the 2nd National Energy Basic Plan and Pending Issues", Journal of the Electric World, Vol. 447, pp. 58-63, 2014.
11 Ministry of Trade, Industry and Trade, "The 11th Basic Plan of Natural Gas Supply and Demand", 2013.
12 NETL, "Life Cycle Analysis: Natural Gas Combined Cycle (NGCC) Power Plant", 2010.
13 Cambridge Energy Solutions, http://www.ces-us.com/index.asp.
14 NETL, "Life Cycle Analysis: Supercritical Pulverized Coal (SCPC) Power Plant", 2010.
15 NETL, "Life Cycle Analysis: Existing Pulverized Coal (EXPC) Power Plant", 2010.