A Study on Standard Construction Process Management System for Prediction of Proper Construction Period of Subsea Tunnel

해저터널 적정 공사기간 예측을 위한 표준공정관리 체계 연구

  • Bae, Keunwoo (Department of Construction Management, Hyeon-In PCM)
  • Received : 2017.03.01
  • Accepted : 2017.07.05
  • Published : 2017.07.31

Abstract

As a typical domestic subsea tunnel construction the Gadeok subsea tunnel applying the method of immersed tunnel has been completed and the Boryeong-Taean subsea tunnel is under construction using NATM. The high-speed railway subsea tunnels between the Honam and Jeju are under consideration, and the feasibility of constructing subsea tunnels with Japan and China is also under consideration. However, it is difficult to provide the process plan information for the construction work such as the analysis of the feasibility of the subsea tunnel and the prediction of the proper construction period because there is no case of domestic construction for it applying the shield TBM method. Due to economic and other reasons, government organizations are reluctant to apply the shield TBM, and there is lack of data on the construction process management field using the shield TBM method. Therefore, a standard construction process management system for the subsea tunnel is needed to analyze the feasibility of the subsea tunnel and to predict the proper construction period. By presenting the standard construction process management system of subsea tunnels such as WBS, Network Diagram, and construction period calculation model, I hope to contribute technically and economically to future subsea tunnel projects.

대표적인 국내 해저터널 시공사례로 침매공법을 적용한 가덕 해저터널이 완공되어 운영 중이고, NATM 공법을 적용한 보령~태안간 해저터널이 건설중이다. 호남~제주 간 고속철도 해저터널이 구상중 이고, 일본, 중국과도 해저터널 건설에 대한 타당성이 검토되고 있다. 그러나 Shield TBM 공법을 적용한 해저터널에 대한 국내 시공사례가 없어, 현재의 기술력으로는 장대 해저터널 사업성 분석 및 적정 공사기간 예측 등 공사수행을 위한 공정계획정보 제공이 어렵다. 경제성 등 이유로 정부기관 및 발주기관도 Shield TBM 공법 적용에 소극적이고, Shield TBM 공법을 적용한 공정관리분야 기술적 자료도 부족한 실정이다. 따라서, 장대 해저터널 사업성 분석 및 적정 공사기간 예측하기 위한 표준공정관리체계가 필요하다. 본 연구를 통해 WBS, Network Diagram, 단위 공사기간 산출모델 등 해저터널 표준공정관리 체계를 제시하므로써, 장래 건설되어질 해저터널 사업에 기술적, 경제적으로 기여하고자 한다.

Keywords

References

  1. Baek, S. H., and Moon, H. K. (2003). "Development and Application of the Assessment System of TBM Tunnelling Procedure" Tunnel and underground space, 13(6). pp. 455-464.
  2. Cho, M. S., Woo, D. C., Kim, K. G., and Lee, J. M. (2003). "Applicability Analysis of Empirical Methods for the Calculation of TBM Advance Rate" Tunnel and underground space, 13 pp. 260-269.
  3. Choi, J. J., and Park, H. T. (2014). "Analysis of Monthly Excavation Length Depending on Ground Condition and TBM Diameter" Journal of the Korean Society of Disaster Information, 23 pp. 141-150.
  4. Choi, S. B. (2010). "Undersea Tunnel Cases and Issues and Suggestions on the Honam-Jeju Undersea High-Speed Railway" Korea Logistics Review, 20(5), pp. 243-268.
  5. Design practice tips of the national highway construction work (2016). MOLIT (Ministry of Land, Infrastructure and Transport).
  6. Jeong, W. T. (2014). "Study on the Improving drilling rate by analyzing in Korea TBM construction site" Kyonggi Univ., pp. 18-37.
  7. Kim, B. S., and Chun, J. K. (2005). "A Study on Estimation Model of Construction Duration for Public Construction" Korean Journal of Construction Engineering and Management, KICEM, 6(6), pp. 142-151.
  8. Kim, K. C. (2009). "Sheild TBM Design and Construction Case on Han River passage section of Bundangline" Korea Rail Network Authority, Korea railway technology, 27, pp. 56-62.
  9. Lee, J. W. (2009). "A study of relevant model of information management system based on business process for embodying BPM on construction company" Korean Journal of Construction Engineering and Management, KICEM, 10(6), pp. 13-27.
  10. Lee, S. W., and Woo, S. K. (2008). "Productivity Improvement by Application of Simulation based Tunneling Operation Planning Model - focused on NATM" Korean Journal of Construction Engineering and Management, KICEM, 9(5), pp. 127-136.
  11. Park, H. T. (2012). "Analysis of Standard Cost and the Construction Period Applied TBM Excavation Method" Journal of the Korean Society of Disaster Information, 18, pp. 319-327.
  12. Park, H. T., and Lee Y. k. (2013). "Analysis of Standard Construction by TBM Diameter Through the Rock Scenario Models in the Field" Journal of the Korean Society of Disaster Information, 9(2). pp. 195-205.
  13. Shin, J. Y. (2009). "Korea Rail Network Authority, Successful penetration of tunnel in Han river for the first time in Korea" Press Relsease of the Korea Rail Network Authority, pp. 1-3.
  14. Choi, S. B., Lee, S. D., Kim, H. W., and Jeon, S. K. (2014). "Review of Subaqueous Tunneling Case Histories" Tunnel and underground space, 24(2), pp. 120-130. https://doi.org/10.7474/TUS.2014.24.2.120
  15. MOLIT, KICT (2017). "2017 Standard of construction estimate" MOLIT (Ministry of Land, Infrastructure and Transport), KICT (Korea Institute of Civil Engineering and Building Technology), pp. 268-269.