Daily Reporting System using Digital Pen at Construction Site

디지털펜 기반의 건설현장 작업일보시스템 개발

  • Shin, Yoonseok (Department of Architectural Engineering, Kyonggi University) ;
  • Kim, Daewon (Department of Architectural Engineering, Kyonggi University) ;
  • Kim, Tae-Yong (Department of Plant Architectural Engineering, Kyonggi University) ;
  • Kim, Gwang-Hee (Department of Architectural Engineering, Kyonggi University)
  • Received : 2015.12.08
  • Accepted : 2016.03.29
  • Published : 2016.04.20

Abstract

The daily report includes the most detailed information and various daily planning and performance data recorded at a site, and includes work types, the number of workers, and the equipment and materials used. However, in the daily reporting process, some information can be omitted or distorted or even made redundant due to there being several steps of manual input. For this reason, the daily report is utilized for a simple report rather than for an appropriate purpose. Thus, to resolve the issues of the existing daily report system mentioned above, a daily report system using a digital pen was developed and then applied to an actual construction site to verify its applicability. As a result, it was found that 96.610% recognition accuracy of handwritten letters could be achieved. In addition, it was no longer necessary to enter the same information multiple times and no additional training or education for using a mobile device was needed. The digital pen-based daily report program developed in this study is expected to contribute to an improvement of information management efficiency and site document management work by addressing the problems of the existing report system.

작업일보는 일일 단위로 계획과 실적이 기록되는 문서로 작업내용, 출력인원, 장비 및 자재 현황 등 다양한 정보를 포함한다. 하지만 작업일보가 여러 단계를 거쳐 수기 작성되는 과정에서 정보의 누락 및 왜곡될 수 있고 업무의 중복 문제가 발생하여 단순 보고에 이용되고 있다. 따라서 본 연구에서는 기존의 작업일보시스템의 문제를 해결할 수 있는 디지털펜 기반의 작업일보시스템을 개발하고 그 적용성 평가를 위해서 실제 건설 현장에 적용해보았다. 그 결과 높은 문자 인식 정확도(94.610%)를 보여주었다. 그리고 정보를 입력하는 추가 업무가 제거되고 휴대 및 이동이 편리하며 사용을 위한 별도의 교육이 필요 없는 장점이 있었다. 본 연구에서 개발한 시스템은 현행 작업일보시스템의 문제를 해결하여 건설현장 문서업무 및 정보관리 효율 개선에 기여할 수 있을 것으로 기대된다.

Keywords

References

  1. Kang WY, Chin SY, Kim YS. Reengineering daily reporting process by using task generator and mobile technology. Korea Journal of Construction Engineering and Management. 2005 Jun;6(3):100-10.
  2. Yoon SW, Kim BK, Choi JM, Kwon SW. A prototype BIM server based viewer for cloud computing BIM services. Journal of the Korean Society of Civil Engineers. 2013 Jul;33(4):1719-30. https://doi.org/10.12652/Ksce.2013.33.4.1719
  3. Jeong MG. A measurement of one day workload using digital pen technology [mater's thesis]. [Suwon (Korea)]: Kyonggi University; 2015. 88 p.
  4. Na KS. A development of tact management system using a daily report information [master's thesis]. [Suwon (Korea)]: Kyunghee University; 2003. 51 p.
  5. Son BK, Kim HJ. A framework for digitalizing handwritten document using digital pen and handwriting recognition technology. 2011 Mar;12(3):1417-26.
  6. Park GT, Jung YC, Nam HJ, Son BK, Kim TH, Kim GH. Construciton information process using digital pen : focused on defect management system. Proceedings of the Korean Institute of Building Construction conference; 2010 May 14; Seoul, Korea. Seoul (Korea): The Korean Institute of Building Construction; 2010. p. 135-8.
  7. Chin S, Kim JJ, Liu YL. A development of Multimedia Construction Site Information System using Information Technology. 1999 Apr:15(4):133-40.
  8. Son BK. A study for improving building construction management productivity using digital pen system. Journal of the Korea Entertainment Industry Association. 2010 Sep;4(3):23-33.
  9. Kim GH, Shin YS, Kim TY, Lee YD. Case study of the application of a digital pen to a defect checklist of an apartment housing project. Applied Mechanics and Materials. 2013 Feb;303-306(2013):2303-6. https://doi.org/10.4028/www.scientific.net/AMM.303-306.2303
  10. Kim SK, Na KS, Kim TH, Yu JH, Lee HS, Kim CD. A study on the tact management using a daily report information. Korea Journal of Construction Engineering and Management. 2003 Dec;4(4):1-8.
  11. Chin SY, Kang WY, Kim YS. A development of task generator through an analysis of task location information structure. Korea Journal of Construction Engineering and Management. 2004 Apr;5(2):64-71.
  12. Cho HH, Kang KI. Development of project management system based on daily report for historical data acquisition and storage. Journal of the Architectural Institute of Korea. 2001 Nov;17(11):123-30.
  13. Shim JK, Yi HI, Kim JJ. A study on the possibility of BIM(Building Information Modeling) application of construction management. Journal of The Korean Digital Architecture Interior Association. 2010 Aug;10(2):49-60.