A Study on the Significance of Unit Capacity Factor (Utilization Rate) of Nuclear Power Plants and Measures for Increasing

원전 이용률의 의의 및 증진방안 고찰

  • Received : 2022.12.08
  • Accepted : 2022.12.21
  • Published : 2022.12.30

Abstract

Unit capacity factor (utilization rate) of nuclear power plants (NPPs) is an important performance indicator. Since the first commercial operation of Kori Unit 1 began in April 1978, the utilization rate of domestic NPPs has gradually increased, reaching 90% from the end of the 1990s. However, due to various issues such as the Fukushima accident in 2011, corrosion of the CLP, the utilization rate dropped to 65~80%. In the early 1980s, the utilization rate of the U.S. NPPs was around 60%. However, since 2004, it has been consistently maintained above 90%. Therefore, in this study, we first examined the causes of declining the utilization rate in domestic NPPs. Next, the significances of the utilization rates are reviewed in five aspects: investment capability, electricity rate, safety and export, etc., with discussion on the current status of the utilization rates in the U.S. Based on this, three key factors are derived as the reasons of the increasing: equipment reliability program, on-line maintenance and the pursuit of institutional rationality. And finally, by synthesizing above results, the measures for increasing the utilization rate of domestic NPPs are proposed in terms of equipment management, institutional improvements, and personnel resources.

Keywords

References

  1. NEI, 2017, Industry standardized performance indicators, Nuclear Energy Institute, Washington, DC, Efficiency Bulletin 17-24.
  2. The JoongAng article, 2022, Consideration of raising the use of nuclear power plants from 70% to 90%.
  3. IAEA Power Reactor Information System - World statics, 2022, http://pris.iaea.org/pris/.
  4. KHNP, 2022, "21st Business Report of KHNP, Korea Hydro and Nuclear Power Co. Ltd., Kyeongju-si.
  5. Business Post article, 2022, Power sales and operation profits of KHNP(Unit: KRW 100 million).
  6. Maekyung article, 2022, Using 10% less electricity cuts the trade deficit in half.
  7. The JoongAng article, 2022, Simultaneous rise in electricity and gas rates, self-employed people only sigh.
  8. Seoul Economic Daily article, 2022, Electricity bill phobia... 50% more next year.
  9. Data Universe, 2006, IPCC(Intergovernmental Panel on Climate Change) Carbon Emission factor, https://slidesplayer.org/slide/14110741/.
  10. Maekyung article, 2022, Low-efficiency solar power pushes ahead, electricity bills boomerang.
  11. The JoongAng article, 2022, A blueprint for renewable energy without a strategy, opening the KEPCO power grid is the answer.
  12. MOTIE, 2022, The 10th basic plan for electricity supply and demand, Ministry of Trade, Industry and Energy, Sejong-si.
  13. MOTIE, 2021, 2030 national greenhouse gas reduction goal upward plan, Ministry of Trade, Industry and Energy, Sejong-si.
  14. Susan G., 2022, U.S. nuclear capacity factors ; A smaller fleet invested in the future, Nuclear News (http://ans.org/nn), pp. 26-33.
  15. Harazim, M. L. and Ferguson, B. J., 2004, Equipment reliability process based on the Institute of Nuclear Power Operations(INPO) AP-913 in conjunction with a preventative maintenance living, U.S. Department of Energy, Washington, DC.
  16. Jim C., 2019, Good to Great ; Why some companies make the leap...and others don't, 1st edition 104th printing, Gimmyoungsa, Paju-si.
  17. KHNP, 2017, KHNP Standard Engineering Model (K-SEM) based on ER Process of INPO, Korea Hydro and Nuclear Power Co. Ltd., Kyeongju-si.
  18. Nuclear Safety Act and Enforcement Decree of the Nuclear Safety Act, June 2022, Nuclear Safety and Security Commission, Seoul-si.
  19. William R., Brian S., Jim W., Marc D., Tim C., Richard C., Tom M., Mark S., Roger M., Frank M. and David N., 2014, No Undue Risk ; Regulating the safety of operating nuclear power plants, U.S. Nuclear Regulatory Commission, Washington, DC, NUREC/BR-0518(https://www.nrc.gov/docs/ML1418/ML14181A493.pdf).
  20. Byun, C. S., Kim, H. J., Na, J. H., Kim, D. H. and Yang, C. K., 2017, A study on trend analysis of NPP re-operation safety management process and optimization plan for domestic application, Korea Hydro and Nuclear Power Co. Ltd., Daejeon-si.
  21. USNRC, 2006 and 2014, Operating reactor assessment program and Reactor oversight process, U.S. Nuclear Regulatory Commission, Washington, DC, IMC-0350 and NUREC/BR-0508.
  22. USNRC, 2020, Integrated risk-informed decision-making process for emergent issues, U.S. Nuclear Regulatory Commission, Washington, DC, LIC-504.
  23. INPO, 2019, Staying on Top ; Advancing a culture of continuous improvement, International Nuclear Power Operations, Atalanta, 19-003.
  24. KHNP, 2022, Basic rules for maintenance engineers and Standard guidelines for operator behavior. Korea Hydro and Nuclear Power Co. Ltd., Kyeongju-si, SG-9680-02 and SG-3035-01.