Analysis of Causes of Increase in Construction Cost and Minimize Increase of Cost through Performance Evaluation of Public Construction Projects

공공건설사업의 성과평가를 통한 공사비 증가 원인 분석 및 증가 최소화 방안

  • 문현석 (서울연구원 탄소중립센터) ;
  • 류근호 (서울특별시 감사위원회) ;
  • 홍현기 (서울특별시 기획조정실)
  • Received : 2024.04.01
  • Accepted : 2024.06.26
  • Published : 2024.08.01

Abstract

The government and local governments are utilizing regulations, policies, and various project management techniques at each project stage to effectively and systematically manage public construction projects. However, the increase in construction costs continues to occur. In order to solve these problems, this study attempted to collect cases of existing public construction projects and analyze historical data. And it would like to derive the impact factor of increased construction costs. Based on the results, a plan was proposed to prevent the causes of increase and minimize in construction costs. The main reasons for the increase in costs were the occurrence of civil petition, differences between design documents and site conditions, and changes due to requests from the owner and changes in the business plan. And to solve these problems, this study proposed improvement for each cause from an institutional perspective, along with interview with experts and project owners. The results of this study are significant in improving the process of existing public construction process and presenting key inspection and review items for each major inspection stage in order to solve problem resulting from the analysis of the performance of public construction projects.

공공건설사업을 효과적이고 체계적으로 관리하기 위해서 정부와 지방자치단체는 건설사업 관련 제도와 정책, 그리고 사업단계별로 다양한 사업 관리 기법들을 활용하고 있으나 공사비의 증가는 계속 발생하고 있다. 이러한 문제를 해결하기 위하여 본 연구에서는 기존에 수행되었던 공공건설사업의 사례를 수집하여 실적 데이터를 분석하고 공사비의 증가 원인을 사례에 기반하여 도출하고자 하였다. 그리고 분석 결과를 토대로 공사비의 증가 원인을 예방하고 공사비 증가를 최소화하는 방안을 제안하고자 하였다. 분석 결과, 공사비 증가 원인은 민원 발생, 설계도서와 현장상태의 상이, 그리고 사업계획 변경 및 발주자의 요청이 주요 원인으로 도출되었고, 본 연구는 전문가와 발주자의 자문과 각각의 원인별 개선 방안을 제도적인 측면에서 제안하였다. 이 연구의 결과는 공공건설사업의 공사비 증가 문제점을 해결하기 위하여 기존 공공건설 프로세스를 개선하고, 주요 점검 단계별로 중점 점검 및 검토 사항을 제시하였다는 것에 의의가 있다.

