Development of Integrated Cost and Schedule Management System using Work Package Concept for Efficient Project Management

Work package 개념을 활용한 현장의 공정관리와 공사비 통합관리 효율화 방안

  • Kim, Yongpyo (Samsung Construction Company) ;
  • Lee, Yongjun (Department of Civil Engineering, Chungnam National University) ;
  • Lee, Minjae (Department of Civil Engineering, Chungnam University)
  • Received : 2017.06.29
  • Accepted : 2017.08.02
  • Published : 2017.09.30

Abstract

Korean construction industry is facing downtime mood and need more productivity. In order to successfully accomplish the construction project with more productivity, systematic and reasonable schedule management techniques should be developed and utilized. Therefore, in this study, first, a current status of the schedule management in the construction site is identified and the improvements in the schedule management are suggested. And, the effective schedule management technique in the construction site is proposed based on the in-site experience of the researcher. In order to find solutions, survey questionnaires designed to measure the understanding of process management and measure perception of the importance of schedule management. Total twenty nine field engineers who are performing schedule management of construction project at domestic civil engineering construction site were participated in the survey, and In-depth interviews were conducted. Eleven construction sites are inspected. Finally, a simple and effective schedule management technique including from WSB classification to schedule analysis, performance management, and performance improvement is proposed based on the inspection of current status of schedule management in civil engineering construction site.

최근 국내 건설산업은 성장의 시기를 지나 침체기로 접어들고 있으며 경쟁력 향상을 위해 건설사업관리 특히 공정관리의 중요성이 더욱 부각되고 있다. 이러한 상황에 토목 건설업계는 생존을 위한 다양한 공사관리 방안의 연구 및 현장 적용에 부단한 노력을 하고 있으며 많은 성과를 이루고 있으나 아직도 체계적이며 효율적이고 현장 활용도가 높은 공정관리 기법의 정착은 이루어지지 못하고 있다. 이에 본 연구에서는 공사관리의 핵심인 공정관리의 활용에 대해 설문조사방식으로 현장기술자들의 인식 및 이해의 정도를 파악하며 현장에서 실제 사용하고 있는 공정표의 작성수준과 활용 현황을 파악을 위해 방문 조사하여 현재 국내 공정관리 현주소 및 문제점을 파악하였다. 아울러, 기존문헌 및 연구논문의 고찰, 현장에의 적용성을 바탕으로 현장 활용성이 높은 WBS 분류에서부터 work pacckage 도출과 Activty도출, 공정표 작성 및 관리방안을 제안하였다.

Keywords

References

  1. Business Roundtable (1987). "Measuring productivity in construction" A Construction Industry Cost Effectiveness Project Report.
  2. CAK (2015). "Results of IPO (Initial Public Offering) companies performance analysis in the first quarter of 2015"
  3. Choi, J., and Kim, Y (2013). "An Analysis of Core Competency of Construction Field Engineer for Cost Management" Korean Journal of Construction Engineering and Management, KICEM, 14(5), pp. 26-34. https://doi.org/10.6106/KJCEM.2013.14.5.026
  4. Joo, S., Park, M., Lee, H., and Lee, K (2015). "TACT Productivity Management for Finish Works of Residential Buildings using Productivity Achievement Ratio (PAR)" Korean Journal of Construction Engineering and Management, KICEM,, 16(3), pp. 36-45. https://doi.org/10.6106/KJCEM.2015.16.3.036
  5. Kang, I (2007). "CM and construction IT" Munundang.
  6. Kang, J., Lee, D., Park, J., and Lee, M (2012). "A Study on Development of BIM-based Asset Management Model for Maintenance of the Bridge" Korean Journal of Construction Engineering and Management, KICEM, 13(5), pp. 3-11. https://doi.org/10.6106/KJCEM.2012.13.5.003
  7. Kim, J. (2015). "Processing project like Progress Management" Let's Book.
  8. Ko, Y., Cha, H., Shin, D., and Kim, K. (2012). "Selecting Optimum Management Practices according to Project Characteristics for Improving Project Performance" Korean Journal of Construction Engineering and Management, KICEM, 13(1), pp. 3-13. https://doi.org/10.6106/KJCEM.2012.13.1.003
  9. Lee, Y., Lee, H., and Jung, D. (2012). "EVMS Development in Daerim Industrial" Korean Journal of Construction Engineering and Management, KICEM, 13(4), pp. 12-16. https://doi.org/10.6106/KJCEM.2012.13.5.012
  10. Lee, Y., and Lee, M. (2016). "A Study on Estimating of Probability Distribution and Mean Life of Bridge Member for Effective Maintenance" Journal of Construction Engineering and Management, 17(4), pp. 57-65.
  11. Oglesby, C., Parker, H., and Howell, G. (1989). "Productivity improvement in construction" McGraw-Hill, New York, N.Y.
  12. Olli Seppänen, Glenn Ballard and Sakari Pesonen (2010). "The combination of Last Planner System and Location-Based Management System" Lean Construction Journal, pp. 43-54.
  13. Park, H. (2007). "Construction progress management operation practice" Goomibook.
  14. Park, S. (2010). "A Study on the building of Project Management System in Construction Project Using Earned Value Management System" Hanyang University Master Thesis.
  15. P. P. Zouein, and I. D. Tommelein (2001). "Improvement Alegorithm for Limited Space Scheduling" Journal of Construction Engineering and Management, 1 27(2), pp. 116-124. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:2(116)
  16. Rhuta Joshi, Prif. and V. Z. Patil (2015). "Resource Scheduling of Construction Project: Case Study" International Journal of Science and Reserch (IJSR) 4(5), pp. 563-568.
  17. Samoo C.M (2011). "Construction Management Handbook"
  18. Shivani sakre, Prof.Abhijit. and N. Bhirud (2015). "Planning and Scheduling in Construction through Model Approach" International Journal on Recent and Innovation Trend Computing and Communication, 3(5), pp. 3029-3031.
  19. Yoon, B., Lim, C., Yoo, J., and Kim, C. (2008). "The Survey of Time Management Status in the Domestic Construction Site" KICEM Conference 2008, p. 916.
  20. Yoon, Y., Suh, S., Jang, G., and Choi, J. (2013). "Improvement of Cost-Schedule integration based Progress Management through PMIS" Korean Journal of Construction Engineering and Management, KICEM, 14(5), pp. 144-151. https://doi.org/10.6106/KJCEM.2013.14.5.144