Verification of ERP Standard Time Using TOC Technique and Improvement of MES Routing Point

TOC 기법을 적용한 ERP 표준시간 검증 및 MES 공정실적개선

  • Kim, Sung-Min (Department of Industrial & Systems Engineering, Graduate School of Public Policy and Information Technology, Seoul National University of Science of Technology) ;
  • Ahn, Jaekyoung (Department of Industrial & Systems Engineering, Graduate School of Public Policy and Information Technology, Seoul National University of Science of Technology)
  • 김성민 (서울과학기술대학교 IT정책전문대학원 산업정보시스템전공) ;
  • 안재경 (서울과학기술대학교 IT정책전문대학원 산업정보시스템전공)
  • Received : 2018.07.31
  • Accepted : 2018.10.22
  • Published : 2018.12.31

Abstract

Recently domestic manufacturing companies have been experiencing worsening profitability and stunted growth due to the long-term economic recession and the rapid rise of developing countries such as China and Southeast Asia. These difficulties force many companies to concentrate their core competencies on new value creation and innovation in order to gain momentum for new growth. Enterprise Resource Planning (ERP) has been considered as one of viable solutions. Among the various modules in ERP, shop floor control function in the production management module is rather limited. In order to overcome this problem, Manufacturing Execution System (MES) has been used as a subsystem which has a strong information gathering power and flexibility. Both systems interact closely with each other. In particular, ERP requires fast, accurate shop floor information at MES. This paper describes how to synchronize relevant information between ERP and MES with theory of constraints (TOC). The processing time information transmitted from the MES workplace is received at the ERP workplace. In the process, the received processing time is causing information distortion in ERP, when the information gathering standard of MES is different from the ERP information interpretation standard. The Drum-Buffer-Rope theory of TOC was applied to resolve this problem, therefore, information synchronization between both systems was made. As a precondition, the standard time of the upper ERP system was rearranged according to the capacity constraints resource. As a result, standard time restructuring has affected changes in labor costs. Standard labor costs have come close to actual ones, and information synchronization of MES transmission data has improved the reliability of standard product costs, such that it enabled various company-wide restructuring actions to be much more effective.

