Fig. 1. Step Scope of Schedule Management
Fig. 2. Construction Period Component
Fig. 3. RC BOX unit schedule(Before reviewing standards)
Fig. 4. RC BOX unit schedule(After reviewing standards)
Table 1. Application Standard of Non-Working day (Level 1)
Table 2. Non-Working day Calculation(Level 2)
Table 3. Multiple calendars Application(Level 3)
Table 4. Non-Working day application by region
Table 5. Annual operating rate by region
Table 6. Chuseok and Sunday in recent 20 years
Table 7. New year and Sunday in recent 20 years
Table 8. Non-Working day standard(plan)
Table 9. Working day standard(plan) by work type
Table 10. Calculation of Non-Working day standard
References
- K. H. Lee, K. R. Kim, D. W. Shin, "Estimation of Non-Working Day Considering Weather Factors in Construction Projects - Based on Estimation Periods for Improving the Forecast", Proceedings of KICEM Annual Conference : Fifth, pp. 394-397, November, 2004.
- J. H. Shin, J. A. Lee, C. S. Lee, "The estimation of Non-Working days for the Construction Project in Incheon Region", Korean Journal of Construction Engineering and Management, KICEM, Vol.11, No.6, pp. 58-64, February, 2005.
- C. D. Kim, D. H. Lee, J. S. You, J. K, You, J. H. Jung, H. K. Jung, J. H. Yu, "Calculation of Non-Working days due to Weather Favtors during Structural Steel Works", Korean Journal of Construction Engineering and Management, KICEM, Vol.7, No.4, pp. 137-145, August, 2006.
- Hanmiglobal, "Construction Management A to Z", pp.273-276, Bo Moon Dang, 2011.
- Korea occupational safety & health agency, "A study on the standard for stopping crane work according to wind velocity", pp.1-68, 2014.
- J. I. Park, "A Study on Construction Delay Computation based on CPM Technique", Kangwon University, pp.1-127, 2016.
- Korea institute of construction technology, "A Study on the Estimation Standard of Construction Duration", pp.1-145, 1992.