Preparation of Radiological Environmental Impact Assessment for the Decommissioning of Nuclear Power Plant in Korea  

Lee, Sang-Ho (KEPCO International Nuclear Graduate School)
Seo, Hyung-Woo (KEPCO International Nuclear Graduate School)
Kim, Chang-Lak (KEPCO International Nuclear Graduate School)
Publication Information
Journal of Nuclear Fuel Cycle and Waste Technology(JNFCWT) / v.16, no.1, 2018 , pp. 107-122 More about this Journal
Abstract
Kori unit 1, the oldest commercial nuclear power plant in South Korea, was permanently shut down in June 2017. There are a lot of things to consider in decommissioning nuclear power plants, and one of them is the radiological environmental impact assessment. Performed to promote the health and safety of residents around the nuclear power plant, radiological environmental impact assessment aims to confirm that off-site radiological dose from radioactive material released from the facility does not exceed the regulatory criteria. There are three main parts of environmental impact assessment: pre-decommissioning environmental monitoring, environmental monitoring during decommissioning, and impact on nearby residents. At present, although the Korea Nuclear Safety Act stipulates that radiological environmental impact assessment resulting from decommissioning should be carried out, the details have not been specified. Therefore, this paper compares and analyzes guidelines for evaluation of radiological environmental impacts of nuclear power plants overseas, and presents a draft on the assessment of radiological dose resulting from decommissioning according to the Korean situation.
Keywords
Radiological environmental impact assessment; Decommissioning plan; Environmental report;
Citations & Related Records
연도 인용수 순위
  • Reference
1 United States Nuclear Regulatory Commission, "10CFR 50.82 Termination of License", August 2017.
2 Dominion Engergy Kewaunee, "Kewaunee Power Station Post-Shutdown Decommissioning Activities Report", February 2013.
3 Sacramento Municipal Utility District, "Rancho Seco Post-Shutdown Decommissioning Activities Report", July 2003.
4 Duke Energy, "Crystal River Unit 3 - Post Shutdown Decommissioning Activities Report", December 2013.
5 Nuclear Safety and Security Commission, "Regulations on Technical Standards such as reactor facilities", NSSC, June 2016.
6 Nuclear Safety and Security Commission, "Regulation for the Preparation of Nuclear Decommissioning Plans", NSSC Notice 2015-8, July 2015.
7 Nuclear Safety and Security Commission, "Standards on Radiation Protection", NSSC Notice 2016-16, August 2016.
8 Nuclear Safety and Security Commission, "Regulation on the Radiation Environment Survey and Radiological Environmental Impact Assessment around Nuclear Facilities", NSSC Notice 2014-12, November 2014.
9 Ineternational Atomic Energy Agency, "Decommissioning of Facilities Using Radioactive Material, Safety Requirements No.WS-R-5", October 2006.
10 International Atomic Energy Agency, "Standrad Format and Content for Safety Related Decommissioning Documents, Safety Report Series No.45", July 2005.
11 NUREG-0586, "Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities", NRC, November 2002.