Keywords

References

  1. Denisa, F., Bottleneck management in discrete batch production, Journal of Competitiveness, 2012, Vol. 4, No. 2, pp. 161-171. https://doi.org/10.7441/joc.2012.02.11
  2. Gattiker, T.F. and Goodhue, D.L., What happens after ERP implementation : Understanding the impact of interdependence and differentiation on plant-level outcomes, MIS Quarterly, 2005, Vol. 29, No. 3, pp. 59-585. https://doi.org/10.2307/25148668
  3. Golmohammadi, D., A study of scheduling under the theory of constraints, International Journal of production Economics, 2015, Vol. 165, pp. 38-50. https://doi.org/10.1016/j.ijpe.2015.03.015
  4. Hong, M.S., Yun, C.J., Min, B.D., and Rim, S.C., Determining CCR by considering facility cost, Journal of the Korean Operations Research and Management Society, 2004, pp. 387-391.
  5. Hwang, J.H., Realizing an Object-Oriented Informationalization for Activity-Based Business Processing, Journal of The Korea Society of IT Services, 2013, Vol. 12, No. 1, pp. 309-321. https://doi.org/10.9716/KITS.2013.12.1.309
  6. Izmailov, A., Korneva, D., and Kozhemiakin, A., Effective Project Management with Theory of Constraints, Procedia-Social and Behavioral Sciences, 2016, Vol. 229, pp. 96-103. https://doi.org/10.1016/j.sbspro.2016.07.118
  7. Jang, S.Y., State-of-the-Art of DBR Scheduling Methodology, Journal of the Korean Institute of Industrial Engineers, 2003, pp. 654-661.
  8. Jee, Y.J., TOC/JIT/MRP integration model for flexible production scheduling under dynamic manufacturing environment, Journal of the Korean Institute of Industrial Engineers, 2004, pp. 383-386.
  9. Jung, N.G., Choi, J.G., Jung, S.H., and Kim, S.J., A Study of APS System Design based on the TOC DBR, Journal of the Korean Operations Research and Management Society, 2001, pp. 532-535.
  10. Kang, D.Y., Jang, H.S., and Kim, J.K., Comparative on Impact of Qualitative and Quantitative of ERP Systems on Korean Firms, Journal of The Korea Contents Association, 2009, Vol. 9, No. 4, pp. 42-153.
  11. Kim, B.J., Kim, D.H., Lee, I.S., and Jun, C.S., A Study on a Smart Factory Layout Design Based on TOCDBR, Journal of the Korean Institute of Industrial Engineers, 2017, Vol. 43, No. 1, pp. 12-18. https://doi.org/10.7232/JKIIE.2017.43.1.012
  12. Kim, S.K. and Lee, J.H., A Study on Resource Plan for Semi-Conductor Assembly Through Wire Count Factor Based on TOC : A Case Study of S Corp., Journal of DAEHAN Association of Business Administration, 2013, pp. 1341-1356.
  13. Kim, S.K. and Lee, J.H., An Application Case of TOC Theory on Semi-Conductor Assembly Process, Journal of The Korean Operations Research And Management Society, 2010, pp. 657-662.
  14. Kim, W.S., Production Management System Constr-uction based on TOC-the case of Hwacheon Machine Tool, [dissertation], [Gwangju, Korea] : The Graduate School, Chonnam University, 2009.
  15. Kwak, T.H., An Analysis on Important Factors for Selection of Constraint Resource based on Theory of Constraints, [dissertation], [Seoul, Korea] : The Graduate School, Myongji University, 2015.
  16. Lea, B.-R., Management accounting in ERP integrated MRP and TOC environments, Industrial Management & Data Systems, 2007, Vol. 107, No. 8, pp. 1188-1211. https://doi.org/10.1108/02635570710822813
  17. Lee, J.G., Jung, Y.K., and Heo, B.K., Financial Analysis of the Effect of the ERP System Implementation and the Productivity Paradox, Journal of The Korean Academic Society of Business Administration, 2008, pp. 1-23.
  18. Lee, S.H., Application of Information Technology using Theory of Constraint, Journal of Society of Korea Industrial and Systems Engineering, 1996, Vol. 19, No. 37, pp. 271-278.
  19. Lim, K.C., An Analysis of Effect of a Fit Between Success Factors of ERP Implementation and Information Characteristics of ERP System Performance, Journal of The Korea Contents Association, 2006, Vol. 6, No. 2, pp. 136-145.
  20. Lowalekar, H. and Ravi, R.R., Revolutionizing blood bank inventory management using the TOC thinking process : An Indian case study, International Journal of Production Economics, 2017, Vol. 186, pp. 89-122. https://doi.org/10.1016/j.ijpe.2017.02.003
  21. Ministry of Science, ICT and Future Planning, February 6, 2015 Press Release, 2015, p. 3.
  22. Na, C.H., A Study on the Improvement of JIT/MRP System with Constraint, [dissertation], [Seongnam, Korea] : The Graduate School of Gachon University, 2015.
  23. Ock, Y.S. and Park, C.H., Development of the DBR Scheduling system using UML and the Visual Basic, Journal of the Korea Contents Society, 2006, pp. 31-36.
  24. Okutmus, E., Kahveci, A., and Kartasova, J., Using theory of constraints for reaching optimal product mix : an application in the furniture sector, Intellectual Economics, 2015, Vol. 9, No. 2, pp. 138-149. https://doi.org/10.1016/j.intele.2016.02.005
  25. Park, M.S., Kim, K.R., Shin, D.W., and Cha, H.S., Improvement on TACT Scheduling Method Applying Theory of Constraints, Journal of The Architectural of Institute of Korea Structure & Construction, 2006, Vol. 22, No. 6, pp. 139-146.
  26. Shin, H.S. and Kim, S.H., Research on the Typical Mis-Conceptions on Enterprise Resource Planning, Journal of The Korea Society of IT Services, 2010, Vol. 9, No. 20, pp. 107-127.
  27. Sukalovaa, V. and Cenigaa, P., Application of The Theory of Constraints Instrument in The Enterprise Distribution System, Procedia Economics and Finance, 2015, Vol. 23, pp. 134-139. https://doi.org/10.1016/S2212-5671(15)00445-1
  28. Umble, M., Umble, E., and Von Deylen, L., Integrating enterprise resources planning and theory of constraints : a case study, Production and Inventory Management Journal, 2001, Vol. 42, No. 2, pp. 43-48.
  29. Wen, Z., Ya-Ming, Z., Jinbo, C., and Kaijun, L., Research on a scheduling mechanism in a complex system based on TOC, Chaos, Solitons & Fractals, 2016, Vol. 89, pp. 335-347. https://doi.org/10.1016/j.chaos.2015.12.017
  30. Wu, H.-H., Lee, A.H., and Tsai, T.-P., A two-level replenishment frequency model for TOC supply chain replenishment systems under capacity constraint, Computers and Industrial Engineering, 2014, Vol. 72, pp. 52-159.
  31. Yok, Y.S. and Kim, B.K., Chassis Module assembly process of the production performance method of Acquisition research, Journal of the Korean Operations Research And Management Society, 2013, pp. 2493-2500.
  32. Yoon, G.G., Kim, T.G., and Lee, D.H., A Study on the Improvement of Plastic Boat Manufacturing Process Using TOC & Statistical Analysis, Journal of Society of Korea Industrial and Systems Engineering, 2016, Vol. 39, No. 1, pp. 130-139. https://doi.org/10.11627/jkise.2016.39.1.130
  33. Yoshida, A. and Park, J.H., Development of an Effective Manufacturing Scheduling System for PCB Manufacturing Line Using Dual DBR Method, Journal of the Korea Academia-Industrial Cooperation Society, 2009, Vol. 10, No. 10, pp. 2935-2944. https://doi.org/10.5762/KAIS.2009.10.10.2935
  34. Yoshida, A. and Park, J.H., Improvement of Lead Time at A PCB Manufacturing Line Using TOC Methodology, Korea Industrial Engineering Association spring joint conference, 2006, pp. 927-932.
  35. Zhou, Z. and O. Rose, A bottleneck detection and dynamic dispatching strategy for semiconductor wafer fabrication facilities, Simulation Conference(WSC), Proceedings of the 2009 Winter, IEEE, 2009.

Cited by

  1. 방탄시험의 효과적 운영을 위한 시료거치 시스템 개발 vol.22, pp.1, 2021, https://doi.org/10.5762/kais.2021.22.1.338