A Study on the Investigation into Obstacles in Construction Budget Estimating

건설기업 실행예산 편성업무의 애로요인 분석에 관한 연구

  • Koo, Kyo Youn (Department of Architecture, Graduate School, Sejong University) ;
  • Kim, Han Soo (Department of Architecture, Sejong University)
  • Received : 2016.03.04
  • Accepted : 2016.04.11
  • Published : 2016.05.31

Abstract

Under the circumstances where the profitability has become a more critical issue for general contractors, the objective of the study is to identify and discuss obstacles and their key characteristics in the construction budget estimating. Through the questionnaire survey and interviews with experienced estimators of general contractors, the study identified 18 obstacles by 6 groups. It discussed that although various obstacles exist, there are key obstacles to which general contractors should pay attention for the realistic construction budget estimating. In particular, improving subcontractors' estimating competency and incubating estimating experts are identified as the key issues to overcome obstacles in the construction budget estimating.

국내 건설기업들의 수익성 악화로 인한 내실 경영이 중요한 화두가 되고 있는 현 시점에서 본 연구는 실행예산 편성 업무에서 나타나는 애로요인을 도출하고 이들 애로요인에서 나타나는 주요 특징과 시사점을 분석하기 위한 목적으로 수행되었다. 종합건설사의 견적과 공무의 경험이 있는 전문가들을 대상으로 설문조사와 인터뷰조사를 통하여 실행예산 편성업무의 6개 애로요인군(群)과 18개 애로요인에 대하여 분석을 실시하였다. 그 결과는 실행 편성 업무에서 다양한 애로요인이 존재하지만 각 애로요인에는 경중이 있으며 우선적으로 주목하고 대비할 애로요인이 존재하는 것으로 나타났다. 또한 실행 예산 편성업무에서 나타나는 어려움을 최소화하기 위해 해결해야 할 가장 중요한 현안은 협력업체의 견적능력 역량 강화와 견적전문가 양성 및 안정적인 운영인 것으로 나타났다.

Keywords

References

  1. An, S. H., Suk, S. J. and Lee, M. H. (2011). "Weighting of Key Factors Influencing the Cost Budgeting in Building Construction Projects." Journal of the Architectural Institute of Korea Sturcture & Construction, AIK, 27(5) pp. 119-126.
  2. Ahn, Y. K. (2014). "Cost Overrun 142%", Kyeonggiilbo, (April. 19, 2015).
  3. Choi, B. J., Park, J. M., Kwak, J. M., Choi, S. W., and Kim O. K. (2009). "Patterns and Trends in Cost Control Practice of Korean Ceneral Contractors." Proceedings of KICEM Annual Conference, KICEM, 9, pp. 231-236.
  4. Choi, E. J., (2015). "Last year, the construction industry growth, reduced profitability, stability improvements." The Journal of Construction & Economy Reserch Institude of Korea, CERIK, pp. 33-34.
  5. Choi, M. S., and Kim, Y. D., (2013). "A Study on the Analysis and Strategies for Enhancing the Lowest Bidding." The Focuse of Construction Issue, CERIK, pp. 4-6.
  6. Golden. B., and Wasil, E. A (2003). "Celebrating 25 years of AHP based decision making." Computers & Operations Research, Pergamon, 30(10), pp. 1419-1420. https://doi.org/10.1016/S0305-0548(02)00184-3
  7. Joe, G. T. (2003). Decision Making for Leaders, DongHyun Publisher, 1st ed. Seoul, pp. 50-75.
  8. Jung, Y. S. and Joo, M. H. (2011). "Patterns and Trends in Cost Control Practice of Korean General Contractors." Korean Journal of Construction Engineering and management, KICEM, 12(4), pp. 79-87. https://doi.org/10.6106/KJCEM.2011.12.4.79
  9. Kang, M. S. (2010). "A Study of Developing Criteria for Evaluating Rural Tourism Village leader's Managerial Abilities." MS Thesis, Sejong University, Seoul.
  10. Kim, D. H., and Kim, H. .S. (2011). "Identification of Core Competencies." Korean Journal of Construction Engineering and management, KICEM, 121(6), pp. 93-100.
  11. Kim, J H., and Kim, H. S. (2013). "A Study on the Investigation into Obstacles in Overseas CM Projects." Korean Journal of Construction Engineering and management, KICEM, 14(5), pp. 113-121. https://doi.org/10.6106/KJCEM.2013.14.5.113
  12. Lai, Y. Y., Wang, W. C., and Wang, H. H. (2007). "AHP-and simulation-based budget determination procedure for public construction projects." Automaition in Construction, Elsevier, 17(5), pp. 623-632.
  13. Lee, M. H. (2010). "A Study to Establish Measures to Manage costs through an Analysis of Factors that Affect a construction projects of a Construction Work." MS Thesis, Daegu University, Daegu.
  14. Leung, M. Y., Skitmore, M., and Chan, Y. S. (2007). "Subjective and objective stress in construction cost estimation." Construction Management and Economics, Tayler & Francis Group, 25(10), pp. 1063-1075. https://doi.org/10.1080/01446190701573296
  15. Momon, A. H., Abdul Rahman, I., Abdullah, M., and Azis, A. (2010). "Factors Affection Construction cost in Mara Large Construction Project: Perspective of Project management consultant." International Journal of Sustainable Construction Engineering and Technology, UTHM, 1(2), pp. 42-54.
  16. Moon, J. Y., Jung, Y. S., and Kim, Y. S. (2000). "Factor s for Improving Construction Cost Control on Job Sites." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 137, pp. 77-83.
  17. Park, S. W. (2013). "A study on problems and improvement of project financing : focused on PFV (project financing vehicle).", MS Thesis, Chung-Ang University, Seoul.
  18. Seo, J. S. (2009). "A study on the Estimate System for cost control of construction industry.", MS Thesis, Hanbat University, Seoul.
  19. Shin, C. K. and Lee, S. (2008). "A Rational Maintenance of Cut Slopes Analytic Hierarchy Process." A doctora l Thesis, University of Seoul, Seoul.
  20. Yeon, G. H. (2003). "A Study on Job Site of Cost Management and Effective Method for Construction Indestry." Journal of the Korean Association of Tax and Accounting, KATA, 12 pp. 117-144.
  21. Yoon, G. C., and Kim. H. S. (2003). "Systematization of Core Knowledge for Construction Project Budget." MS Thesis, Sejong University, Seoul.