Keywords

References

  1. Akinradewo, O., Aigbavboa, C., Oke, A., Coffie, H. and Ogunbayo, B. (2022). "Unearthing causative factors of cost overrun on ghanaian road projects." The Baltic Journal of Road and Bridge Engineering, Riga Technical University, Vol. 17, No. 4, pp. 171-188, https://doi.org/10.7250/bjrbe.2022-17.584. 
  2. Anigbogu, N. A., Ahmad, Z. B. and Molwus, J. J. (2019). "Cost overruns on federal capital territory authority road construction projects." FUTY Journal of the Environment, Federal University, Vol. 13, No. 1, pp. 1-14. 
  3. Ammar, T., Abdel-Monem, M. and El-Dash, K. (2022). "Risk factors causing cost overruns in road networks." Ain Shams Engineering Journal, Ain Shams University, Vol. 13, No. 5, 101720, https://doi.org/10.1016/j.asej.2022.101720. 
  4. Busan Metropolitan City. (2020). Management guidelines of total project cost (in Korean). 
  5. Chamuwange, S. K. and Ning, Y. (2022). "Identifying the factors affecting the cost management of road construction projects in Tanzania." Journal of Civil, Construction and Environmental Engineering, SciencePG, Vol. 7, No. 3, pp. 35-39, https://doi.org/10.11648/j.jccee.20220703.13. 
  6. Creedy, G. D., Skitmore, M. and Wong, J. K. (2010). "Evaluation of risk factors leading to cost overrun in delivery of highway construction projects." Journal of Construction Engineering and Management, ASCE, Vol. 136, No. 5, pp. 528-537, https://doi.org/10.1061/(ASCE)CO.1943-7862.0000160. 
  7. Dolage, D. A. R. and Dasantha, O. M. C. (2022). "Critical factors affecting cost overrun in foreign funded road construction projects in Sri Lanka." Engineer, The Institution of Engineers, SriLanka, Vol. 55, No. 2, pp. 21-30, https://doi.org/10.4038/engineer.v55i2.7505. 
  8. Du, S. G. (2016). Research on reasonable civil petition handling in construction projects, Construction & Economy Research Institute of Korea (in Korean). 
  9. Gyeonggi-Do (2021). Total project cost management guidelines for public construction projects (in Korean). 
  10. Jennifer, S. S., Keith, R. M., Stuart, A. and Cliff, S. (2009). "Construction project cost escalation factors." Journal of Management in Engineering, ASCE, Vol. 25, No. 4, pp. 221-229, https://doi.org/10.1061/(ASCE)0742-597X(2009)25:4(221). 
  11. Kaliba, C., Muya, M. and Mumba, K. (2009). "Cost escalation and schedule delays in road construction projects in Zambia." International Journal of Project Management, Elsevier, Vol. 27, No. 5, pp. 522-531, https://doi.org/10.1016/j.ijproman.2008.07.003. 
  12. Kirkham, R., Williams, T., Vo, H., Cook-Davies, T., Howells, A. and Forster, R. (2021). "An empirical study of assurance in the UK government major projects portfolio: from data to recommendations, to action or inaction." International Journal of Managing Projects in Business, Vol. 14, No. 4, pp. 865-897. 
  13. Kurniawan, D., Mairizal, Masril, Sam, A. R. M. and Abd Majid, M. Z. (2022). "Critical risk factor affecting cost overrun in highway project of west sumatra." Proceedings of IOP Conference Series: Earth and Environmental Science, IOP, Vol. 1022, No. 1, 012013, https://doi.org/10.1088/1755-1315/1022/1/012013. 
  14. Lee, K. E. (2012). The Study on the Priority of Cost-Increasing Factors in Public Construction Project, Msc. Dissertation, Dong-A University (in Korean). 
  15. Lee, Y. M. (2013). Study on Cost Increasing Factor of Road in the Construction Phase, Msc. Dissertation, Pukyong National University (in Korean). 
  16. Ministry of Construction & Transportation (MOCT) (2007). Handling manual of civil petition for public construction projects (in Korean). 
  17. Ministry of Economy and Finance (MOEF) (2023a). Management guidelines of total project cost (in Korean). 
  18. Ministry of Economy and Finance (MOEF) (2023b). National Finance Act (in Korean). 
  19. Ministry of Land, Infrastructure and Transport (MOLIT) (2024). Construction Technology Promotion Act (in Korean). 
  20. Ministry of the Interior and Safety (MOIS) (2024). Local Finance Act (in Korean). 
  21. Moon, H. S., Jung, H. Y. and Go, J. H. (2020). Efficient project implementation methods through performance evaluation of large-scale public construction projects. Seoul Metropolitan Government (in Korean). 
  22. Mun, J. B., Lee, J. H., Baek, S. W., Lee, K. W. and Yun, S. M. (2023). "Standardization of factors classification associated with cost and schedule variations in road construction projects." KSCE Journal of Civil Engineering, KSCE, Vol. 43, No. 6, pp. 821-830, https://doi.org/10.12652/Ksce.2023.43.6.0821 (in Korean). 
  23. Office of Government Commerce (OGC) (2007). The OGC GatewayTM Process. Gateway to Success. 
  24. Office of Management Budget (OMB) (2023a). Capital programming guide supplement to office of management budget circular A-11: Planning, Budgeting, and Acquisition of capital assets. 
  25. Office of Management Budget (OMB) (2023b). Preparation, Submission, and Execution of the Budget. 
  26. Park, S. Y. (2017). "Management system for large-scale capital expenditures in UK: Focusing on Gateway Review Process." Monthly Public Finance Information, Korea Fiscal Information Service, Vol. 1, No. 11, pp. 22-31 (in Korean). 
  27. Seoul Metropolitan Government (2014). Construction manual (in Korean). 
  28. Seoul Metropolitan Government (2018). Management manual for construction technology service (in Korean). 
  29. Sim, S. D., Jang, J. K. and Song, J. Y. (2004). Efficient budget management of public investment projects III: Focusing on the operational performance and future improvement plans of the total project cost management system. Korea Development Institute (in Korean). 
  30. Woo, S. K., Lee, Y. H., Chang, C. K. and Lee, S. W. (2012). "A study on analysis of productive construction project and influential elements for public owner's perspective: focused on highway construction." Journal of the Korean Society of Civil Engineers, KSCE, Vol. 32, No. 6D, pp. 645-653, https://doi.org/10.12652/Ksce.2012.32.6D.645 (in Korean). 
  31. Yoon, B. H. (2009). Risk Assessment of Cost Increasing by Change Orders of Road Projects, Msc. Dissertation, Yonsei University (in Korean).