Abstract

This paper is a maintenance system for bridge represented by Class 3 and other than by law bridges. Domestic bridge are divided into Class 1 & 2 bridges and Class 3 & other than by law bridges. The number of type 3 and other than by law bridges is very large. But, it is considered to be of relatively low importance compared to Class 1 & 2 Bridge Bridge. So, in this paper is propose a maintenance system and procedure for small & medium-sized bridges. However, because the number of small & medium-sized bridges is large, it is not possible to evaluate the performance of all bridges like Class 1 & 2 bridge. The reason is the lack of manpower and budget. Based on the Risk Matrix method, a maintenance procedure was created to select the bridge for which performance evaluation should be performed first. For this purpose, basic information of the bridge is used. And, the developed maintenance procedures were applied to the bridges in actual use.

본 논문은 3종 및 법정 외 교량인 중소규모 교량에 대한 유지관리 체계를 수립하여 제안하는데 그 목적을 두고 있다. 국내 교량은 1, 2종 교량과 3종 및 법정 외 교량으로 구분된다. 3종 및 법정외 교량의 개소수는 많으나 1, 2종 교량에 비해 상대적으로 중요도가 낮은 것으로 판단된다. 따라서 본 논문에서는 이러한 중소규모 교량에 대한 유지관리 시나리오 체계를 수립하고자 한다. 하지만 중소규모 교량의 경우 그 개소수가 많아 1, 2종 교량과 같이 모든 교량에 대해 성능평가를 실시하는데 인력과 예산의 문제가 있다. 이에 따라 본 연구는 리스크 매트릭스 기법을 기반으로 교량의 기본적인 현황정보를 이용하여 현재 성능평가가 우선적으로 수행되어야할 교량을 선정하기 위한 기법을 개발하였으며, 개발된 기법에 대하여 실제 공용중인 교량을 대상으로 적용하였다.

Keywords

Acknowledgement

본 논문은 국토교통부 건설기술연구사업(과제번호 : 21SCIP-B128492-05) '중소 노후교량 실증기반 성능 및 보수보강 평가연구'의 연구비 지원으로 수행되었으며, 이에 감사드립니다.

References

  1. Kim, H. J., Ji, S. G., Kim, H. K., Kim, P. S., Jung, J. S., and Lee, M. J. (2018), Evaluation of Tension of PSC Box Girder Bridges Using Risk Matrix, Korean Journal of Construction Engineering and Management, 19(5), 53-60. https://doi.org/10.6106/KJCEM.2018.19.5.053
  2. Ji, S. G., Kim, J. S., and Kim, H. J. (2017), Probability Risk Analysis for Prestressed Concrete Bridge Post-Tension based on Risk Matrix, The Korea Institute For Structural Maintenance and Inspection, KSMI 2017 Spring Conference & Forum, 21(1), 383-384
  3. CEREMA1 (2014), RISK ANALYSIS OF VULNERABLE BRIDGES ON THE NATIONAL ROAD NETWORK IN FRANCE, Division for ransportation Infrastructure and Materials, Technical Centre for Bridge Engineering.
  4. He, Zhi. (1995), Risk management for overseas construction project, International Journal of Project Management, 13(4), 231-237. https://doi.org/10.1016/0263-7863(95)00015-I
  5. Ministry of Land, Infrastructure and Transport. (2019), Detailed guidelines for the safety control and maintenance(Performance assessment).
  6. 「Special Act On The Safety Control And Maintenance Of Establishments」, Act No. 17551, Oct. 20, 2020.
  7. 「Framework Act On Sustainable Infrastructure Management」, Act No. 17237, Apr. 7, 2020.
  8. Ministry of Land, Infrastructure and Transport. (2021), Integrated Infrastructure management system: https://www.inframanage.go.kr
  9. Ministry of Land, Infrastructure and Transport. (2020), Facility management system: https://www.fms.or.kr
  10. Ministry of Land, Infrastructure and Transport. (2020), Bridge Management System: http://nbms.kict.re.kr
  11. Lee, H.Y., Shin, B. G., Lee, Y. I., and Kim, Y. M. (2019), Suggestion of Priority Decision Method for Performance Evaluation Based on Risk Index for Small and Medium Sized Bridges, Journal of the Korea institute for structural maintenance and inspection, 23(6), 70-76.